325 N FICKETT ST 90033

Certificate Information: 325 N FICKETT ST 90033

Application / Permit
19010-10000-00794
Plan Check / Job No.
B19LA03824
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY TOC AFFORDABLE HOUSING APARTMENT BLDG. (21 AFFORDABLE UNITS AND 1 MANAGER'S UNIT)
Permit Issued
Issued on 1/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2019 APPLICANT
Green Plans Picked Up 3/7/2019 APPLICANT
Assigned to Plan Check Engineer 3/8/2019 JOE VO
Disabled Access Plans Picked Up 3/13/2019 APPLICANT
Corrections Issued 3/18/2019 JOE VO
Quality Review Completed 3/18/2019 GARO TELMI
Building Plans Picked Up 3/19/2019 APPLICANT
Applicant returned to address corrections 10/16/2019 JOE VO
Plan Check Approved 12/12/2019 JOE VO
Issued 1/13/2020 LADBS
CofO in Progress 3/31/2023 RAFAEL ESPINOZA
Permit Finaled 3/31/2023 ERNESTO CORRAL
CofO Issued 3/31/2023 ERNESTO CORRAL
Permit Finaled 3/31/2023 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 5/20/2019 ELENA LOPEZ
Permit Cleared 5/20/2019 ELENA LOPEZ
Address approval Cleared 8/8/2019 JOSE CRUZ RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 8/8/2019 JOSE CRUZ RODRIGUEZ
Clean Up Green Up Cleared 9/20/2019 DIANA JIMENEZ
Fire Marshall Fire Life Safety Cleared 9/20/2019 OSCAR SALGADO JR
Frnt yard landscape/Water mgmt Cleared 9/20/2019 DIANA JIMENEZ
Hydrant and Access approval Cleared 9/20/2019 GEORGE SUCHAND
Opn space landscape/Water mgmt Cleared 9/20/2019 DIANA JIMENEZ
ZA Case Cleared 9/20/2019 DIANA JIMENEZ
DAS Clearance Cleared 9/23/2019 ELIZABETH TOMS
Green Code Cleared 10/4/2019 COLIN LOREDO
Low Impact Development Cleared 10/16/2019 ANDRES COVARRUBIAS
Miscellaneous Cleared 10/16/2019 JOE VO
Roof/Waste drainage to street Cleared 10/16/2019 ELAINE LEI
DCP conditions approval Cleared 11/21/2019 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 11/21/2019 NICHOLAS KAWAZOE
Sewer availability Cleared 12/11/2019 JEANIE LAM

Contact Information

Contractor Bancomer Construction & Development; Lic. No.: 783429-B 2168 S ATLANTIC BL PMB 206      MONTEREY PARK, CA 91754
Engineer Afsharhasani,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/7/2020 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/30/2020 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 6/30/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 6/30/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 6/30/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/1/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/8/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/9/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 10/15/2020 Approved RAFAEL ESPINOZA
METHANE-Rough 10/15/2020 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/15/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/15/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/7/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/7/2021 Partial Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 4/12/2021 Approved RAFAEL ESPINOZA
Pre-Inspection 9/1/2021 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/11/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/11/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/15/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/15/2022 Partial Inspection RAFAEL ESPINOZA
Wood Frame 2/23/2022 Partial Approval RAFAEL ESPINOZA
Insulation 3/9/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/21/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/25/2022 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/5/2022 Partial Inspection RAFAEL ESPINOZA
Final 1/26/2023 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 1/26/2023 Approved RAFAEL ESPINOZA
Green Building Final 1/26/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 1/26/2023 Approved RAFAEL ESPINOZA
METHANE-Subgrade 1/26/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 1/26/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/26/2023 Approved RAFAEL ESPINOZA
Wood Frame 1/26/2023 Approved RAFAEL ESPINOZA
Final 2/8/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 2/8/2023 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 2/8/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 3/1/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 3/1/2023 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 3/1/2023 Approved RAFAEL ESPINOZA
Final 3/31/2023 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 3/31/2023 Approved RAFAEL ESPINOZA