325 N FICKETT ST 90033
Certificate Information: 325 N FICKETT ST 90033
- Application / Permit
- 19010-10000-00794
- Plan Check / Job No.
- B19LA03824
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3-STORY TOC AFFORDABLE HOUSING APARTMENT BLDG. (21 AFFORDABLE UNITS AND 1 MANAGER'S UNIT)
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2019 | APPLICANT |
| Green Plans Picked Up | 3/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2019 | JOE VO |
| Disabled Access Plans Picked Up | 3/13/2019 | APPLICANT |
| Corrections Issued | 3/18/2019 | JOE VO |
| Quality Review Completed | 3/18/2019 | GARO TELMI |
| Building Plans Picked Up | 3/19/2019 | APPLICANT |
| Applicant returned to address corrections | 10/16/2019 | JOE VO |
| Plan Check Approved | 12/12/2019 | JOE VO |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 3/31/2023 | RAFAEL ESPINOZA |
| Permit Finaled | 3/31/2023 | ERNESTO CORRAL |
| CofO Issued | 3/31/2023 | ERNESTO CORRAL |
| Permit Finaled | 3/31/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 5/20/2019 | ELENA LOPEZ |
| Permit | Cleared | 5/20/2019 | ELENA LOPEZ |
| Address approval | Cleared | 8/8/2019 | JOSE CRUZ RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2019 | JOSE CRUZ RODRIGUEZ |
| Clean Up Green Up | Cleared | 9/20/2019 | DIANA JIMENEZ |
| Fire Marshall Fire Life Safety | Cleared | 9/20/2019 | OSCAR SALGADO JR |
| Frnt yard landscape/Water mgmt | Cleared | 9/20/2019 | DIANA JIMENEZ |
| Hydrant and Access approval | Cleared | 9/20/2019 | GEORGE SUCHAND |
| Opn space landscape/Water mgmt | Cleared | 9/20/2019 | DIANA JIMENEZ |
| ZA Case | Cleared | 9/20/2019 | DIANA JIMENEZ |
| DAS Clearance | Cleared | 9/23/2019 | ELIZABETH TOMS |
| Green Code | Cleared | 10/4/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 10/16/2019 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 10/16/2019 | JOE VO |
| Roof/Waste drainage to street | Cleared | 10/16/2019 | ELAINE LEI |
| DCP conditions approval | Cleared | 11/21/2019 | NICHOLAS KAWAZOE |
| Density Bonus 12.22.A.31 | Cleared | 11/21/2019 | NICHOLAS KAWAZOE |
| Sewer availability | Cleared | 12/11/2019 | JEANIE LAM |
Contact Information
| Contractor | Bancomer Construction & Development; Lic. No.: 783429-B | 2168 S ATLANTIC BL PMB 206 MONTEREY PARK, CA 91754 |
| Engineer | Afsharhasani,, Rouzbeh; Lic. No.: C87032 | 1133 CAMELBACK ST 9038 NEWPORT BEACH, CA 92658 |
| Engineer | Bozorgnia,, Behrouz; Lic. No.: C79581 | 1557 WESTWOOD BLVD 145 LOS ANGELES, CA 90024 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/7/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/30/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 6/30/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Barrier | 6/30/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Subgrade | 6/30/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 10/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2020 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 10/15/2020 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 10/15/2020 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 10/15/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 10/15/2020 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/7/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 4/7/2021 | Partial Inspection | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 4/12/2021 | Approved | RAFAEL ESPINOZA |
| Pre-Inspection | 9/1/2021 | Partial Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 2/11/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 2/11/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 2/15/2022 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 2/15/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Wood Frame | 2/23/2022 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 3/9/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/21/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/25/2022 | Partial Inspection | ERNESTO CORRAL |
| Pre-Inspection | 12/5/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 1/26/2023 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 1/26/2023 | Approved | RAFAEL ESPINOZA |
| Green Building Final | 1/26/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Barrier | 1/26/2023 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 1/26/2023 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 1/26/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 1/26/2023 | Approved | RAFAEL ESPINOZA |
| Final | 2/8/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 2/8/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Smoke Detectors | 2/8/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 3/1/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 3/1/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Smoke Detectors | 3/1/2023 | Approved | RAFAEL ESPINOZA |
| Final | 3/31/2023 | OK to Issue CofO | RAFAEL ESPINOZA |
| Green Building Final | 3/31/2023 | Approved | RAFAEL ESPINOZA |