5717 W AIRDROME ST 90019

Certificate Information: 5717 W AIRDROME ST 90019

Application / Permit
19010-10000-00781
Plan Check / Job No.
B19LA03742
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT (1116.5 SF) , 2-BEDROOMS/2-BATHROOMS, PER AB 494 AND SB 229
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 6/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2019 APPLICANT
Assigned to Plan Check Engineer 3/14/2019 SERGIO GUTIERREZ
Corrections Issued 4/5/2019 SERGIO GUTIERREZ
Quality Review Completed 4/9/2019 JOSE RODRIGUEZ
Building Plans Picked Up 4/25/2019 APPLICANT
Green Plans Picked Up 12/29/2020 APPLICANT
Plan Check Approved 2/9/2021 SERGIO GUTIERREZ
Issued 7/1/2021 APPLICANT
CofO in Progress 5/23/2022 JOSE AVILA
Permit Finaled 6/14/2022 DEROLD HAUFF
Permit Finaled 6/14/2022 DEROLD HAUFF
CofO Issued 6/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/20/2019 JEANETTE VONG
Construction near power lines Cleared 7/9/2019 RIDWAN HARDY
Roof/Waste drainage to street Cleared 10/9/2020 ELENA LOPEZ
Low Impact Development Cleared 12/8/2020 YVAINNE GALSIM
Green Code Cleared 12/28/2020 SERGIO GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 1/7/2021 JEANIE LAM
Sewer availability Cleared 1/7/2021 JEANIE LAM
Hydrant and Access approval Cleared 1/14/2021 MATTHEW CRAIG

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Wong,, Jim Chu Man; Lic. No.: C69393 PO BOX 373      GLENDORA, CA 91740

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/9/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/9/2021 Approved STUART CHAPMAN
METHANE-Barrier 7/9/2021 Approved STUART CHAPMAN
METHANE-Subgrade 7/9/2021 Approved STUART CHAPMAN
Underground Mechanical 7/26/2021 Approved JUSTIN HAWLEY
Insulation 8/4/2021 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/1/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/1/2021 Approved STUART CHAPMAN
Green Building Rough 10/1/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/1/2021 Approved STUART CHAPMAN
METHANE-Rough 10/1/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/1/2021 Approved STUART CHAPMAN
Posting Pre-Inspection 10/1/2021 Not Ready for Inspection STUART CHAPMAN
Shower Pan 10/1/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/1/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/14/2021 Partial Approval JUSTIN HAWLEY
Green Building Rough 10/14/2021 Not Ready for Inspection JUSTIN HAWLEY
Wood Frame 10/14/2021 Approved JUSTIN HAWLEY
Insulation 10/29/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/29/2021 Partial Approval JUSTIN HAWLEY
Drywall Nailing 11/10/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 11/22/2021 Approved JOSE AVILA
Underground Mechanical 2/10/2022 Approved JOSE AVILA
ELECTRICAL-Final 2/14/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 2/23/2022 Approved JOSE AVILA
ELECTRICAL-Final 2/23/2022 Approved JOSE AVILA
Final 2/23/2022 Corrections Issued JOSE AVILA
Green Building Final 2/23/2022 Corrections Issued JOSE AVILA
Green Building Rough 2/23/2022 Approved JOSE AVILA
HVAC-Final 2/23/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 2/23/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Approved JOSE AVILA
Service/Power Release 2/23/2022 Approved JOSE AVILA
Smoke Detectors 2/23/2022 Approved JOSE AVILA
Final 4/12/2022 Corrections Issued JOSE AVILA
Green Building Final 4/12/2022 Approved JOSE AVILA
ELECTRICAL-Final 4/20/2022 Approved JOSE AVILA
Final 4/20/2022 Corrections Issued JOSE AVILA
HVAC-Final 4/20/2022 Approved JOSE AVILA
PLUMBING-Final 4/20/2022 Approved JOSE AVILA
Final 5/20/2022 OK to Issue CofO JOSE AVILA