3630 S OVERLAND AVE 90034

Certificate Information: 3630 S OVERLAND AVE 90034

Application / Permit
19010-10000-00780
Plan Check / Job No.
B19LA03733
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
74 UNIT, 7 STORY APARTMENT BUILDING WITH GROUND FLOOR COMMERCIAL AND 3 LEVELS SUBTERRANEAN PARKING GARAGE. 5 LEVELS OF TYPE IIIA CONSTRUCTION OVER TWO LEVELS OF TYPE 1A CONTRUCTION. NFPA SPRINKLERS THROUGHOUT (TOC TIER 2) 8 UNITS TO BE SET ASIDE FOR EXTREMELY LOW INCOME
Permit Issued
Issued on 3/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2019 APPLICANT
Assigned to Plan Check Engineer 3/7/2019 MICHAEL PEREZ
Green Plans Picked Up 3/18/2019 APPLICANT
Corrections Issued 3/27/2019 MICHAEL PEREZ
Quality Review Completed 3/29/2019 QUAN NGHIEM
Building Plans Picked Up 4/16/2019 APPLICANT
Disabled Access Plans Picked Up 5/6/2019 APPLICANT
Plan Check Approved 3/3/2020 MICHAEL PEREZ
Issued 3/3/2020 LADBS
TCO Issued (Expire Date: 01-13-2024) 7/17/2023 DAVID TSAU
TCO Issued (Expire Date: 07-06-2024) 1/8/2024 DAVID TSAU
TCO Issued (Expire Date: 12-29-2024) 7/2/2024 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 06-04-2025) 12/6/2024 DAVID TSAU
CofO in Progress 5/7/2025 DANIEL VARNUM
No Progress 6/2/2025 PAUL DAVIDSON
CofO in Progress 6/2/2025 PAUL DAVIDSON
TCO Issued (Expire Date: 11-29-2025) 6/2/2025 HENRY BAGHDASSARIAN
Permit Finaled 9/24/2025 DAVID TSAU
CofO Issued 9/24/2025 DAVID TSAU
Permit Finaled 9/24/2025 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 4/24/2019 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 4/24/2019 STEVEN JIN
Permit Cleared 4/24/2019 STEVEN JIN
CPC Cleared 4/26/2019 ANNA VAN
Miscellaneous Cleared 4/26/2019 ANNA VAN
Miscellaneous Cleared 4/26/2019 ANNA VAN
Prkng lot landscape/Water mgmt Cleared 4/26/2019 ANNA VAN
Site Plan review Cleared 4/26/2019 ANNA VAN
Construction near power lines Cleared 5/6/2019 RIDWAN HARDY
Sewer availability Cleared 5/6/2019 KRISTEN LY
Building over 3-story or 36-ft Cleared 7/5/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/5/2019 CALOSHA APPROVED
Hydrant and Access approval Cleared 8/14/2019 GILBERT URREA
Green Code Cleared 9/6/2019 COLIN LOREDO
Density Bonus 12.22.A.31 Cleared 9/25/2019 KENNETH LE
Highway dedication Cleared 10/31/2019 NIKTA MOUSAVI
Low Impact Development Cleared 11/8/2019 MARTIN FRAGOSO
Opn space landscape/Water mgmt Cleared 11/15/2019 JOSE ROMERO-NAVARRO
Trees in Parkway Cleared 11/19/2019 ADRIAN SANCHEZ
DAS Clearance Cleared 11/20/2019 MICHAEL PEREZ
Bicycle Parking Cleared 12/2/2019 OSCAR GUTIERREZ
Fire Marshall Fire Life Safety Cleared 12/17/2019 MENOA AGHAJANI
Grading Pre-Inspection Cleared 12/19/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 12/19/2019 CELINA MORENO
Work Adjacent to Public Way Cleared 12/19/2019 ANTHONY MAINEZ
Specific Plan Cleared 2/11/2020 PEDRO AYALA
Hold Cleared 3/26/2025 CARMEN MERAZ

Contact Information

Contractor Integrare Group Llc; Lic. No.: 1063352-B 12421 VENICE BLVD      LOS ANGELES, CA 90066
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Landscape Architect Chee,, Tina Mae Lan; Lic. No.: LA6159 2435 KENILWORTH AVE      LOS ANGELES, CA 90039

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/10/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 11/13/2020 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 11/13/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 11/13/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 11/16/2020 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 11/18/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 12/3/2020 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 12/16/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 1/4/2021 Approved NICK LAROCCA
Green Building Rough 1/4/2021 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 1/4/2021 Partial Approval NICK LAROCCA
Verify Sprinkler Sign Off 1/4/2021 Not Ready for Inspection NICK LAROCCA
Deputy Reinf. Concrete 1/7/2021 Approved JEFF BYTHEWAY
Green Building Rough 1/15/2021 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 1/15/2021 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 1/15/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/19/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 1/19/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/20/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/21/2021 Approved JEFF BYTHEWAY
Green Building Rough 2/19/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 2/19/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/24/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 2/24/2021 Approved JEFF BYTHEWAY
Green Building Rough 2/24/2021 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 2/24/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/25/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 2/25/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 2/25/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/26/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 2/26/2021 Approved JEFF BYTHEWAY
Green Building Rough 3/3/2021 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 3/3/2021 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 3/5/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 3/8/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 3/9/2021 Approved DERRICK SPENCER
Reinforced Concrete Frame 4/1/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/6/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/12/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 4/12/2021 Approved JEFF BYTHEWAY
Green Building Rough 4/12/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 4/12/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 4/19/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 4/19/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 4/20/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/21/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 4/21/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 4/22/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 5/7/2021 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/24/2021 Partial Inspection JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/27/2021 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/28/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 6/14/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 6/14/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/16/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/16/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/17/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/7/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 7/22/2021 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 7/23/2021 Partial Inspection JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 8/6/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/6/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/10/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 8/10/2021 Approved JEFF BYTHEWAY
Pre-Inspection 8/23/2021 Partial Inspection JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 9/7/2021 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 9/8/2021 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 9/8/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/10/2021 Approved DERRICK SPENCER
Pre-Inspection 9/16/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 9/23/2021 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 9/28/2021 Approved JEFF BYTHEWAY
Deputy Wood Construction 9/29/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 10/8/2021 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 10/14/2021 Conditional Approval NICK LAROCCA
Reinforced Concrete Frame 10/14/2021 Partial Approval NICK LAROCCA
Deputy Steel/Welding 10/18/2021 Approved JEFF BYTHEWAY
Deputy Steel/Welding 10/19/2021 Approved JEFF BYTHEWAY
Deputy Steel/Welding 10/20/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 10/26/2021 Corrections Issued JEFF BYTHEWAY
Wood Frame 11/5/2021 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 11/10/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 11/10/2021 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 12/1/2021 Approved JEFF BYTHEWAY
Wood Frame 12/7/2021 Partial Inspection JEFF BYTHEWAY
Wood Frame 12/10/2021 Partial Inspection JEFF BYTHEWAY
Light Gage Steel Frame 12/14/2021 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 12/15/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 12/17/2021 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 1/7/2022 Partial Inspection JEFF BYTHEWAY
Wood Frame 1/12/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 1/20/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 1/24/2022 Partial Inspection JEFF BYTHEWAY
Wood Frame 1/28/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 2/1/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 2/4/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 2/9/2022 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 2/10/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 2/14/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 2/23/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 2/24/2022 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 3/2/2022 Approved JEFF BYTHEWAY
Drywall Nailing 3/2/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 3/9/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 3/11/2022 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 3/16/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 3/23/2022 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 3/25/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 3/29/2022 Partial Approval JEFF BYTHEWAY
Insulation 4/27/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 4/28/2022 Approved JEFF BYTHEWAY
Insulation 5/3/2022 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 5/4/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 5/5/2022 Approved JEFF BYTHEWAY
Insulation 5/6/2022 Partial Approval JEFF BYTHEWAY
Insulation 5/17/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 5/17/2022 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 5/20/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 5/23/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 5/24/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Steel/Welding 5/31/2022 Approved NICK LAROCCA
Deputy Steel/Welding 5/31/2022 Conditional Approval DAVID TSAU
Drywall Nailing 5/31/2022 Not Ready for Inspection DAVID TSAU
Light Gage Steel Frame 5/31/2022 Partial Approval DAVID TSAU
Deputy Steel/Welding 6/1/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 6/2/2022 Approved JEFF BYTHEWAY
Drywall Nailing 6/2/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 6/3/2022 Approved JEFF BYTHEWAY
Special/Order Compliance 6/3/2022 Approved JEFF BYTHEWAY
Wood Frame 6/3/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 6/6/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/7/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/8/2022 Approved JEFF BYTHEWAY
Drywall Nailing 6/8/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 6/9/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/10/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/13/2022 Approved JEFF BYTHEWAY
Wood Frame 6/13/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 6/14/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/15/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/16/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/17/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/22/2022 Approved JEFF BYTHEWAY
Drywall Nailing 6/22/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 6/23/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 6/24/2022 Approved JEFF BYTHEWAY
Light Gage Steel Frame 6/24/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 6/29/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 7/6/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 7/8/2022 Not Ready for Inspection DAVID TSAU
Drywall Nailing 7/12/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 7/13/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 7/18/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 7/19/2022 Approved SORIN CIRSTOIU
Interior/Exterior Lathing 7/20/2022 Partial Approval NICK LAROCCA
Deputy Steel/Welding 7/21/2022 Conditional Approval DERRICK SPENCER
Drywall Nailing 7/21/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 7/25/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 7/26/2022 Approved JEFF BYTHEWAY
Light Gage Steel Frame 7/29/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/12/2022 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 8/15/2022 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 8/18/2022 Partial Approval DERRICK SPENCER
Wood Frame 8/23/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 8/25/2022 Approved JEFF BYTHEWAY
Interior/Exterior Lathing 8/29/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 9/7/2022 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 9/7/2022 Approved JEFF BYTHEWAY
Interior/Exterior Lathing 9/8/2022 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 9/8/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/12/2022 Partial Approval JEFF BYTHEWAY
Masonry Wall/Backfill 9/14/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/19/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 9/21/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 9/22/2022 Conditional Approval DERRICK SPENCER
Reinforced Concrete Frame 9/27/2022 Partial Approval DERRICK SPENCER
Deputy Shotcrete 9/30/2022 Approved DERRICK SPENCER
Special/Order Compliance 10/17/2022 Approved DERRICK SPENCER
Reinforced Concrete Frame 10/21/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 11/2/2022 Conditional Approval JEFF BYTHEWAY
Reinforced Concrete Frame 11/2/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/9/2022 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 11/23/2022 Approved DERRICK SPENCER
Structural Steel Frame 11/28/2022 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 12/2/2022 Partial Approval DERRICK SPENCER
Pre-Inspection 12/6/2022 Approved DERRICK SPENCER
Drywall Nailing 12/8/2022 Partial Approval DERRICK SPENCER
Special/Order Compliance 12/29/2022 Approved DERRICK SPENCER
Drywall Nailing 1/3/2023 Approved DERRICK SPENCER
Final 1/3/2023 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 1/3/2023 Approved DERRICK SPENCER
Green Building Final 1/3/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 1/3/2023 Approved DERRICK SPENCER
Reinforced Masonry Frame 1/3/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved DERRICK SPENCER
Smoke Detectors 1/3/2023 Approved DERRICK SPENCER
Structural Steel Frame 1/3/2023 Approved DERRICK SPENCER
Wood Frame 1/3/2023 Approved DERRICK SPENCER
Pre-Inspection 1/6/2023 Approved DERRICK SPENCER
Special/Order Compliance 1/8/2023 Conditional Approval DERRICK SPENCER
Interior/Exterior Lathing 1/20/2023 Partial Approval DERRICK SPENCER
Final 3/16/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 3/16/2023 Not Ready for Inspection DERRICK SPENCER
Final 5/19/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 5/19/2023 Not Ready for Inspection DERRICK SPENCER
Final 5/30/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 5/30/2023 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 6/1/2023 Approved DERRICK SPENCER
Final 6/5/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/5/2023 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 6/6/2023 Approved DERRICK SPENCER
Final 6/7/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/7/2023 Partial Approval DERRICK SPENCER
Final 6/15/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/15/2023 Not Ready for Inspection DERRICK SPENCER
Final 6/22/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 6/22/2023 Approved DERRICK SPENCER
Special/Order Compliance 6/23/2023 Approved DERRICK SPENCER
Final 6/27/2023 Not Ready for Inspection DERRICK SPENCER
Final 7/6/2023 Not Ready for Inspection DERRICK SPENCER
Final 10/25/2023 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 12/19/2023 Approved DAVID TSAU
Special/Order Compliance 6/11/2024 Partial Inspection PAUL DAVIDSON
Special/Order Compliance 12/3/2024 Partial Inspection DANIEL VARNUM
Special/Order Compliance 5/6/2025 Partial Inspection DANIEL VARNUM
Final 5/8/2025 OK to Issue CofO DANIEL VARNUM
Special/Order Compliance 5/22/2025 Partial Inspection PAUL DAVIDSON