Pre-Inspection
|
6/7/2021
|
Approved
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/6/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/2/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/6/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
8/10/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
8/13/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
8/26/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
9/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
9/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
9/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
9/7/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
9/10/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
9/10/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
9/28/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
9/28/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/14/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
10/15/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
10/15/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/18/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/20/2021
|
Conditional Approval
|
BRUCE CAMPBELL
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
10/21/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
10/22/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/25/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/26/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/26/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
10/27/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
10/27/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/28/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/28/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Pre-Stress Concrete
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
10/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
11/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Pre-Stress Concrete
|
11/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
11/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
11/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Steel/Welding
|
11/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
11/2/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
11/2/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/3/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
11/3/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
11/3/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
11/3/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/4/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
11/4/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
11/5/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
11/8/2021
|
Partial Approval
|
TED RIES
|
|
Masonry Wall/Backfill
|
11/8/2021
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
11/9/2021
|
Conditional Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
11/12/2021
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
11/15/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
11/15/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
11/17/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
11/22/2021
|
Partial Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
11/22/2021
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
11/23/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Steel/Welding
|
11/24/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
12/7/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
12/8/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/9/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
12/30/2021
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2022
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
1/3/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
1/3/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
1/3/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/4/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/4/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/7/2022
|
Approved
|
TED RIES
|
|
Deputy Steel/Welding
|
1/7/2022
|
Approved
|
TED RIES
|
|
Deputy Wood Construction
|
1/7/2022
|
Approved
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
1/10/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/10/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/10/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
1/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/18/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/18/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/18/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
1/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
1/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
2/4/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
2/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
2/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
2/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
2/22/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
2/28/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/1/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
3/3/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/10/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/24/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
3/25/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
3/30/2022
|
Conditional Approval
|
TED RIES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2022
|
Partial Approval
|
TED RIES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Steel/Welding
|
4/6/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
5/2/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/2/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
5/2/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
5/6/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
5/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
5/12/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
5/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
5/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
5/24/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
5/25/2022
|
Conditional Approval
|
TERRY HERR
|
|
Deputy Steel/Welding
|
5/26/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
5/27/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
5/31/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
6/2/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
6/3/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
6/6/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/8/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
6/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Steel/Welding
|
6/9/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
6/15/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
6/15/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/21/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
7/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
7/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
7/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
8/11/2022
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
8/15/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/29/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/1/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/7/2022
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
9/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/15/2022
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
9/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
10/12/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/1/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
11/17/2022
|
Approved
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
11/17/2022
|
Partial Approval
|
JAMES POWERS
|
|
T-Bar Ceiling
|
11/29/2022
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
1/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
1/23/2023
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
1/23/2023
|
Approved
|
JAMES POWERS
|
|
Green Building Rough
|
1/23/2023
|
Approved
|
JAMES POWERS
|
|
Pre-Inspection
|
1/23/2023
|
Partial Approval
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/23/2023
|
SGSOV Not Ready
|
JAMES POWERS
|
|
Smoke Detectors
|
1/23/2023
|
Approved
|
JAMES POWERS
|
|
Special/Order Compliance
|
1/23/2023
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
1/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
1/23/2023
|
Partial Approval
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
5/16/2023
|
SGSOV Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/16/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Final
|
10/20/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/20/2023
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
10/20/2023
|
Approved
|
JAMES POWERS
|
|
Final
|
11/1/2023
|
OK to Issue CofO
|
JAMES POWERS
|
|
Special/Order Compliance
|
11/1/2023
|
Approved
|
JAMES POWERS
|