3320 W 50TH ST 90043

Certificate Information: 3320 W 50TH ST 90043

Application / Permit
19010-10000-00674
Plan Check / Job No.
B19LA03153
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Patio Cover
Work Description
New detached covered patio.
Permit Issued
Issued on 9/1/2023
Issuing Office
Metro
Current Status
Issued on 9/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/15/2019 APPLICANT
Assigned to Plan Check Engineer 2/27/2019 RODOLFO ARIAS
Corrections Issued 3/1/2019 RODOLFO ARIAS
Building Plans Picked Up 3/1/2019 APPLICANT
Disabled Access Plans Picked Up 3/1/2019 APPLICANT
Quality Review Completed 6/26/2019 MINYE PAK
Applicant returned to address corrections 5/13/2020 RODOLFO ARIAS
Applicant returned to address corrections 7/15/2021 RODOLFO ARIAS
Applicant returned to address corrections 4/13/2022 RODOLFO ARIAS
Applicant returned to address corrections 7/21/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/2/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/9/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/22/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/20/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/21/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/27/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/29/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/14/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/27/2022 RODOLFO ARIAS
Applicant returned to address corrections 12/29/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/5/2023 RODOLFO ARIAS
Applicant returned to address corrections 3/21/2023 RODOLFO ARIAS
Plan Check Approved 3/21/2023 RODOLFO ARIAS
Issued 9/1/2023 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/10/2021 KURT CORRAL
Metro Rail approval Cleared 7/15/2021 EDDI ZEPEDA
ZI Cleared 8/27/2021 TERRI OSBORNE
"D" conditions Cleared 9/2/2021 KYLE WINSTON
CPC Cleared 9/2/2021 KYLE WINSTON
Specific Plan Cleared 9/2/2021 KYLE WINSTON
Trees in Parkway Cleared 1/5/2022 ADALBERTO VERA
Sewer availability Cleared 4/7/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/21/2022 STEVE MELGAR
Historic Resource Verification Cleared 6/6/2022 SUSAN WONG
Redevelopment Project Area Cleared 6/6/2022 SUSAN WONG
DAS Clearance Cleared 8/24/2022 RODOLFO ARIAS
Low Impact Development Cleared 11/8/2022 AMMAR ELTAWIL
Highway dedication Cleared 11/15/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/15/2022 STEVE MELGAR

Contact Information

Architect Bullock,, Gabrielle A; Lic. No.: C30192 242 N LUCERNE BLVD      LOS ANGELES, CA 90004
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1212 ABBOT KINNEY BLVD #A      LOS ANGELES, CA 90291
Engineer Delgadillo,, Christian; Lic. No.: GE3144 10828 CORD AVE      DOWNEY, CA 90241
Engineer Powers,, Brian Frederick; Lic. No.: C75902 2090 WEST 31ST STREET      LOS ANGELES, CA 90018
Engineer Reynolds,, Aaron D'Angelo; Lic. No.: S4338 4022 JOELTON DRIVE      AGOURA HILLS, CA 91301
Engineer Shimizu,, Ryan Kenji; Lic. No.: C86518 1011 ROSE GLEN AVE      ROSEMEAD, CA 91770

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

No Data Available.