668 S CORONADO ST 90057
Certificate Information: 668 S CORONADO ST 90057
- Application / Permit
- 19010-10000-00654
- Plan Check / Job No.
- B19LA03066
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 5 STORY TYPE IIIA APARTMENT BUILDLING OVER 2 STORY OF TYPE IA WITH RETAIL AND OVER 2 LEVELS OF SUBTERRANEAN PARKING. 2 of Moderate income, 8 of Very low income and 2 of extremely low units per 12.22.A.25
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Metro
- Current Status
- Issued on 7/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2019 | HERNAN ARREOLA |
| Corrections Issued | 3/21/2019 | HERNAN ARREOLA |
| Quality Review Completed | 3/22/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 3/28/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/20/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/26/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/16/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/12/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/27/2020 | HERNAN ARREOLA |
| Plan Check Approved | 3/3/2020 | HERNAN ARREOLA |
| Issued | 7/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2019 | JEANIE LAM |
| Highway dedication | Cleared | 4/8/2019 | JEANIE LAM |
| Project located in CRA area | Cleared | 6/27/2019 | JIM URQUHART |
| Hydrant and Access approval | Cleared | 7/30/2019 | JEREMY CARTER |
| Bicycle Parking | Cleared | 8/8/2019 | KAREN LE |
| Encroachment in public way | Cleared | 9/16/2019 | ELENA LOPEZ |
| Construction near power lines | Cleared | 10/1/2019 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 10/7/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/7/2019 | EMIL KYUPELYAN |
| Trees in Parkway | Cleared | 10/23/2019 | JOHN KIM |
| Permit | Cleared | 10/29/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/4/2019 | EMIL KYUPELYAN |
| Density Bonus 12.22.A.25 | Cleared | 11/5/2019 | JACOB COMER |
| Green Code | Cleared | 12/4/2019 | HERNAN ARREOLA |
| DAS Clearance | Cleared | 12/9/2019 | HERNAN ARREOLA |
| "Q" conditions | Cleared | 12/27/2019 | JOE LUCKEY |
| "T" removal | Cleared | 12/27/2019 | JOE LUCKEY |
| CPC | Cleared | 12/27/2019 | JOE LUCKEY |
| Frnt yard landscape/Water mgmt | Cleared | 12/27/2019 | JOE LUCKEY |
| Opn space landscape/Water mgmt | Cleared | 12/27/2019 | JOE LUCKEY |
| Prkng lot landscape/Water mgmt | Cleared | 12/27/2019 | JOE LUCKEY |
| Site Plan review | Cleared | 12/27/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/27/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/27/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/27/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/27/2019 | JOE LUCKEY |
| ZI | Cleared | 1/6/2020 | GISELLE CORELLA |
| Fire Marshall Fire Life Safety | Cleared | 3/2/2020 | WILLIAM JOHNS |
| Building over 3-story or 36-ft | Cleared | 3/3/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Shubin,, Russell James; Lic. No.: C19250 | 3834 WILLAT AVENUE CULVER CITY, CA 90232 |
| Contractor | Trg Construction Inc; Lic. No.: 1069375-B | PO BOX 1225 LOMITA, CA 90717 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Tang,, Stanley Siu Kei; Lic. No.: C56178 | 1105 N AVON STREET BURBANK, CA 91505 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2023 | Partial Inspection | GREGORY POMISH |
| Pre-Inspection | 5/3/2024 | Partial Inspection | NICK DANERI |
| Pre-Inspection | 5/23/2024 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 6/28/2024 | Corrections Issued | NICK DANERI |
| Pre-Inspection | 7/9/2024 | Partial Inspection | LARRY ARNICK |
| Pre-Inspection | 10/9/2024 | No Access for Inspection | NICK DANERI |
| Pre-Inspection | 12/4/2024 | Partial Inspection | NICK DANERI |
| Pre-Inspection | 2/7/2025 | Partial Inspection | NICK DANERI |
| Grading Pre-Inspection | 3/19/2025 | Partial Approval | NICK DANERI |
| Pre-Inspection | 3/19/2025 | Partial Inspection | NICK DANERI |
| Pre-Inspection | 3/25/2025 | Partial Approval | NICK DANERI |
| Footing/Foundation/Slab | 3/27/2025 | Partial Inspection | NICK DANERI |
| METHANE-Barrier | 3/27/2025 | Approved | NICK DANERI |
| METHANE-Subgrade | 3/27/2025 | Approved | NICK DANERI |
| Piling/Pier/Caisson | 3/27/2025 | Partial Approval | NICK DANERI |
| Piling/Pier/Caisson | 4/14/2025 | Partial Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 6/2/2025 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 7/3/2025 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Shotcrete | 8/6/2025 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/6/2025 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 8/6/2025 | Approved | JOEY BUCHANAN |
| METHANE-Rough | 8/6/2025 | Approved | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/6/2025 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 8/6/2025 | Partial Approval | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 8/6/2025 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 8/7/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/11/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 8/11/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/12/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 8/15/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/19/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/25/2025 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/19/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/30/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 9/30/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 9/30/2025 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/6/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 10/7/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 10/7/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Concrete Frame | 10/17/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 10/23/2025 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 10/23/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/5/2025 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/12/2025 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 12/12/2025 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 12/12/2025 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Reinf. Concrete | 12/16/2025 | No Result Entered | NICK DANERI |
| Footing/Foundation/Slab | 12/16/2025 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 1/22/2026 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 1/22/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/22/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Structural Steel Frame | 1/26/2026 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/3/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Interior/Exterior Lathing | 2/3/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 2/3/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Structural Steel Frame | 2/3/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 2/4/2026 | Conditional Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 2/4/2026 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 2/4/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 2/25/2026 | Conditional Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 2/25/2026 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 2/25/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/2/2026 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 3/4/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 3/4/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Concrete Frame | 3/6/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 3/6/2026 | Partial Approval | JOEY BUCHANAN |
| Reinforced Concrete Frame | 3/10/2026 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 3/10/2026 | Partial Approval | JOEY BUCHANAN |