147-149 E 56TH ST 90011
Certificate Information: 147-149 E 56TH ST 90011
- Application / Permit
- 19010-10000-00648
- Plan Check / Job No.
- B19LA03039
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2 CARS GARAGE AND LAUNDRY ROOM AT REAR OF LOT
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- Issued on 6/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2019 | YAQUB MIRZA |
| Corrections Issued | 3/11/2019 | YAQUB MIRZA |
| Quality Review Completed | 3/18/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 4/18/2019 | APPLICANT |
| Building Plans Picked Up | 4/19/2019 | APPLICANT |
| Plan Check Approved | 3/15/2022 | YAQUB MIRZA |
| Issued | 6/17/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | ELAINE LEI |
| Sewer availability | Cleared | 9/13/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 10/1/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/1/2019 | THOMAS LANG |
| Trees in Parkway | Cleared | 1/16/2020 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 6/15/2021 | HELEN JADALI |
| Green Code | Cleared | 3/15/2022 | COLIN LOREDO |
| Hold | Cleared | 7/13/2023 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/18/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/18/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 7/18/2023 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 8/31/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 12/11/2023 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 5/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 1/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/4/2025 | Approved | SABAS ALONSO |
| Insulation | 2/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/19/2025 | Approved | ANTHONY RAMOS |
| Final | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/4/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/4/2025 | Approved | ALEX COLIN |
| Final | 12/16/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 12/16/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Ready | LUIS CASTRO |
| Service/Power Release | 12/16/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 12/16/2025 | Approved | LUIS CASTRO |