1723 S CREST DR 90035

Certificate Information: 1723 S CREST DR 90035

Application / Permit
19010-10000-00630
Plan Check / Job No.
B19LA02977
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE.
Permit Issued
Issued on 5/13/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 ERIC WONG
Corrections Issued 2/25/2019 ERIC WONG
Quality Review Completed 2/28/2019 LAURA DUONG
Building Plans Picked Up 3/1/2019 APPLICANT
Green Plans Picked Up 3/1/2019 APPLICANT
Applicant returned to address corrections 4/18/2019 ERIC WONG
Plan Check Approved 5/8/2019 ERIC WONG
Issued 5/13/2019 LADBS
CofO in Progress 10/14/2020 EVAN COOPER
CofO Issued 10/27/2020 VINCENT COTTON
Permit Finaled 10/27/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 4/4/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/4/2019 GUILLERMO PETRA
Low Impact Development Cleared 4/4/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 4/4/2019 GUILLERMO PETRA
Sewer availability Cleared 4/5/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 4/8/2019 ROBERT DUFF
Green Code Cleared 4/22/2019 NEGAR NEJAD

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 326 PASEO DE LA PLAYA UNIT B      REDONDO BEACH, CA 90277
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/26/2019 Not Ready for Inspection EVAN COOPER
Underground Mechanical 8/30/2019 No Access for Inspection EVAN COOPER
PLUMBING-Rough 9/4/2019 Partial Approval EVAN COOPER
Sewer 9/4/2019 Approved EVAN COOPER
Underground Mechanical 9/4/2019 Partial Approval EVAN COOPER
Footing/Foundation/Slab 9/16/2019 Conditional Approval EVAN COOPER
METHANE-Barrier 9/16/2019 Conditional Approval EVAN COOPER
METHANE-Subgrade 9/16/2019 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/1/2019 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 11/20/2019 Approved EVAN COOPER
PLUMBING-Rough 11/23/2019 Corrections Issued KENNETH NAGLE
HVAC-Rough 12/6/2019 Corrections Issued EVAN COOPER
PLUMBING-Rough 12/6/2019 Approved EVAN COOPER
BUILDING-Rough-Frame 12/11/2019 Partial Approval EVAN COOPER
Green Building Rough 12/11/2019 Not Ready for Inspection EVAN COOPER
METHANE-Rough 12/11/2019 Approved EVAN COOPER
Verify Sprinkler Sign Off 12/11/2019 Partial Approval EVAN COOPER
Special/Order Compliance 1/2/2020 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 1/28/2020 Not Ready for Inspection EVAN COOPER
Green Building Rough 1/28/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 1/28/2020 Approved EVAN COOPER
Special/Order Compliance 1/30/2020 Partial Inspection EVAN COOPER
Deputy Steel/Welding 2/5/2020 Conditional Approval EVAN COOPER
Insulation 2/5/2020 Conditional Approval EVAN COOPER
Special/Order Compliance 2/25/2020 Partial Inspection KENNETH NAGLE
Drywall Nailing 3/2/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 3/2/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 3/9/2020 Partial Approval EVAN COOPER
Drywall Nailing 3/19/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 3/19/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/1/2020 Approved EVAN COOPER
ELECTRICAL-Final 8/21/2020 Approved EVAN COOPER
Final 8/21/2020 Corrections Issued EVAN COOPER
PLUMBING-Final 8/21/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 9/23/2020 Approved EVAN COOPER
Drywall Nailing 9/23/2020 Approved EVAN COOPER
Final 9/23/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 9/23/2020 Approved EVAN COOPER
Green Building Final 9/23/2020 Approved EVAN COOPER
Green Building Rough 9/23/2020 Approved EVAN COOPER
METHANE-Barrier 9/23/2020 Approved EVAN COOPER
METHANE-Subgrade 9/23/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Approved EVAN COOPER
Service/Power Release 9/23/2020 Approved EVAN COOPER
Smoke Detectors 9/23/2020 Approved EVAN COOPER
Final 10/9/2020 Corrections Issued EVAN COOPER
Final 10/14/2020 Conditional Approval EVAN COOPER
HVAC-Final 10/14/2020 Approved EVAN COOPER