414 N LUCERNE BLVD 90004

Certificate Information: 414 N LUCERNE BLVD 90004

Application / Permit
19010-10000-00604
Plan Check / Job No.
B19LA02835
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW ONE-STORY DETACHED GARAGE (355.5 SQFT.) INCLUDING GARDEN ROOM (31.5 SQ.FT.)
Permit Issued
Issued on 10/10/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 MUKUL GUPTA
Corrections Issued 2/28/2019 MUKUL GUPTA
Quality Review Completed 3/4/2019 MOHAMMAD FIROUZBAKHT
Applicant returned to address corrections 4/9/2019 MUKUL GUPTA
Plan Check Approved 4/12/2019 MUKUL GUPTA
Issued 10/10/2019 LADBS
Green Plans Picked Up 5/1/2020 APPLICANT
CofO in Progress 11/10/2021 CHRIS CHRISTENSEN
Permit Finaled 2/22/2023 DANIEL ORRANTE
CofO Issued 2/22/2023 DANIEL ORRANTE
Permit Finaled 2/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/6/2019 JAMES KHO
Sewer availability Cleared 3/6/2019 ELAINE LEI
Green Code Cleared 3/22/2019 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 4/2/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 4/11/2019 ROBERT DUFF

Contact Information

Contractor Js Design & Construction Inc; Lic. No.: 1019860-B 521 S CATALINA STREET      LOS ANGELES, CA 90020
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/21/2019 Approved LUIS BARRALES
Excavation/Setback/Form/Re-Bar 11/26/2019 Approved ENRIQUE MIRELES
HVAC-Rough 2/3/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 2/4/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/5/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/5/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 2/5/2021 Corrections Issued CHRIS CHRISTENSEN
METHANE-Rough 2/5/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/22/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 2/22/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/22/2021 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 3/4/2021 Approved CHRIS CHRISTENSEN
Sewer 4/21/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 5/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 5/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Service/Power Release 5/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 5/25/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 5/25/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 5/25/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 5/25/2021 Not Required CHRIS CHRISTENSEN
ELECTRICAL-Final 7/9/2021 Approved CHRIS CHRISTENSEN
Final 7/9/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/9/2021 Approved CHRIS CHRISTENSEN
Green Building Final 7/9/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 7/9/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 7/9/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 7/9/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/9/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 7/9/2021 Approved CHRIS CHRISTENSEN
Final 11/9/2021 OK to Issue CofO CHRIS CHRISTENSEN