3977 W BEVERLY BLVD 90004

Certificate Information: 3977 W BEVERLY BLVD 90004

Application / Permit
19010-10000-00603
Plan Check / Job No.
B19LA02834
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
PROPOSED 5-STORY MIXED USE BLDG. PER TOC TIER 3 DIR 2019-2765-TOC
Permit Issued
Issued on 2/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2019 APPLICANT
Assigned to Plan Check Engineer 2/23/2019 LAWRENCE QUIRANTE
Corrections Issued 3/4/2019 LAWRENCE QUIRANTE
Quality Review Completed 3/8/2019 GARO TELMI
Disabled Access Plans Picked Up 3/19/2019 APPLICANT
Building Plans Picked Up 3/29/2019 APPLICANT
Green Plans Picked Up 4/4/2019 APPLICANT
Applicant returned to address corrections 5/8/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/23/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/1/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/29/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/5/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/29/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/6/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/10/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/12/2022 LAWRENCE QUIRANTE
Plan Check Approved 1/20/2022 LAWRENCE QUIRANTE
Issued 2/24/2022 APPLICANT
CofO in Progress 1/29/2025 DAVID BURKHEAD
CofO Issued 1/29/2025 ERNESTO CORRAL
Permit Finaled 1/29/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/8/2019 ELAINE LEI
Building over 3-story or 36-ft Cleared 7/11/2019 CALOSHA APPROVED
Low Impact Development Cleared 7/31/2019 ANDRES COVARRUBIAS
Trees in Parkway Cleared 10/31/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/5/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 6/10/2021 KURT CORRAL
Fire Marshall Fire Life Safety Cleared 6/23/2021 DOMINIQUE MEDINA
Green Code Cleared 7/7/2021 NEGAR NEJAD
DAS Clearance Cleared 7/14/2021 ELIZABETH TOMS
Roof/Waste drainage to street Cleared 7/19/2021 JEANIE LAM
Construction near power lines Cleared 9/3/2021 TINA MIRANDA
Comm Cor/Mini-Mall Cleared 9/22/2021 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 9/22/2021 JOE LUCKEY
Specific Plan Cleared 9/22/2021 JOE LUCKEY
Project located in CRA area Cleared 9/30/2021 SUSAN WONG
Highway dedication Cleared 10/7/2021 CELINA MORENO
Sewer availability Cleared 10/8/2021 JEANIE LAM
Work Adjacent to Public Way Cleared 11/3/2021 CELINA MORENO
Density Bonus 14.00.A.13 Cleared 11/9/2021 LOUIE MILLER

Contact Information

Contractor Daniel S D Construction Inc; Lic. No.: 657391-B 2934 BEVERLY GLEN CIRCLE #357      LOS ANGELES, CA 90077
Engineer Enayat,, Simhaee; Lic. No.: C37206 1332 S ST JOSEPH PL      LOS ANGELES, CA 90015
Engineer Hassan,, Mohamed Ali; Lic. No.: S5285 3621 HARBOR BLVD #125      SANTA ANA, CA 92704
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Young,, Don Yuk-Man; Lic. No.: C35713 149 PASADENA AVE STE B      SOUTH PASADENA, CA 91030

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/24/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/25/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/29/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/30/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/31/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/1/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/4/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/5/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/6/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/7/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/11/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/12/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/13/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/14/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/15/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/18/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/19/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/20/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/21/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 4/22/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 6/23/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/24/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/28/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/29/2022 Partial Approval TIMOTHY BUXTON
METHANE-Barrier 6/29/2022 Approved TIMOTHY BUXTON
METHANE-Subgrade 6/29/2022 Approved TIMOTHY BUXTON
Deputy Reinf. Concrete 6/30/2022 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 7/7/2022 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 7/8/2022 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 7/8/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/11/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/11/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/13/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/13/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 7/15/2022 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/15/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/18/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 7/19/2022 Conditional Approval WINSTON DUNNING
Piling/Pier/Caisson 7/19/2022 Partial Approval TED RIES
Deputy Shotcrete 7/20/2022 Conditional Approval WINSTON DUNNING
Excavation/Setback/Form/Re-Bar 7/20/2022 Partial Approval TED RIES
Deputy Shotcrete 7/21/2022 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 7/25/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 7/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/27/2022 Conditional Approval WINSTON DUNNING
Excavation/Setback/Form/Re-Bar 7/27/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/27/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 7/29/2022 Conditional Approval TED RIES
Piling/Pier/Caisson 7/29/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 8/1/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/1/2022 Partial Approval JAMES POWERS
Deputy Shotcrete 8/2/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 8/2/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/8/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/8/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/9/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 8/9/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/12/2022 Conditional Approval TED RIES
Footing/Foundation/Slab 9/12/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 9/14/2022 Partial Approval TED RIES
Deputy Reinf. Masonry 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/19/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/21/2022 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/22/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/13/2022 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/13/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/20/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 10/20/2022 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/8/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/9/2022 Conditional Approval DAVID BURKHEAD
Reinforced Concrete Frame 11/9/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/14/2022 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/14/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/14/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Piling/Pier/Caisson 11/17/2022 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 11/18/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/21/2022 Conditional Approval TED RIES
Masonry Wall/Backfill 11/21/2022 Partial Approval TED RIES
Deputy Reinf. Masonry 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 12/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/27/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/27/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/28/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/29/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/17/2023 Conditional Approval TED RIES
Deputy Reinf. Masonry 1/18/2023 Conditional Approval TED RIES
Deputy Reinf. Concrete 1/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Partial Approval TED RIES
Deputy Wood Construction 1/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 2/7/2023 Conditional Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval TED RIES
Deputy Drilled-In Anchors 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 2/16/2023 Conditional Approval MICHAEL ROSENBERG
Wall Anchors 2/16/2023 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 2/21/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval TED RIES
Deputy Wood Construction 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 3/20/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 3/29/2023 Conditional Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval TED RIES
Deputy Wood Construction 3/30/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 4/19/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval TED RIES
Deputy Wood Construction 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 5/3/2023 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 5/10/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/23/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 5/26/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 6/14/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 6/16/2023 Partial Inspection GREGORY POMISH
Insulation 6/30/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/25/2023 Partial Inspection DAVID BURKHEAD
Insulation 7/31/2023 Partial Inspection DAVID BURKHEAD
Insulation 8/2/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval DAVID BURKHEAD
Insulation 8/18/2023 Not Ready for Inspection GREGORY POMISH
Insulation 8/24/2023 Not Ready for Inspection TED RIES
Wood Frame 8/25/2023 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/28/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Partial Approval DAVID BURKHEAD
Insulation 8/30/2023 Partial Approval DAVID BURKHEAD
Insulation 9/1/2023 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 9/6/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 9/15/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval RAFAEL ESPINOZA
Insulation 9/19/2023 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 10/2/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/12/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/16/2023 Partial Approval GREGORY POMISH
Insulation 10/18/2023 Partial Approval DAVID BURKHEAD
Insulation 10/20/2023 Partial Approval RAFAEL ESPINOZA
Insulation 10/23/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 10/27/2023 Partial Approval DAVID BURKHEAD
Insulation 10/31/2023 Partial Approval GREGORY POMISH
Drywall Nailing 11/1/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/7/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 11/13/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/15/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 11/17/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/20/2023 Partial Inspection GREGORY POMISH
Insulation 11/29/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 12/1/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/4/2023 Partial Approval GREGORY POMISH
Drywall Nailing 12/21/2023 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/23/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/30/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/27/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/17/2024 Partial Approval LARRY ARNICK
Drywall Nailing 4/29/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 5/20/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/10/2024 Partial Approval TIMOTHY POWELL
Final 9/12/2024 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 9/12/2024 Approved DAVID BURKHEAD
Green Building Final 9/12/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 9/12/2024 Approved DAVID BURKHEAD
METHANE-Final 9/12/2024 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 9/12/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 9/12/2024 Partial Approval DAVID BURKHEAD
Reinforced Masonry Frame 9/12/2024 Partial Approval DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 9/12/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/12/2024 Not Ready for Inspection DAVID BURKHEAD
Final 10/8/2024 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 11/19/2024 Partial Inspection EDWIN GREGORYONA
Special/Order Compliance 11/20/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/26/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 12/17/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 12/19/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 12/20/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 12/20/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 12/23/2024 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 12/26/2024 Approved DAVID BURKHEAD
Special/Order Compliance 1/6/2025 Approved DAVID BURKHEAD
Special/Order Compliance 1/22/2025 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 1/22/2025 Approved DAVID BURKHEAD
Pre-Inspection 1/23/2025 Corrections Issued DAVID BURKHEAD
Final 1/27/2025 OK to Issue CofO DAVID BURKHEAD
Green Building Final 1/27/2025 Approved DAVID BURKHEAD
METHANE-Final 1/27/2025 Approved DAVID BURKHEAD
METHANE-Rough 1/27/2025 Approved DAVID BURKHEAD
Reinforced Concrete Frame 1/27/2025 Approved DAVID BURKHEAD
Reinforced Masonry Frame 1/27/2025 Approved DAVID BURKHEAD
Smoke Detectors 1/27/2025 Approved DAVID BURKHEAD