540 N TOYOPA DR 90272

Certificate Information: 540 N TOYOPA DR 90272

Application / Permit
19010-10000-00529
Plan Check / Job No.
B19LA02490
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 3-CAR GARAGE OVER PARTIAL BASEMENT. (1 OF 4)
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 MICHAEL LOPEZ
Green Plans Picked Up 2/20/2019 APPLICANT
Corrections Issued 2/21/2019 MICHAEL LOPEZ
Quality Review Completed 3/1/2019 FELIX FIGUEROA
Building Plans Picked Up 3/4/2019 APPLICANT
Applicant returned to address corrections 4/18/2019 MICHAEL LOPEZ
Applicant returned to address corrections 5/2/2019 MICHAEL LOPEZ
Applicant returned to address corrections 5/7/2019 MICHAEL LOPEZ
Applicant returned to address corrections 3/17/2021 MICHAEL LOPEZ
Plan Check Approved 4/22/2021 MICHAEL LOPEZ
Plan Check Approved 4/22/2021 MICHAEL LOPEZ
Issued 4/30/2021 APPLICANT
CofO in Progress 1/15/2026 STEPHANIE SWANSON
Permit Finaled 1/27/2026 RICHARD STEINBACH
CofO Issued 1/27/2026 RICHARD STEINBACH
Permit Finaled 1/27/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/13/2019 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 3/13/2019 GEORGE SUCHAND
Permit Cleared 3/13/2019 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/13/2019 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 4/4/2019 ADRIAN SANCHEZ
GPI Written Notices Cleared 4/18/2019 GRANT WOODS
Grading Pre-Inspection Cleared 4/18/2019 GRANT WOODS
Green Code Cleared 4/29/2019 DONALD CRICHLOW
Excavation more than 5-ft deep Cleared 5/2/2019 CALOSHA APPROVED
Low Impact Development Cleared 5/2/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/2/2019 CELINA MORENO

Contact Information

Architect Burdge,, Douglas W; Lic. No.: C16899 24911 PACIFIC COAST HWY      MALIBU, CA 90265
Contractor Rattigan Construction; Lic. No.: 760004-B 11549 DILLING ST      STUDIO CITY, CA 91604
Engineer Liston,, Leonard Irvin; Lic. No.: C31902 889 PIERCE CT STE 101      THOUSAND OAKS, CA 91360
Engineer Padilla,, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/14/2021 Approved ANDREW NAVE
PLUMBING-Rough 12/3/2021 Partial Inspection ANDREW NAVE
Special/Order Compliance 12/3/2021 Corrections Issued ANDREW NAVE
Special/Order Compliance 1/14/2022 Partial Inspection ANDREW NAVE
PLUMBING-Rough 2/9/2022 Partial Approval ANDREW NAVE
Special/Order Compliance 2/9/2022 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/24/2022 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/27/2022 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 6/29/2022 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 6/29/2022 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 6/30/2022 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 7/1/2022 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 8/8/2022 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 8/25/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 8/25/2022 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 8/26/2022 Conditional Approval BRENDAN LOONEY
Deputy Shotcrete 9/7/2022 Conditional Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 9/13/2022 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 9/14/2022 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 9/15/2022 Conditional Approval BRENDAN LOONEY
Deputy Reinf. Concrete 9/19/2022 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 10/13/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 10/13/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 10/28/2022 Partial Approval BRENDAN LOONEY
Deputy Steel/Welding 11/16/2022 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 11/17/2022 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 11/29/2022 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 11/30/2022 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 12/19/2022 Conditional Approval BRENDAN LOONEY
Deputy Other (see comments) 12/20/2022 Approved BRENDAN LOONEY
Deputy Reinf. Concrete 12/20/2022 Approved BRENDAN LOONEY
Footing/Foundation/Slab 12/20/2022 Partial Approval BRENDAN LOONEY
Deputy Shotcrete 12/21/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 1/13/2023 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 2/1/2023 Approved BRENDAN LOONEY
Footing/Foundation/Slab 2/1/2023 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 2/3/2023 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 4/19/2023 Conditional Approval BRENDAN LOONEY
Deputy Steel/Welding 4/21/2023 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/7/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/9/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 6/9/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/15/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/16/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Not Ready for Inspection KENNETH NAGLE
Deputy Steel/Welding 7/6/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 7/7/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 7/14/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 7/17/2023 Conditional Approval MICHAEL PELHAM
Drywall Nailing 7/21/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/26/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/23/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 12/21/2023 Partial Approval EVAN COOPER
HVAC-Rough 1/16/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 1/18/2024 Partial Approval EVAN COOPER
PLUMBING-Rough 1/25/2024 Partial Approval EVAN COOPER
HVAC-Rough 2/12/2024 Approved EVAN COOPER
PLUMBING-Rough 2/12/2024 Approved EVAN COOPER
Deputy Drilled-In Anchors 2/28/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 3/4/2024 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued STEPHANIE SWANSON
Deputy Steel/Welding 3/12/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 3/15/2024 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 4/1/2024 Approved ARAM AVEDISIAN
Green Building Rough 4/1/2024 Approved ARAM AVEDISIAN
Insulation 4/1/2024 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 4/1/2024 Approved ARAM AVEDISIAN
Shower Pan 4/19/2024 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 4/29/2024 Partial Approval KENNETH NAGLE
Deputy Steel/Welding 5/2/2024 No Access for Inspection KENNETH NAGLE
Drywall Nailing 5/17/2024 Partial Approval EVAN COOPER
Interior/Exterior Lathing 5/17/2024 Approved EVAN COOPER
Shower Pan 5/17/2024 Approved EVAN COOPER
Drywall Nailing 6/13/2024 Approved KENNETH NAGLE
Deputy Drilled-In Anchors 6/24/2024 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 7/3/2024 Approved EVAN COOPER
Interior/Exterior Lathing 7/3/2024 Approved EVAN COOPER
Sewer 7/25/2024 Approved EVAN COOPER
ELECTRICAL-Rough 9/9/2024 Approved EVAN COOPER
Interior/Exterior Lathing 9/19/2024 Approved EVAN COOPER
PLUMBING-Rough 10/4/2024 Corrections Issued ARAM AVEDISIAN
Deputy Reinf. Concrete 11/18/2024 Conditional Approval EVAN COOPER
PLUMBING-Rough 11/21/2024 Approved EVAN COOPER
PLUMBING-Final 8/28/2025 Corrections Issued MEL KHACHATOURIAN
Service/Power Release 9/10/2025 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 9/12/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 9/12/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved STEPHANIE SWANSON
Service/Power Release 9/12/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 9/16/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/10/2025 Corrections Issued STEPHANIE SWANSON
Final 11/21/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/21/2025 Approved STEPHANIE SWANSON
Green Building Final 11/21/2025 Approved STEPHANIE SWANSON
HVAC-Final 11/21/2025 Corrections Issued STEPHANIE SWANSON
Smoke Detectors 11/21/2025 Approved STEPHANIE SWANSON
Final 12/4/2025 Partial Inspection STEPHANIE SWANSON
Final 1/15/2026 OK to Issue CofO STEPHANIE SWANSON