113 N KINGSLEY DR 90004
Certificate Information: 113 N KINGSLEY DR 90004
- Application / Permit
- 19010-10000-00516
- Plan Check / Job No.
- B19LA02416
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESORY DWELLING UNIT PER AB 494 AND SB 229 OVER GARAGE AND RECREATION ROOM.
- Permit Issued
- Issued on 5/29/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | MONICA RAMIREZ |
| Corrections Issued | 2/19/2019 | AUNG SOE |
| Green Plans Picked Up | 2/20/2019 | APPLICANT |
| Quality Review Completed | 2/27/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 3/1/2019 | APPLICANT |
| Plan Check Approved | 12/4/2019 | EVERARDO SANTOS |
| Issued | 5/29/2020 | LADBS |
| CofO in Progress | 5/6/2021 | CHRIS CHRISTENSEN |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/28/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 8/6/2019 | GILBERT URREA |
| Sewer availability | Cleared | 8/29/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/10/2019 | SARAH ABOULHOSN |
| Low Impact Development | Cleared | 9/10/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 9/11/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 11/19/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/19/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 11/25/2019 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 11/26/2019 | JEREMY CARTER |
Contact Information
| Architect | Seo,, Hyung Jin; Lic. No.: C31053 | 86 QUAIL CANYON IRVINE, CA 92618 |
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/20/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/2/2020 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/2/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/23/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 10/23/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 10/23/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 10/23/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/23/2020 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 10/23/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/28/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/28/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/5/2020 | Corrections Issued | DONALD CRICHLOW |
| Interior/Exterior Lathing | 11/5/2020 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 11/19/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/19/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/28/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 12/28/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 12/28/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/28/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 3/11/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/11/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/30/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/30/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Final | 3/30/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 3/30/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 3/30/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/30/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 5/5/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 5/5/2021 | Approved | CHRIS CHRISTENSEN |