11714 W ARCHWOOD ST 201-510 91606

Certificate Information: 11714 W ARCHWOOD ST 201-510 91606

Application / Permit
19010-10000-00498
Plan Check / Job No.
B19LA02360
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY 37-UNIT APARTMENT BUILDING 1 LEVEL TYPE 1 PARKING GARAGE WITH 4 LEVELS OF TYPE IIIA CONSTRUCTION. TOC TIER 2 PROGRAM CASE NO. DIR-2019-0575 TOC
Permit Issued
Issued on 7/22/2021
Issuing Office
Valley
Current Status
CofO Corrected on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 MICHAEL PEREZ
Disabled Access Plans Picked Up 3/15/2019 APPLICANT
Green Plans Picked Up 3/15/2019 APPLICANT
Corrections Issued 3/18/2019 MICHAEL PEREZ
Quality Review Completed 4/5/2019 QUAN NGHIEM
Building Plans Picked Up 4/11/2019 APPLICANT
Plan Check Approved 5/26/2020 MICHAEL PEREZ
Issued 7/22/2021 APPLICANT
CofO in Progress 1/16/2025 JOHN KITCKO
CofO Issued-Status Void 1/16/2025 RICKEY JACKSON
Permit Finaled-Status Void 1/16/2025 RICKEY JACKSON
Re-Activate Permit 5/21/2025 RICKEY JACKSON
Permit Finaled 3/26/2026 RICKEY JACKSON
CofO Corrected 3/26/2026 RICKEY JACKSON
Permit Finaled 3/26/2026 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/4/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 6/6/2019 GEORGE SUCHAND
Highway dedication Cleared 6/11/2019 LEE GUILBEAUX
Permit Cleared 6/11/2019 LEE GUILBEAUX
Trees in Parkway Cleared 6/20/2019 ADRIAN SANCHEZ
CPC Cleared 7/22/2019 ANNA VAN
Miscellaneous Cleared 7/22/2019 ANNA VAN
Miscellaneous Cleared 7/22/2019 ANNA VAN
Prkng lot landscape/Water mgmt Cleared 7/22/2019 ANNA VAN
Address approval Cleared 8/1/2019 KAREN LE
Sewer availability Cleared 8/1/2019 KAREN LE
Green Code Cleared 8/5/2019 SARAH ABOULHOSN
Low Impact Development Cleared 9/27/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/8/2019 EMIL KYUPELYAN
Density Bonus 12.22.A.31 Cleared 12/10/2019 EDMUND WONG
DAS Clearance Cleared 1/23/2020 SHINE LIN
Fire Marshall Fire Life Safety Cleared 4/6/2020 MENOA AGHAJANI
Frnt yard landscape/Water mgmt Cleared 4/21/2020 SARAHI ORTEGA
Miscellaneous Cleared 4/21/2020 SARAHI ORTEGA
Opn space landscape/Water mgmt Cleared 4/21/2020 SARAHI ORTEGA
Building over 3-story or 36-ft Cleared 5/26/2020 CALOSHA APPROVED

Contact Information

Architect Kim,, Seong Bae; Lic. No.: C23320 3450 WILSHIRE BLVD SUITE 1000      LOS ANGELES, CA 90010
Contractor G N L Development Inc; Lic. No.: 981677-B 5939 TOPEKA DRIVE      TARZANA, CA 91356
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect Kim,, Samuel Kyun; Lic. No.: LA3249 380 N. PALM STREET STE B      BREA, CA 92821

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 5/26/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 5/31/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 6/7/2022 Partial Approval JOHN KITCKO
Deputy Shotcrete 6/9/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 7/1/2022 Partial Approval JOHN KITCKO
Special/Order Compliance 8/5/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/9/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 9/29/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 10/18/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval JOHN KITCKO
Special/Order Compliance 10/18/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 11/22/2022 Approved JOHN KITCKO
Wood Frame 11/23/2022 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval JOHN KITCKO
Wood Frame 1/23/2023 Partial Approval DANIEL VARNUM
Deputy Wood Construction 1/24/2023 Approved JOHN KITCKO
Special/Order Compliance 2/2/2023 Approved BRIAN KELLY
Wood Frame 2/2/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 2/14/2023 Approved BRIAN KELLY
Wood Frame 2/21/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Not Ready for Inspection JOHN KITCKO
Insulation 3/7/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 3/9/2023 Approved JOHN KITCKO
Insulation 3/9/2023 Partial Approval JOHN KITCKO
Wood Frame 3/10/2023 Partial Inspection JOHN KITCKO
Wood Frame 3/28/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 3/30/2023 Partial Approval JOHN KITCKO
Wood Frame 4/3/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/4/2023 Partial Approval JOHN KITCKO
Drywall Nailing 4/5/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/7/2023 Approved JOHN KITCKO
Insulation 4/7/2023 Partial Approval JOHN KITCKO
Wood Frame 4/11/2023 Partial Approval JOHN KITCKO
Insulation 4/14/2023 Partial Approval JOHN KITCKO
Wood Frame 4/21/2023 Partial Approval JOHN KITCKO
Insulation 4/25/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 4/26/2023 Partial Inspection JOHN KITCKO
Special/Order Compliance 4/26/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 5/2/2023 Partial Inspection ANDREW DORSO
Insulation 5/8/2023 No Access for Inspection JOHN KITCKO
Insulation 5/10/2023 Partial Approval JOHN KITCKO
Drywall Nailing 5/26/2023 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 5/26/2023 Partial Approval JOHN KITCKO
Drywall Nailing 6/5/2023 Partial Approval JOHN KITCKO
Drywall Nailing 6/16/2023 Partial Approval JOHN KITCKO
Drywall Nailing 6/21/2023 Partial Approval JOHN KITCKO
Drywall Nailing 6/23/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 7/11/2023 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 7/12/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 7/31/2023 Partial Approval ROBERT DAVIS
Wood Frame 10/11/2023 Partial Approval JOHN KITCKO
Drywall Nailing 10/17/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 11/8/2023 Partial Approval DANNY RODRIGUEZ
Final 12/22/2023 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 12/22/2023 Approved JOHN KITCKO
Green Building Final 12/22/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 12/22/2023 Approved JOHN KITCKO
Reinforced Concrete Frame 12/22/2023 Approved JOHN KITCKO
Reinforced Masonry Frame 12/22/2023 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 12/22/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 12/22/2023 Approved JOHN KITCKO
Wood Frame 5/28/2024 Partial Inspection JOHN KITCKO
Drywall Nailing 6/3/2024 Partial Approval ROBERT DAVIS
Final 11/19/2024 Partial Inspection JOHN KITCKO
Green Building Final 11/19/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 11/19/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 11/19/2024 Approved JOHN KITCKO
Final 12/12/2024 Partial Inspection JOHN KITCKO
Final 1/14/2025 OK to Issue CofO JOHN KITCKO