237 E LINNIE CL 90291

Certificate Information: 237 E LINNIE CL 90291

Application / Permit
19010-10000-00437
Plan Check / Job No.
B19LA02042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 1/17/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2019 APPLICANT
Green Plans Picked Up 2/12/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 FARSHAD ALIMOHAMADI
Corrections Issued 2/20/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 2/26/2019 FELIX FIGUEROA
Building Plans Picked Up 3/19/2019 APPLICANT
Plan Check Approved 9/18/2019 FARSHAD ALIMOHAMADI
Issued 1/17/2020 LADBS
CofO in Progress 1/6/2023 EVAN COOPER
Permit Finaled 1/7/2023 DANIEL ORRANTE
CofO Issued 1/7/2023 DANIEL ORRANTE
Permit Finaled 1/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/19/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/19/2019 ADRIAN SANCHEZ
Permit Cleared 3/19/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 3/19/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/19/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 4/1/2019 ROBERT DUFF
Trees in Parkway Cleared 4/1/2019 ADRIAN SANCHEZ
Green Code Cleared 5/17/2019 DONALD CRICHLOW
Construction near power lines Cleared 8/20/2019 RIDWAN HARDY
Coastal Zone Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Specific Plan Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Low Impact Development Cleared 9/18/2019 SARAH YOUSSEF

Contact Information

Architect Peters,, Curt Austin; Lic. No.: C30632 23177 LA CADENA DRIVE SUITE 101      LAGUNA HILLS, CA 92656
Contractor Silicon Bay Inc; Lic. No.: 1014712-B 1300 HIGHLAND AVE #102      MANHATTAN BEACH, CA 90266
Engineer Mesinovic,, Sead; Lic. No.: C64335 3719 EMERALD ST APT A      TORRANCE, CA 90503
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 5/11/2020 Approved DAVID HEINE
PLUMBING-Rough 5/26/2020 Partial Approval DAVID HEINE
METHANE-Subgrade 6/4/2020 Partial Approval DAVID HEINE
Deputy Methane Barrier 6/9/2020 Partial Approval DAVID HEINE
Deputy Methane Barrier 6/10/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 6/30/2020 Partial Approval DAVID HEINE
METHANE-Barrier 6/30/2020 Approved DAVID HEINE
METHANE-Subgrade 6/30/2020 Approved DAVID HEINE
Footing/Foundation/Slab 7/21/2020 Partial Approval DAVID HEINE
Deputy Steel/Welding 8/24/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval DAVID HEINE
Rough-Elec/Plmb/HVAC 1/29/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 2/5/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Approved JOHNNY MIRANDA
Green Building Rough 4/8/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 4/8/2021 Corrections Issued JOHNNY MIRANDA
Verify Sprinkler Sign Off 4/8/2021 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 4/12/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/12/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 4/12/2021 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 4/12/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/12/2021 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 6/3/2021 No Access for Inspection JOHNNY MIRANDA
Insulation 6/4/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/4/2021 Partial Approval JOHNNY MIRANDA
Drywall Nailing 6/14/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/15/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 3/15/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 5/6/2022 Corrections Issued DAVID FEILER
HVAC-Final 5/6/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/23/2022 Not Ready for Inspection JESUS RODRIGUEZ
Final 5/23/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 5/23/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 5/23/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/2/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/2/2022 Approved JESUS RODRIGUEZ
Final 6/2/2022 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Rough 6/2/2022 Approved JESUS RODRIGUEZ
HVAC-Final 6/2/2022 Not Ready for Inspection JESUS RODRIGUEZ
METHANE-Rough 6/2/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/2/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 9/26/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/3/2022 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 10/20/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Approved DAVID FEILER
Final 1/4/2023 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 1/4/2023 Approved EVAN COOPER
Green Building Final 1/4/2023 Approved EVAN COOPER
Service/Power Release 1/4/2023 Approved EVAN COOPER
Smoke Detectors 1/4/2023 Approved EVAN COOPER
ELECTRICAL-Final 1/6/2023 Approved EVAN COOPER
Final 1/6/2023 OK to Issue CofO EVAN COOPER
HVAC-Final 1/6/2023 Approved EVAN COOPER
PLUMBING-Final 1/6/2023 Approved EVAN COOPER