237 E LINNIE CL 90291
Certificate Information: 237 E LINNIE CL 90291
- Application / Permit
- 19010-10000-00437
- Plan Check / Job No.
- B19LA02042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2019 | APPLICANT |
| Green Plans Picked Up | 2/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/20/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 2/26/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 3/19/2019 | APPLICANT |
| Plan Check Approved | 9/18/2019 | FARSHAD ALIMOHAMADI |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 1/6/2023 | EVAN COOPER |
| Permit Finaled | 1/7/2023 | DANIEL ORRANTE |
| CofO Issued | 1/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 3/19/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/19/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/19/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 4/1/2019 | ROBERT DUFF |
| Trees in Parkway | Cleared | 4/1/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 5/17/2019 | DONALD CRICHLOW |
| Construction near power lines | Cleared | 8/20/2019 | RIDWAN HARDY |
| Coastal Zone | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Specific Plan | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 9/18/2019 | SARAH YOUSSEF |
Contact Information
| Architect | Peters,, Curt Austin; Lic. No.: C30632 | 23177 LA CADENA DRIVE SUITE 101 LAGUNA HILLS, CA 92656 |
| Contractor | Silicon Bay Inc; Lic. No.: 1014712-B | 1300 HIGHLAND AVE #102 MANHATTAN BEACH, CA 90266 |
| Engineer | Mesinovic,, Sead; Lic. No.: C64335 | 3719 EMERALD ST APT A TORRANCE, CA 90503 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/11/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 5/26/2020 | Partial Approval | DAVID HEINE |
| METHANE-Subgrade | 6/4/2020 | Partial Approval | DAVID HEINE |
| Deputy Methane Barrier | 6/9/2020 | Partial Approval | DAVID HEINE |
| Deputy Methane Barrier | 6/10/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 6/30/2020 | Partial Approval | DAVID HEINE |
| METHANE-Barrier | 6/30/2020 | Approved | DAVID HEINE |
| METHANE-Subgrade | 6/30/2020 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 7/21/2020 | Partial Approval | DAVID HEINE |
| Deputy Steel/Welding | 8/24/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Partial Approval | DAVID HEINE |
| Rough-Elec/Plmb/HVAC | 1/29/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/5/2021 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 4/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 4/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 4/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/12/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 4/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 4/12/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/3/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Insulation | 6/4/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 6/14/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/15/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 3/15/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 5/6/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 5/6/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 5/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 5/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Final | 6/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/2/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| METHANE-Rough | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 9/26/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/3/2022 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 10/20/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | DAVID FEILER |
| Final | 1/4/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/4/2023 | Approved | EVAN COOPER |
| Green Building Final | 1/4/2023 | Approved | EVAN COOPER |
| Service/Power Release | 1/4/2023 | Approved | EVAN COOPER |
| Smoke Detectors | 1/4/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 1/6/2023 | Approved | EVAN COOPER |
| Final | 1/6/2023 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 1/6/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/6/2023 | Approved | EVAN COOPER |