10446 W WHIPPLE ST 91602

Certificate Information: 10446 W WHIPPLE ST 91602

Application / Permit
19010-10000-00419
Plan Check / Job No.
B19LA01950
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) TWO-STORY RESIDENCE WITH ATTACHED GARAGE. 1 OF 3
Permit Issued
Issued on 8/1/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Assigned to Plan Check Engineer 2/8/2019 FARSHAD ALIMOHAMADI
Corrections Issued 2/11/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 2/12/2019 FELIX FIGUEROA
Building Plans Picked Up 3/6/2019 APPLICANT
Green Plans Picked Up 3/6/2019 APPLICANT
Plan Check Approved 6/17/2019 FARSHAD ALIMOHAMADI
Issued 8/1/2019 LADBS
CofO in Progress 7/12/2021 THOMAS FINNILA
CofO in Progress 7/12/2021 THOMAS FINNILA
Permit Finaled 2/3/2022 MICHAEL SMITH
CofO Issued 2/3/2022 MICHAEL SMITH
Permit Finaled 2/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/2/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/2/2019 ELAINE LEI
Hydrant and Access approval Cleared 5/2/2019 GILBERT URREA
Permit Cleared 5/2/2019 ELAINE LEI
Sewer availability Cleared 5/2/2019 ELAINE LEI
ZI Cleared 5/31/2019 SARAHI ORTEGA
Low Impact Development Cleared 6/11/2019 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 6/11/2019 CELINA MORENO
Trees in Parkway Cleared 6/12/2019 JOHN KIM
Green Code Cleared 6/17/2019 SARAH ABOULHOSN

Contact Information

Architect Coane,, James Vincent; Lic. No.: C24789 30 NORTH RAYMOND AVENUE #611      PASADENA, CA 91103
Contractor C S H Properties Inc; Lic. No.: 951406-B 3084 10TH STREET      RIVERSIDE, CA 92507
Engineer Lin,, Jason K; Lic. No.: S6095 900 N SANTA ANITA AVE STE B      ARCADIA, CA 91006

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/15/2019 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 1/13/2020 Approved JEFFREY PARD
Footing/Foundation/Slab 1/13/2020 Approved JEFFREY PARD
Underground Mechanical 1/13/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 4/20/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Approved JEFFREY PARD
Deputy Drilled-In Anchors 5/21/2020 Approved JEFFREY PARD
Deputy Other (see comments) 5/21/2020 Approved JEFFREY PARD
Insulation 6/16/2020 Not Ready for Inspection THOMAS FINNILA
Insulation 7/9/2020 Partial Approval THOMAS FINNILA
Pre-Inspection 7/9/2020 Approved THOMAS FINNILA
PLUMBING-Rough 8/4/2020 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/11/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/11/2020 Partial Approval THOMAS FINNILA
PLUMBING-Rough 8/11/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 8/12/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/24/2020 Approved THOMAS FINNILA
HVAC-Rough 8/24/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/27/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/8/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 9/8/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 9/8/2020 Partial Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 9/8/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/15/2020 Approved THOMAS FINNILA
Green Building Rough 9/15/2020 Approved THOMAS FINNILA
Deputy Drilled-In Anchors 9/16/2020 Conditional Approval THOMAS FINNILA
Insulation 9/21/2020 Not Ready for Inspection THOMAS FINNILA
Insulation 9/25/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/25/2020 Approved THOMAS FINNILA
Drywall Nailing 10/8/2020 Approved DANIEL ORRANTE
Shower Pan 10/29/2020 Approved THOMAS FINNILA
Drywall Nailing 11/6/2020 Approved DANIEL ORRANTE
Interior/Exterior Lathing 11/16/2020 Approved THOMAS FINNILA
PLUMBING-Rough 3/1/2021 Approved THOMAS FINNILA
Gas Test 6/3/2021 Approved THOMAS FINNILA
HVAC-Final 6/9/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 6/10/2021 Partial Inspection THOMAS FINNILA
Service/Power Release 6/10/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 6/11/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 6/16/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 6/16/2021 Approved MATTHEW NELSON
PLUMBING-Final 6/16/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 6/18/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 7/6/2021 Conditional Approval THOMAS FINNILA
Final 7/12/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 7/12/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved THOMAS FINNILA
Service/Power Release 7/12/2021 Approved THOMAS FINNILA
Smoke Detectors 7/12/2021 Approved THOMAS FINNILA