1112 E LANZIT AVE 90059
Certificate Information: 1112 E LANZIT AVE 90059
- Application / Permit
- 19010-10000-00404
- Plan Check / Job No.
- B19LA27054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 61'10"x24' 1-story single family dwelling at rear of lot. NFPA 13D is provided throughout. "COMPLY WITH DEPARTMENT ORDER effective date 09/05/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 826095.
- Permit Issued
- Issued on 7/5/2020
- Issuing Office
- Current Status
- CofO Issued on 7/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | TU HUA |
| Corrections Issued | 5/8/2020 | TU HUA |
| Plan Check Approved | 7/2/2020 | TU HUA |
| Issued | 7/5/2020 | APPLICANT |
| CofO in Progress | 7/26/2023 | KEITH EDGHILL |
| Permit Finaled | 7/27/2023 | PAUL BECKER |
| CofO Issued | 7/27/2023 | PAUL BECKER |
| Permit Finaled | 7/27/2023 | PAUL BECKER |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2019 | KAREN LE |
| Permit | Cleared | 4/3/2019 | KAREN LE |
| Hydrant and Access approval | Cleared | 4/9/2019 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2019 | KAREN LE |
| Sewer availability | Cleared | 6/4/2019 | KAREN LE |
| Green Code | Cleared | 11/19/2019 | KHEDER ALRAZAA |
| Disturb/Remove Protected Trees | Cleared | 12/20/2019 | STEPHEN DUPREY |
| Trees in Parkway | Cleared | 12/20/2019 | JOHN KIM |
| Low Impact Development | Cleared | 3/5/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/26/2020 | Corrections Issued | EUGENE CASSIDY |
| Special/Order Compliance | 8/27/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 9/1/2020 | Approved | KEITH EDGHILL |
| BUILDING-Rough-Frame | 9/22/2020 | Not Ready for Inspection | PAUL BECKER |
| Footing/Foundation/Slab | 9/22/2020 | Corrections Issued | KEITH EDGHILL |
| Green Building Rough | 9/22/2020 | Not Ready for Inspection | KEITH EDGHILL |
| Verify Sprinkler Sign Off | 9/22/2020 | Not Ready for Inspection | KEITH EDGHILL |
| Footing/Foundation/Slab | 9/29/2020 | Corrections Issued | KEITH EDGHILL |
| BUILDING-Rough-Frame | 10/7/2020 | Not Ready for Inspection | KEITH EDGHILL |
| Footing/Foundation/Slab | 10/7/2020 | Approved | KEITH EDGHILL |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | KEITH EDGHILL |
| Verify Sprinkler Sign Off | 10/7/2020 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 2/4/2021 | Partial Approval | KEITH EDGHILL |
| ELECTRICAL-Rough | 2/4/2021 | Partial Approval | KEITH EDGHILL |
| Green Building Rough | 2/4/2021 | Not Ready for Inspection | KEITH EDGHILL |
| PLUMBING-Rough | 2/4/2021 | Conditional Approval | KEITH EDGHILL |
| Verify Sprinkler Sign Off | 2/4/2021 | Not Ready for Inspection | KEITH EDGHILL |
| Insulation | 2/9/2021 | Conditional Approval | KEITH EDGHILL |
| Drywall Nailing | 2/12/2021 | Conditional Approval | KEITH EDGHILL |
| Green Building Rough | 2/12/2021 | Conditional Approval | KEITH EDGHILL |
| Underground Mechanical | 3/12/2021 | Approved | KEITH EDGHILL |
| Underground Mechanical | 3/19/2021 | Conditional Approval | KEITH EDGHILL |
| PLUMBING-Rough | 6/8/2021 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 11/16/2022 | Conditional Approval | KEITH EDGHILL |
| Drywall Nailing | 11/16/2022 | Conditional Approval | KEITH EDGHILL |
| Final | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Rough | 11/16/2022 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Not Ready | KEITH EDGHILL |
| Service/Power Release | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| Smoke Detectors | 11/16/2022 | Approved | KEITH EDGHILL |
| Verify Sprinkler Sign Off | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | KEITH EDGHILL |
| Drywall Nailing | 3/30/2023 | Approved | KEITH EDGHILL |
| Final | 3/30/2023 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 3/30/2023 | Approved | KEITH EDGHILL |
| Green Building Rough | 3/30/2023 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | KEITH EDGHILL |
| Service/Power Release | 3/30/2023 | Corrections Issued | KEITH EDGHILL |
| Verify Sprinkler Sign Off | 3/30/2023 | Approved | KEITH EDGHILL |
| Final | 4/24/2023 | Corrections Issued | KEITH EDGHILL |
| Service/Power Release | 4/24/2023 | Approved | KEITH EDGHILL |
| Final | 5/5/2023 | Conditional Approval | KEITH EDGHILL |
| Final | 7/26/2023 | OK to Issue CofO | KEITH EDGHILL |