3733 N LOMITAS DR 90032
Certificate Information: 3733 N LOMITAS DR 90032
- Application / Permit
- 19010-10000-00370
- Plan Check / Job No.
- B19LA01782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FOR NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTCHED 2-CAR GARAGE.
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 5/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | MUKUL GUPTA |
| Corrections Issued | 2/11/2019 | MUKUL GUPTA |
| Green Plans Picked Up | 2/12/2019 | APPLICANT |
| Quality Review Completed | 2/22/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 2/25/2019 | APPLICANT |
| Applicant returned to address corrections | 8/2/2019 | JOHNNY WU |
| Applicant returned to address corrections | 8/7/2019 | JOHNNY WU |
| Applicant returned to address corrections | 8/20/2019 | JOHNNY WU |
| Applicant returned to address corrections | 9/4/2019 | JOHNNY WU |
| Applicant returned to address corrections | 11/7/2019 | JOHNNY WU |
| Plan Check Approved | 11/15/2019 | JOHNNY WU |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 5/29/2025 | LILIANA PORTILLO |
| Permit Finaled | 5/31/2025 | DEROLD HAUFF |
| Permit Finaled | 5/31/2025 | DEROLD HAUFF |
| CofO Issued | 5/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/16/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 4/16/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 4/16/2019 | ELENA LOPEZ |
| Permit | Cleared | 4/16/2019 | ELENA LOPEZ |
| Construction near power lines | Cleared | 4/29/2019 | WALTER RAMIREZ |
| Green Code | Cleared | 5/16/2019 | KHEDER ALRAZAA |
| Address approval | Cleared | 5/31/2019 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 5/31/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/31/2019 | ADRIAN SANCHEZ |
| "D" conditions | Cleared | 7/2/2019 | NICOLE SANCHEZ |
| "Q" conditions | Cleared | 7/2/2019 | NICOLE SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 7/2/2019 | NICOLE SANCHEZ |
| ZI | Cleared | 7/2/2019 | NICOLE SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 7/16/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 7/18/2019 | JEREMY CARTER |
| Sewer availability | Cleared | 7/18/2019 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 8/2/2019 | MUKUL GUPTA |
| GPI Written Notices | Cleared | 11/7/2019 | MUKUL GUPTA |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/31/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/25/2020 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/18/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 11/30/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| Pre-Inspection | 1/5/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 1/11/2021 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 1/21/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Not Ready for Inspection | COREY HUPP |
| Underground Mechanical | 2/16/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 2/23/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Corrections Issued | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 10/31/2022 | Approved | AMY COLIN |
| Gas Test | 10/31/2022 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 10/31/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 10/31/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 11/16/2022 | Corrections Issued | AMY COLIN |
| Insulation | 11/18/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/18/2022 | Not Ready for Inspection | AMY COLIN |
| Drywall Nailing | 12/7/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 1/23/2023 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 6/21/2023 | Approved | AMY COLIN |
| Final | 6/21/2023 | Corrections Issued | AMY COLIN |
| Gas Test | 6/21/2023 | Approved | AMY COLIN |
| HVAC-Final | 6/21/2023 | Approved | AMY COLIN |
| PLUMBING-Final | 6/21/2023 | Approved | AMY COLIN |
| Final | 6/27/2023 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 6/27/2023 | Approved | AMY COLIN |
| Smoke Detectors | 6/27/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | LILIANA PORTILLO |
| Final | 5/28/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/28/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 5/28/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 5/28/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | LILIANA PORTILLO |