318-320 E 118TH ST 90061

Certificate Information: 318-320 E 118TH ST 90061

Application / Permit
19010-10000-00298
Plan Check / Job No.
B19LA01580
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX
Permit Issued
Issued on 6/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 SERGIO GUTIERREZ
Corrections Issued 2/25/2019 SERGIO GUTIERREZ
Quality Review Completed 2/26/2019 MOHAMMAD FIROUZBAKHT
Green Plans Picked Up 3/1/2019 APPLICANT
Building Plans Picked Up 3/7/2019 APPLICANT
Plan Check Approved 6/5/2019 SERGIO GUTIERREZ
Issued 6/19/2019 LADBS
CofO in Progress 9/2/2021 EUGENE CASSIDY
Permit Finaled 9/25/2021 DEROLD HAUFF
CofO Issued 9/25/2021 DEROLD HAUFF
Permit Finaled 9/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 4/9/2019 ADRIAN SANCHEZ
Green Code Cleared 4/11/2019 SARAH ABOULHOSN
ZI Cleared 4/12/2019 JOSE ROMERO-NAVARRO
Hydrant and Access approval Cleared 4/16/2019 JOHN CONNEALLY
Address approval Cleared 4/22/2019 JEANETTE VONG
Community Plan Implem. Overlay Cleared 4/22/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/22/2019 JEANETTE VONG
Low Impact Development Cleared 4/22/2019 JORGE MEJIA LEMUS
Permit Cleared 4/22/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 4/22/2019 JEANETTE VONG
Sewer availability Cleared 5/14/2019 ELAINE LEI
Community Plan Implem. Overlay Cleared 6/5/2019 JOE LUCKEY
Miscellaneous Cleared 6/5/2019 JOE LUCKEY

Contact Information

Contractor V C Construction & Development; Lic. No.: 959583-B 24132 MEADOW FALLS DRIVE      DIAMOND BAR, CA 91765
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2019 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 7/22/2019 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/24/2019 Conditional Approval WILLIAM ROSE
Underground Mechanical 8/16/2019 Approved JOHN KLARIN
Insulation 8/20/2019 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/26/2019 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/16/2019 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 10/17/2019 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 10/21/2019 Corrections Issued WILLIAM ROSE
Deputy Wood Construction 10/25/2019 Conditional Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Corrections Issued WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 1/15/2020 Partial Approval WILLIAM ROSE
PLUMBING-Rough 4/28/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/18/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/18/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/20/2020 Approved BRIAN CHRISTIAN
Wood Frame 5/20/2020 Not Ready for Inspection BRIAN CHRISTIAN
HVAC-Rough 5/27/2020 Not Ready for Inspection BRIAN CHRISTIAN
HVAC-Rough 5/29/2020 Approved EUGENE CASSIDY
Wood Frame 5/29/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 6/4/2020 Approved EUGENE CASSIDY
Insulation 6/9/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 6/12/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 6/16/2020 Approved BRIAN CHRISTIAN
Wood Frame 6/16/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 6/24/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 6/25/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 3/23/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
Final 3/26/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/26/2021 Approved EUGENE CASSIDY
Green Building Final 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 3/26/2021 Approved EUGENE CASSIDY
MERV13>=Final 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 3/26/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 3/26/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/6/2021 Approved EUGENE CASSIDY
Final 4/6/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/6/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/6/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/13/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/13/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 4/13/2021 Approved EUGENE CASSIDY
Final 4/30/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/5/2021 Approved EUGENE CASSIDY
Sewer 5/5/2021 Approved EUGENE CASSIDY
Final 5/17/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 5/17/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 5/17/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 5/17/2021 Approved EUGENE CASSIDY
Service/Power Release 5/17/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 5/17/2021 Approved EUGENE CASSIDY
Final 7/9/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 7/9/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 7/9/2021 Not Ready for Inspection EUGENE CASSIDY
Final 8/23/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 8/23/2021 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 8/23/2021 Not Ready for Inspection EUGENE CASSIDY
Final 8/26/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 8/26/2021 Approved EUGENE CASSIDY
Service/Power Release 8/26/2021 Not Ready for Inspection EUGENE CASSIDY
Final 9/1/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 9/1/2021 Approved EUGENE CASSIDY
Service/Power Release 9/1/2021 Approved EUGENE CASSIDY