1367 N CASIANO ROAD 90049
Certificate Information: 1367 N CASIANO ROAD 90049
- Application / Permit
- 19010-10000-00266
- Plan Check / Job No.
- B19LA01395
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. FULLY SPRINKLERED(NFPA13D).
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 2/13/2019 | SAMUEL GONZALEZ |
| Green Plans Picked Up | 3/4/2019 | APPLICANT |
| Quality Review Completed | 3/18/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| Plan Check Approved | 7/15/2021 | SAMUEL GONZALEZ |
| Issued | 7/29/2021 | APPLICANT |
| CofO in Progress | 11/21/2024 | CARLOS MATAMOROS |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 12/13/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 12/13/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 12/13/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2019 | JAMES MORALEZ |
| Green Code | Cleared | 12/13/2019 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 12/13/2019 | JEREMY CARTER |
| Sewer availability | Cleared | 12/13/2019 | JAMES MORALEZ |
| Trees in Parkway | Cleared | 2/14/2020 | JOHN KIM |
| Low Impact Development | Cleared | 7/22/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 6/29/2021 | SAMUEL GONZALEZ |
| Grading Pre-Inspection | Cleared | 6/29/2021 | SAMUEL GONZALEZ |
Contact Information
| Architect | De, Mure, Jeffrey; Lic. No.: C26832 | 5905 GRANITE LAKE DRIVE SUITE 140 GRANITE BAY, CA 95746 |
| Contractor | Blusky Restoration Contractors Llc; Lic. No.: 1005805-B | 9767 E EASTER AVE CENTENNIAL, CO 80112 |
| Engineer | Andreasen,, Jeremy Von; Lic. No.: S5123 | 2088 DORRINGTON DR ROSEVILLE, CA 95661 |
| Engineer | Doss,, Richard E; Lic. No.: C48987 | 30141 AGOURA RD 200 AGOURA HILLS, CA 91301 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/2/2022 | Partial Inspection | DANIEL ORRANTE |
| Piling/Pier/Caisson | 11/18/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/21/2022 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 12/8/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 12/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 12/16/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/19/2022 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 12/28/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/30/2023 | Corrections Issued | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 5/30/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/5/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 6/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Underground Mechanical | 6/30/2023 | Approved | CARLOS MATAMOROS |
| Sewer | 7/3/2023 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/13/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 7/14/2023 | Conditional Approval | MICHAEL PELHAM |
| Wood Frame | 8/29/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 10/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 10/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 11/17/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 12/7/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/26/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/26/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/13/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 2/13/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/13/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/16/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 2/20/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/5/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 3/5/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/20/2024 | Approved | CARLOS MATAMOROS |
| Sewer | 7/23/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/28/2024 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 8/28/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 9/12/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/12/2024 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 9/16/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | CARLOS MATAMOROS |
| Final | 11/7/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/7/2024 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 11/7/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 11/7/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | CARLOS MATAMOROS |
| Final | 11/21/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 11/21/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/21/2024 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 11/21/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | CARLOS MATAMOROS |