2521 N ONYX DR 90032

Certificate Information: 2521 N ONYX DR 90032

Application / Permit
19010-10000-00253
Plan Check / Job No.
B19LA01322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New SFD with attached garage and ADU per AB 494 and SB 229.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 SERGIO GUTIERREZ
Corrections Issued 2/5/2019 SERGIO GUTIERREZ
Quality Review Completed 2/6/2019 MOHAMMAD FIROUZBAKHT
Green Plans Picked Up 2/12/2019 APPLICANT
Building Plans Picked Up 3/5/2019 APPLICANT
Plan Check Approved 3/17/2021 SERGIO GUTIERREZ
Issued 4/7/2021 APPLICANT
CofO in Progress 9/21/2022 OSVALDO PARAMO
CofO in Progress 9/21/2022 OSVALDO PARAMO
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/3/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/3/2019 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 5/6/2019 ROBERT DUFF
Sewer availability Cleared 5/22/2019 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 5/29/2019 JEANETTE VONG
Green Code Cleared 5/30/2019 SERGIO GUTIERREZ
Low Impact Development Cleared 6/11/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/25/2019 DENNIS BRAGIN
"D" conditions Cleared 9/17/2019 NICOLE SANCHEZ
"Q" conditions Cleared 9/17/2019 NICOLE SANCHEZ
ZI Cleared 9/17/2019 NICOLE SANCHEZ
GPI Written Notices Cleared 10/23/2019 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 10/23/2019 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2021 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 4/16/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 4/27/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/6/2021 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 5/6/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/24/2021 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/27/2021 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 6/9/2021 No Access for Inspection DAVID FEILER
Masonry Wall/Backfill 6/17/2021 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 6/23/2021 Not Ready for Inspection OSVALDO PARAMO
Masonry Wall/Backfill 7/2/2021 Not Ready for Inspection RAUL BARAJAS
Masonry Wall/Backfill 7/7/2021 Approved OSVALDO PARAMO
Deck 8/2/2021 Partial Inspection SCOTT FINNILA
Masonry Wall/Backfill 8/2/2021 Partial Approval SCOTT FINNILA
Wood Frame 10/5/2021 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 11/3/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 11/5/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 11/22/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 11/22/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/30/2021 Approved OSVALDO PARAMO
HVAC-Rough 11/30/2021 Approved OSVALDO PARAMO
Special/Order Compliance 11/30/2021 Partial Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 12/8/2021 Approved OSVALDO PARAMO
Green Building Rough 12/8/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 12/8/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/9/2021 Approved OSVALDO PARAMO
Insulation 2/3/2022 Approved OSVALDO PARAMO
Drywall Nailing 3/1/2022 Approved OSVALDO PARAMO
Gas Test 5/24/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 5/25/2022 Corrections Issued OSVALDO PARAMO
HVAC-Final 5/26/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 5/27/2022 Corrections Issued OSVALDO PARAMO
Service/Power Release 5/31/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Final 6/2/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 6/2/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 6/30/2022 Corrections Issued OSVALDO PARAMO
HVAC-Final 6/30/2022 Approved OSVALDO PARAMO
PLUMBING-Final 6/30/2022 Approved OSVALDO PARAMO
Final 9/12/2022 OK to Issue CofO OSVALDO PARAMO
Footing/Foundation/Slab 9/12/2022 Approved OSVALDO PARAMO
Green Building Final 9/12/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Approved OSVALDO PARAMO
Service/Power Release 9/12/2022 Approved OSVALDO PARAMO
Smoke Detectors 9/12/2022 Approved OSVALDO PARAMO