3209 N PORTOLA AVE 90032
Certificate Information: 3209 N PORTOLA AVE 90032
- Application / Permit
- 19010-10000-00217
- Plan Check / Job No.
- B19LA01166
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 2/12/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 2/12/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 2/15/2019 | APPLICANT |
| Applicant returned to address corrections | 4/4/2019 | EMMANUEL MARTINEZ |
| Green Plans Picked Up | 9/10/2019 | APPLICANT |
| Applicant returned to address corrections | 12/18/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 12/30/2019 | EMMANUEL MARTINEZ |
| Issued | 1/14/2020 | LADBS |
| CofO in Progress | 3/15/2021 | COREY HUPP |
| CofO in Progress | 3/15/2021 | COREY HUPP |
| Permit Finaled | 3/24/2021 | DEROLD HAUFF |
| CofO Issued | 3/24/2021 | DEROLD HAUFF |
| Permit Finaled | 3/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/18/2019 | BARTON HOLMES |
| Address approval | Cleared | 4/4/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2019 | ELAINE LEI |
| GPI Written Notices | Cleared | 4/4/2019 | EMMANUEL MARTINEZ |
| Hydrant and Access approval | Cleared | 4/4/2019 | GILBERT URREA |
| Sewer availability | Cleared | 4/4/2019 | ELAINE LEI |
| Disturb/Remove Protected Trees | Cleared | 5/13/2019 | JOHN KIM |
| "D" conditions | Cleared | 10/24/2019 | JOE LUCKEY |
| "Q" conditions | Cleared | 10/24/2019 | JOE LUCKEY |
| ZI | Cleared | 10/24/2019 | JOE LUCKEY |
| Green Code | Cleared | 12/9/2019 | VIVIAN LAO |
| Low Impact Development | Cleared | 12/9/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/9/2019 | CELINA MORENO |
Contact Information
| Architect | Wu,, Juan-Lieh John; Lic. No.: C11469 | 412 SOUTH STONEMAN AVENUE ALHAMBRA, CA 91801 |
| Contractor | Pong D A Construction Inc; Lic. No.: 1007004-B | 1255 SOUTH EASTMAN AVENUE LOS ANGELES, CA 90023 |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 3129 S HACIENDA BL STE 524 HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/3/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/31/2020 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/21/2020 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 5/13/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/20/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/20/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/20/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/20/2020 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/20/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 5/28/2020 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/28/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 6/2/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/8/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/8/2020 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Final | 9/16/2020 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 9/24/2020 | Approved | COREY HUPP |
| ELECTRICAL-Final | 9/25/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 9/25/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | COREY HUPP |
| Final | 3/15/2021 | OK to Issue CofO | COREY HUPP |
| Green Building Final | 3/15/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Approved | COREY HUPP |
| Service/Power Release | 3/15/2021 | Approved | COREY HUPP |
| Smoke Detectors | 3/15/2021 | Approved | COREY HUPP |