337 S 6TH AVE 90291

Certificate Information: 337 S 6TH AVE 90291

Application / Permit
19010-10000-00204
Plan Check / Job No.
B18LA12044
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
2-STORY GARAGE W/ REC ROOM ABOVE.
Permit Issued
Issued on 2/20/2019
Issuing Office
West Los Angeles
Current Status
Issued on 2/20/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2018 APPLICANT
Green Plans Picked Up 7/3/2018 APPLICANT
Assigned to Plan Check Engineer 7/12/2018 JOE VO
Corrections Issued 7/16/2018 JOE VO
Quality Review Completed 7/18/2018 GARO TELMI
Building Plans Picked Up 7/24/2018 APPLICANT
Applicant returned to address corrections 8/23/2018 JOE VO
Applicant returned to address corrections 8/31/2018 JOE VO
Applicant returned to address corrections 10/23/2018 JOE VO
Plan Check Approved 2/19/2019 JOE VO
Issued 2/20/2019 LADBS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Becht,, Charles; Lic. No.: C30213 PO BOX 300   BECHT ENGINEERING CO    LIBERTY CORNER, NJ 7938
Engineer Sagherian,, Jonathan Hovnathan; Lic. No.: C37138 444 PIEDMONT AVE 203      GLENDALE, CA 91206

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/13/2019 Partial Approval DAVID HEINE
Footing/Foundation/Slab 5/22/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 6/18/2019 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 6/25/2019 Approved DAVID HEINE
PLUMBING-Rough 5/5/2020 Corrections Issued DAVID HEINE
PLUMBING-Rough 5/8/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 5/13/2020 Approved DAVID HEINE
Excavation/Setback/Form/Re-Bar 3/10/2022 Partial Approval KENNETH NAGLE
Underground Mechanical 5/13/2022 Partial Approval DAVID FEILER
Underground Mechanical 5/18/2022 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Final 1/18/2023 Not Ready for Inspection EVAN COOPER
Green Building Final 1/18/2023 Not Ready for Inspection EVAN COOPER
HVAC-Final 1/18/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 1/18/2023 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 3/6/2025 Corrections Issued HERBERT GIRON