561 E SAN JUAN AVE 90291

Certificate Information: 561 E SAN JUAN AVE 90291

Application / Permit
19010-10000-00161
Plan Check / Job No.
B19LA00838
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1) NEW 3-STORY SFR WITH 3 CAR GARAGE AND ROOF DECK 1 OF 2
Permit Issued
Issued on 1/30/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 ARSALAN SHABESTARI
Corrections Issued 1/26/2019 ARSALAN SHABESTARI
Green Plans Picked Up 1/31/2019 APPLICANT
Quality Review Completed 2/4/2019 FELIX FIGUEROA
Building Plans Picked Up 2/5/2019 APPLICANT
Plan Check Approved 1/16/2020 ARSALAN SHABESTARI
Issued 1/30/2020 LADBS
Permit Finaled 11/20/2025 RICHARD STEINBACH
CofO Issued 11/20/2025 RICHARD STEINBACH
Permit Finaled 11/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Green Code Cleared 2/19/2019 COLIN LOREDO
Address approval Cleared 2/25/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 2/25/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 2/25/2019 GILBERT URREA
Miscellaneous Cleared 2/25/2019 DIANA JIMENEZ
Miscellaneous Cleared 2/25/2019 DIANA JIMENEZ
Sewer availability Cleared 2/25/2019 ELENA LOPEZ
Low Impact Development Cleared 9/27/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/27/2019 JEANETTE VONG
Specific Plan Cleared 10/25/2019 JULIET OH
Specific Plan Cleared 10/28/2019 PEDRO AYALA
Coastal Zone Cleared 12/19/2019 NOAH MCCOY
Miscellaneous Cleared 12/19/2019 NOAH MCCOY

Contact Information

Architect Ward,, Soyoung Choi; Lic. No.: C32634 22340 S WESTERN AVENUE      TORRANCE, CA 90501
Contractor Owner-Builder       ,
Engineer Bell,, William Andrew; Lic. No.: C88870 22403 LADEENE AVE      TORRANCE, CA 90505
Engineer Chen,, Shaofu; Lic. No.: C76834 5589 CARMELLO COURT      RANCHO CUCAMONGA, CA 91739
Engineer Morales,, Ricky Augusto; Lic. No.: C40289 27520 HAWTHORNE BLVD STE 250      ROLLING HILLS ESTATES, CA 90274

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2020 Partial Approval DAVID HEINE
Pre-Inspection 4/17/2023 Approved EVAN COOPER
PLUMBING-Rough 4/28/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/12/2023 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 6/13/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 6/27/2023 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 7/21/2023 Approved EVAN COOPER
Footing/Foundation/Slab 7/21/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Corrections Issued HERBERT GIRON
Deputy Wood Construction 4/2/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 5/9/2024 Approved HERBERT GIRON
HVAC-Rough 5/13/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 6/6/2024 Partial Approval HERBERT GIRON
Underground Mechanical 6/6/2024 Partial Approval HERBERT GIRON
HVAC-Rough 6/10/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 6/10/2024 Partial Approval HERBERT GIRON
Shower Pan 6/10/2024 Approved HERBERT GIRON
Deputy Wood Construction 6/24/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 6/25/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 6/27/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 7/2/2024 Approved HERBERT GIRON
Green Building Rough 7/2/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 7/2/2024 Approved HERBERT GIRON
Insulation 7/15/2024 Corrections Issued HERBERT GIRON
Insulation 7/25/2024 Approved HERBERT GIRON
Drywall Nailing 8/2/2024 Partial Approval HERBERT GIRON
Drywall Nailing 8/8/2024 Approved DANIEL VERA
Interior/Exterior Lathing 1/16/2025 Approved HERBERT GIRON
Underground Mechanical 1/16/2025 Approved HERBERT GIRON
PLUMBING-Final 4/18/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/21/2025 Approved JESUS RODRIGUEZ
HVAC-Final 4/21/2025 Approved JESUS RODRIGUEZ
Service/Power Release 4/21/2025 Approved JESUS RODRIGUEZ
Final 10/2/2025 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 10/2/2025 Approved JESUS RODRIGUEZ
Final 11/17/2025 Partial Approval JESUS RODRIGUEZ
Green Building Final 11/17/2025 Approved JESUS RODRIGUEZ