977 S CATALINA ST 90006

Certificate Information: 977 S CATALINA ST 90006

Application / Permit
19010-10000-00119
Plan Check / Job No.
B19LA00577
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 49 UNITS APARTMENT BUILDING; 4 STORY OF TYPE V-A OVER 1 STORY TYPE 1-A PODIUM, WITH ONE LEVEL TYPE IA SUBTERRANEAN PARKING; TOTAL 5 STORIES ABOVE GROUND W/ROOF DECK (TOC).
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
Issued on 2/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 DEAN LEE
Disabled Access Plans Picked Up 1/25/2019 APPLICANT
Corrections Issued 2/5/2019 DEAN LEE
Quality Review Completed 2/14/2019 BILL STUTSMAN
Applicant returned to address corrections 3/19/2019 DEAN LEE
Applicant returned to address corrections 1/15/2020 DEAN LEE
Applicant returned to address corrections 3/11/2020 DEAN LEE
Applicant returned to address corrections 8/13/2020 DEAN LEE
Green Plans Picked Up 4/30/2021 APPLICANT
Plan Check Approved 1/5/2022 EUGENE BARBEAU
Issued 2/2/2022 APPLICANT
Building Plans Picked Up 2/4/2022 APPLICANT
TCO Issued (Expire Date: 01-11-2027) 7/15/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/13/2019 JEANIE LAM
Project located in CRA area Cleared 3/13/2019 JIM URQUHART
Address approval Cleared 3/21/2019 ELAINE LEI
Highway dedication Cleared 3/21/2019 ELAINE LEI
Permit Cleared 3/21/2019 ELAINE LEI
Sewer availability Cleared 1/23/2020 ERIK BEASLEY
Building over 3-story or 36-ft Cleared 10/14/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/14/2020 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 10/22/2020 HERMINIGILDO AGUSTIN
Opn space landscape/Water mgmt Cleared 10/22/2020 HERMINIGILDO AGUSTIN
ZA Case Cleared 10/22/2020 HERMINIGILDO AGUSTIN
Driveway location Cleared 10/29/2020 PETE EYRE
Internal circulation Cleared 10/29/2020 PETE EYRE
Green Code Cleared 11/16/2020 COLIN LOREDO
Hydrant and Access approval Cleared 11/19/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/16/2020 MARTIN FRAGOSO
Density Bonus 12.22.A.31 Cleared 12/23/2020 LOUIE MILLER
Roof/Waste drainage to street Cleared 1/12/2021 JEANIE LAM
Encroachment in public way Cleared 1/13/2021 ELAINE LEI
Trees in Parkway Cleared 2/24/2021 JOHN KIM
Fire Marshall Fire Life Safety Cleared 3/25/2021 WILLIAM JOHNS
DAS Clearance Cleared 4/19/2021 SHINE LIN
Work Adjacent to Public Way Cleared 7/21/2021 CHIU TAM

Contact Information

Architect , ; Lic. No.: C38323       ,
Contractor New Creation Engineering & Builders Inc; Lic. No.: 768842-B 17809 CLARK AVENUE      BELLFLOWER, CA 90706
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010
Engineer Kim,, Hosang; Lic. No.: C67288 18759 WILLOWTREE LANE      PORTER RANCH, CA 91326
Engineer Yim,, Donghyun; Lic. No.: C59739 5629 BURNING TREE DR      LA CANADA, CA 91011
Landscape Architect Kim,, Yunsoo; Lic. No.: LA5887 404 SHATTO PLACE #444      LOS ANGELES, CA 90020

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/11/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/18/2023 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/28/2023 Conditional Approval NICK DANERI
Special/Order Compliance 9/28/2023 Partial Inspection NICK DANERI
Deputy Shotcrete 9/29/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/2/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/3/2023 Conditional Approval NICK DANERI
Deputy Shotcrete 10/4/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/5/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/10/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 1/9/2024 Partial Approval GREGORY POMISH
Green Building Rough 2/16/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/16/2024 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 2/16/2024 Not Ready for Inspection NICK DANERI
Masonry Wall/Backfill 3/6/2024 Partial Approval NICK DANERI
Masonry Wall/Backfill 3/13/2024 Partial Approval NICK DANERI
Green Building Rough 4/17/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 4/17/2024 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 4/17/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 4/24/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/24/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/24/2024 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Partial Approval NICK DANERI
Insulation 8/28/2024 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval LARRY ARNICK
Insulation 9/18/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Approval NICK DANERI
Insulation 10/7/2024 Partial Approval EDWIN GREGORYONA
Insulation 10/9/2024 Partial Approval PAUL BAZERKANIAN
Insulation 10/21/2024 Not Ready for Inspection LARRY ARNICK
Green Building Rough 10/25/2024 Not Ready for Inspection NICK DANERI
Insulation 10/25/2024 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 10/25/2024 Not Ready for Inspection NICK DANERI
Wood Frame 10/25/2024 Partial Approval NICK DANERI
Insulation 10/31/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 11/1/2024 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 11/1/2024 Partial Inspection EDWIN GREGORYONA
Insulation 11/1/2024 Partial Approval EDWIN GREGORYONA
Insulation 11/4/2024 Partial Approval NICK DANERI
Drywall Nailing 11/5/2024 Partial Inspection NICK DANERI
Green Building Rough 11/5/2024 Not Ready for Inspection NICK DANERI
Insulation 11/8/2024 Partial Approval NICK DANERI
Drywall Nailing 11/15/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 11/15/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/21/2024 Partial Inspection NICK DANERI
Green Building Rough 11/21/2024 Partial Approval NICK DANERI
Drywall Nailing 12/3/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 12/3/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 12/12/2024 Partial Approval LARRY ARNICK
Green Building Rough 12/12/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 12/18/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/18/2024 Partial Inspection EDWIN GREGORYONA
Insulation 12/27/2024 Partial Approval NICK DANERI
Drywall Nailing 12/31/2024 Partial Approval NICK DANERI
Green Building Rough 12/31/2024 Partial Inspection NICK DANERI
Drywall Nailing 1/13/2025 Partial Approval NICK DANERI
Green Building Rough 1/13/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 1/15/2025 Partial Approval LARRY ARNICK
Green Building Rough 1/15/2025 Approved LARRY ARNICK
Insulation 2/20/2025 No Access for Inspection RAFAEL CORTES
Wood Frame 2/25/2025 Partial Approval NICK DANERI
Insulation 3/5/2025 Partial Approval NICK DANERI
Drywall Nailing 3/7/2025 Partial Approval NICK DANERI
Insulation 3/14/2025 Partial Approval LARRY ARNICK
Insulation 3/17/2025 Partial Approval NICK DANERI
Insulation 3/24/2025 Partial Approval NICK DANERI
Insulation 3/27/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 4/4/2025 Partial Approval NICK DANERI
Drywall Nailing 4/11/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 4/15/2025 Partial Approval NICK DANERI
Drywall Nailing 4/28/2025 Partial Approval NICK DANERI
Insulation 4/28/2025 Partial Inspection NICK DANERI
Interior/Exterior Lathing 4/28/2025 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 4/30/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 5/2/2025 Partial Approval MARTIN TAVITIAN
Insulation 5/7/2025 Partial Approval NICK DANERI
Drywall Nailing 5/13/2025 Partial Approval NICK DANERI
Drywall Nailing 5/20/2025 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/20/2025 Approved NICK DANERI
Insulation 5/20/2025 Approved NICK DANERI
Interior/Exterior Lathing 5/20/2025 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 5/20/2025 Not Ready for Inspection NICK DANERI
Wood Frame 5/20/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 6/25/2025 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 6/25/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 7/15/2025 Conditional Approval JOEY BUCHANAN
Masonry Wall/Backfill 7/18/2025 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 7/28/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Masonry 7/29/2025 Conditional Approval JOEY BUCHANAN
Masonry Wall/Backfill 7/30/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 8/1/2025 Conditional Approval JOEY BUCHANAN
Special/Order Compliance 9/5/2025 Partial Inspection LARRY ARNICK
Special/Order Compliance 11/14/2025 Partial Approval JOEY BUCHANAN
Special/Order Compliance 1/13/2026 Approved JOEY BUCHANAN
Special/Order Compliance 1/29/2026 Approved JOEY BUCHANAN
Special/Order Compliance 5/18/2026 Approved JOEY BUCHANAN
Verify Rec and Parks Fee Memo 5/18/2026 Not Ready for Inspection JOEY BUCHANAN
Drywall Nailing 5/19/2026 Approved JOEY BUCHANAN
Final 5/19/2026 Corrections Issued JOEY BUCHANAN
Green Building Final 5/19/2026 Approved JOEY BUCHANAN
Reinforced Concrete Frame 5/19/2026 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/19/2026 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 5/19/2026 Approved JOEY BUCHANAN
Structural Steel Frame 5/19/2026 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 5/19/2026 Approved JOEY BUCHANAN
Wood Frame 5/19/2026 Approved JOEY BUCHANAN
Special/Order Compliance 5/20/2026 Approved JOEY BUCHANAN
Final 7/9/2026 Partial Approval RONALD JIMENEZ
Final 7/14/2026 OK for TCO JOEY BUCHANAN