135 S KINGSLEY DR 90004
Certificate Information: 135 S KINGSLEY DR 90004
- Application / Permit
- 19010-10000-00097
- Plan Check / Job No.
- B19LA00452
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 3-CAR GARAGE AT GROUND LEVEL WITH 2ND FLOOR ADU ABOVE PER AB 494 AND SB 229. FULLY SPRINKLERED. SEE COMMENTS.
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 2/8/2019 | ANA AVELAR |
| Quality Review Completed | 2/11/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 2/13/2019 | APPLICANT |
| Green Plans Picked Up | 3/7/2019 | APPLICANT |
| Applicant returned to address corrections | 6/4/2019 | EMMANUEL MARTINEZ |
| Applicant returned to address corrections | 6/27/2019 | EMMANUEL MARTINEZ |
| Applicant returned to address corrections | 8/15/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 2/5/2020 | EMMANUEL MARTINEZ |
| Issued | 7/14/2020 | APPLICANT |
| CofO in Progress | 1/10/2024 | JEFFREY MEAD |
| Permit Finaled | 1/14/2024 | DEROLD HAUFF |
| CofO Issued | 1/14/2024 | DEROLD HAUFF |
| Permit Finaled | 1/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 3/7/2019 | JEANETTE VONG |
| Green Code | Cleared | 5/8/2019 | ANA AVELAR |
| Low Impact Development | Cleared | 11/22/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 11/22/2019 | THOMAS LANG |
| Green Code | Cleared | 12/19/2019 | ANA AVELAR |
| Hydrant and Access approval | Cleared | 1/24/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Total Service Of America Inc; Lic. No.: 544459-B | 2111 SOUTH BROADWAY #202 LOS ANGELES, CA 90007 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2020 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 9/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/16/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 10/16/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/27/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/17/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 11/17/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 11/17/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 11/17/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 12/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/14/2020 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/21/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/21/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 12/21/2020 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/21/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Wood Frame | 12/21/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/19/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/19/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 2/19/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Shower Pan | 2/19/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 2/19/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/5/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/5/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 3/31/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/31/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Service/Power Release | 6/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 8/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 8/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 9/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 10/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 10/25/2021 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 11/8/2021 | Corrections Issued | MASHEL JONGERT |
| Service/Power Release | 11/8/2021 | Approved | MASHEL JONGERT |
| Final | 12/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Special/Order Compliance | 12/13/2022 | Corrections Issued | JEFFREY MEAD |
| Final | 12/19/2023 | Corrections Issued | JEFFREY MEAD |
| Final | 1/10/2024 | OK to Issue CofO | JEFFREY MEAD |