1 S LMU DR BUILDING B 90045

Certificate Information: 1 S LMU DR BUILDING B 90045

Application / Permit
19010-10000-00096
Plan Check / Job No.
B19LA00431
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(11) Dormitory
Work Description
(N) 4-story Type V-A dormitory with partial basement. It is comprised of communal amenity spaces, one- and two-bed dorm rooms, bathrooms, faculty apartments, and housing offices. (Building B).
Permit Issued
Issued on 8/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 HERNAN ARREOLA
Corrections Issued 2/15/2019 HERNAN ARREOLA
Quality Review Completed 2/25/2019 BILL STUTSMAN
Building Plans Picked Up 2/26/2019 APPLICANT
Applicant returned to address corrections 3/11/2019 HERNAN ARREOLA
Disabled Access Plans Picked Up 3/15/2019 APPLICANT
Applicant returned to address corrections 6/28/2019 HERNAN ARREOLA
Plan Check Approved 8/20/2019 HERNAN ARREOLA
Issued 8/20/2019 LADBS
TCO Issued (Expire Date: 09-22-2021) 3/26/2021 HENRY BAGHDASSARIAN
CofO in Progress 5/18/2021 NICK LAROCCA
Permit Finaled 5/18/2021 HENRY BAGHDASSARIAN
CofO Issued 5/18/2021 HENRY BAGHDASSARIAN
Permit Finaled 5/18/2021 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/7/2019 JOHN CONNEALLY
Sewer availability Cleared 7/8/2019 ELENA LOPEZ
Miscellaneous Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/9/2019 SOPHIE GABEL-SCHEINBAU
Prkng lot landscape/Water mgmt Cleared 7/15/2019 BRIDGETTE WOOTEN
Frnt yard landscape/Water mgmt Cleared 7/16/2019 BRIDGETTE WOOTEN
Site Plan review Cleared 7/16/2019 BRIDGETTE WOOTEN
Specific Plan Cleared 7/17/2019 DAVID TEHRANI
ZI Cleared 7/17/2019 DAVID TEHRANI
Low Impact Development Cleared 7/31/2019 MARTIN FRAGOSO
Specific Plan Cleared 7/31/2019 EDER ROMERO
Address approval Cleared 8/1/2019 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 8/1/2019 CHRISTOPHER LAW
Highway dedication Cleared 8/1/2019 CHRISTOPHER LAW
DAS Clearance Cleared 8/5/2019 EDDIE GARIN
Green Code Cleared 8/5/2019 KHEDER ALRAZAA
Fire Marshall Fire Life Safety Cleared 8/6/2019 PEJMAN NOORI
Roof/Waste drainage to street Cleared 8/7/2019 ADRIAN SANCHEZ
Permit Cleared 8/8/2019 MAHELET GEBEYHU
Building over 3-story or 36-ft Cleared 8/20/2019 CALOSHA APPROVED
GPI Written Notices Cleared 8/20/2019 HERNAN ARREOLA
Grading Pre-Inspection Cleared 8/20/2019 HERNAN ARREOLA

Contact Information

Contractor Bernards Bros Inc; Lic. No.: 302007-B 555 FIRST STREET      SAN FERNANDO, CA 91340
Engineer Rezaian,, Reza; Lic. No.: C62048 3665 MOUNTAIN VIEW AVENUE      LOS ANGELES, CA 90066
Engineer Sordyl,, Douglas John; Lic. No.: C35854 3234 WALDON COVE      WHITE LAKE, MI 48383

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/26/2019 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 8/27/2019 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 8/30/2019 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/13/2019 Approved NICK LAROCCA
Footing/Foundation/Slab 9/13/2019 Not Ready for Inspection NICK LAROCCA
METHANE-Barrier 9/13/2019 Approved NICK LAROCCA
METHANE-Subgrade 9/13/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/16/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/17/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/18/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/19/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/20/2019 Approved NICK LAROCCA
Footing/Foundation/Slab 9/20/2019 Partial Approval NICK LAROCCA
Deputy Shotcrete 9/24/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/26/2019 Approved NICK LAROCCA
Deputy Shotcrete 9/27/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/30/2019 Approved NICK LAROCCA
Deputy Shotcrete 9/30/2019 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 9/30/2019 Partial Approval NICK LAROCCA
Deputy Other (see comments) 10/1/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/1/2019 Approved NICK LAROCCA
Deputy Shotcrete 10/1/2019 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/1/2019 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/2/2019 Approved NICK LAROCCA
Deputy Shotcrete 10/2/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/3/2019 Approved DERRICK SPENCER
Deputy Shotcrete 10/3/2019 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/4/2019 Approved DERRICK SPENCER
Deputy Shotcrete 10/4/2019 Approved DERRICK SPENCER
Footing/Foundation/Slab 10/8/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 10/10/2019 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/11/2019 Approved DERRICK SPENCER
Reinforced Concrete Frame 10/11/2019 Partial Approval DERRICK SPENCER
Deputy Wood Construction 10/18/2019 Approved DERRICK SPENCER
Deputy Steel/Welding 10/21/2019 Conditional Approval TONY HARTONO
Deputy Steel/Welding 10/22/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/23/2019 Approved NICK LAROCCA
Deputy Steel/Welding 10/23/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/24/2019 Approved NICK LAROCCA
Deputy Steel/Welding 10/24/2019 Approved NICK LAROCCA
Deputy Reinf. Concrete 10/25/2019 Approved NICK LAROCCA
Deputy Steel/Welding 10/25/2019 Approved NICK LAROCCA
Deputy Steel/Welding 11/6/2019 Approved NICK LAROCCA
Deputy Steel/Welding 11/8/2019 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 11/8/2019 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 11/12/2019 Approved NICK LAROCCA
Deputy Steel/Welding 11/13/2019 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 11/14/2019 Approved NICK LAROCCA
Deputy Steel/Welding 11/15/2019 Approved TED RIES
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Partial Approval TED RIES
Deputy Steel/Welding 11/18/2019 Approved TED RIES
Deputy Steel/Welding 11/19/2019 Approved NICK LAROCCA
Deputy Steel/Welding 11/20/2019 Conditional Approval NICK LAROCCA
Footing/Foundation/Slab 11/22/2019 Partial Approval NICK LAROCCA
Deputy Steel/Welding 12/3/2019 Approved NICK LAROCCA
Deputy Steel/Welding 12/5/2019 Approved NICK LAROCCA
Deputy Steel/Welding 12/6/2019 Approved NICK LAROCCA
Deputy Steel/Welding 12/9/2019 Approved NICK LAROCCA
Deputy Steel/Welding 12/10/2019 Conditional Approval NICK LAROCCA
Deputy Steel/Welding 12/23/2019 Approved NICK LAROCCA
Deputy Steel/Welding 12/24/2019 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/8/2020 Approved NICK LAROCCA
Deputy Wood Construction 1/8/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/9/2020 Approved NICK LAROCCA
Deputy Wood Construction 1/9/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/10/2020 Approved NICK LAROCCA
Deputy Wood Construction 1/10/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/13/2020 Approved NICK LAROCCA
Deputy Wood Construction 1/13/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/14/2020 Approved NICK LAROCCA
Deputy Wood Construction 1/14/2020 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 1/14/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 1/21/2020 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/3/2020 Partial Approval NICK LAROCCA
Deputy Steel/Welding 2/5/2020 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval NICK LAROCCA
Green Building Rough 3/13/2020 Approved NICK LAROCCA
METHANE-Rough 3/13/2020 Approved NICK LAROCCA
Verify Sprinkler Sign Off 3/13/2020 Approved NICK LAROCCA
Wood Frame 3/13/2020 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval NICK LAROCCA
Wood Frame 3/31/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 4/2/2020 Approved NICK LAROCCA
Deputy Wood Construction 4/2/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 4/3/2020 Approved NICK LAROCCA
Deputy Wood Construction 4/3/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 4/6/2020 Approved NICK LAROCCA
Deputy Wood Construction 4/6/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 4/7/2020 Approved NICK LAROCCA
Deputy Wood Construction 4/7/2020 Approved NICK LAROCCA
Wood Frame 4/7/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 4/8/2020 Approved NICK LAROCCA
Deputy Wood Construction 4/8/2020 Approved NICK LAROCCA
Insulation 4/13/2020 Partial Approval NICK LAROCCA
Wood Frame 4/17/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval NICK LAROCCA
Wood Frame 5/6/2020 Partial Approval NICK LAROCCA
Wood Frame 5/11/2020 Partial Approval DERRICK SPENCER
Wood Frame 5/19/2020 Partial Approval NICK LAROCCA
Wood Frame 5/27/2020 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 5/29/2020 Approved NICK LAROCCA
Interior/Exterior Lathing 5/29/2020 Partial Approval NICK LAROCCA
Deputy Steel/Welding 6/2/2020 Approved NICK LAROCCA
Wood Frame 6/3/2020 Partial Approval NICK LAROCCA
Insulation 6/8/2020 Partial Approval DERRICK SPENCER
Wood Frame 6/8/2020 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval NICK LAROCCA
Insulation 6/22/2020 Not Ready for Inspection NICK LAROCCA
Interior/Exterior Lathing 6/22/2020 Approved NICK LAROCCA
Wood Frame 6/25/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 7/10/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 7/27/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 7/27/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/31/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/5/2020 Approved DERRICK SPENCER
Reinforced Concrete Frame 8/7/2020 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/19/2020 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/28/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 8/31/2020 Approved NICK LAROCCA
Drywall Nailing 9/1/2020 Not Ready for Inspection NICK LAROCCA
Green Building Final 9/1/2020 Not Ready for Inspection NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 9/1/2020 SGSOV Approved NICK LAROCCA
Smoke Detectors 9/1/2020 Approved NICK LAROCCA
Wood Frame 9/1/2020 Not Ready for Inspection NICK LAROCCA
Deputy Reinf. Concrete 9/3/2020 Approved NICK LAROCCA
Insulation 9/8/2020 Partial Approval NICK LAROCCA
Wood Frame 9/21/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/24/2020 Approved NICK LAROCCA
Insulation 9/25/2020 Partial Approval NICK LAROCCA
Insulation 9/28/2020 Not Ready for Inspection NICK LAROCCA
Insulation 9/30/2020 Partial Approval NICK LAROCCA
Insulation 10/1/2020 Not Ready for Inspection NICK LAROCCA
Insulation 10/2/2020 Partial Approval NICK LAROCCA
Insulation 10/5/2020 Partial Approval NICK LAROCCA
Insulation 10/7/2020 Partial Approval NICK LAROCCA
Insulation 10/8/2020 Partial Approval NICK LAROCCA
Insulation 10/9/2020 Partial Approval NICK LAROCCA
Insulation 10/13/2020 Partial Approval NICK LAROCCA
Insulation 10/14/2020 Partial Approval NICK LAROCCA
Insulation 10/15/2020 Not Ready for Inspection NICK LAROCCA
Insulation 10/19/2020 Partial Approval NICK LAROCCA
Insulation 10/21/2020 Partial Approval JOEY BUCHANAN
Insulation 10/22/2020 Partial Inspection NICK LAROCCA
Insulation 10/26/2020 Partial Approval NICK LAROCCA
Insulation 10/27/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/29/2020 Approved NICK LAROCCA
Deputy Wood Construction 10/29/2020 Approved NICK LAROCCA
Insulation 10/29/2020 Partial Approval NICK LAROCCA
Insulation 11/2/2020 Partial Approval NICK LAROCCA
Insulation 11/5/2020 Partial Approval NICK LAROCCA
Drywall Nailing 11/9/2020 Corrections Issued NICK LAROCCA
Drywall Nailing 11/12/2020 Partial Approval NICK LAROCCA
Insulation 11/13/2020 Partial Approval NICK LAROCCA
Insulation 11/16/2020 Partial Approval NICK LAROCCA
Insulation 11/17/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/18/2020 Approved NICK LAROCCA
Insulation 11/23/2020 Partial Approval JOEY BUCHANAN
Insulation 11/30/2020 Not Ready for Inspection NICK LAROCCA
Insulation 12/2/2020 Partial Approval NICK LAROCCA
Insulation 12/4/2020 Partial Approval JOEY BUCHANAN
Insulation 12/18/2020 Partial Approval NICK LAROCCA
Insulation 12/23/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/6/2021 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/7/2021 Approved JOEY BUCHANAN
Insulation 1/8/2021 Partial Approval JOEY BUCHANAN
T-Bar Ceiling 1/11/2021 Not Ready for Inspection NICK LAROCCA
Deputy Steel/Welding 1/14/2021 Approved NICK LAROCCA
T-Bar Ceiling 1/14/2021 Partial Approval NICK LAROCCA
Deputy Steel/Welding 1/15/2021 Approved NICK LAROCCA
T-Bar Ceiling 1/15/2021 Partial Approval NICK LAROCCA
T-Bar Ceiling 1/26/2021 Partial Approval TED RIES
T-Bar Ceiling 2/5/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 2/11/2021 Not Ready for Inspection DERRICK SPENCER
Final 2/11/2021 Not Ready for Inspection DERRICK SPENCER
Green Building Final 2/11/2021 Not Ready for Inspection DERRICK SPENCER
Wood Frame 2/11/2021 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 2/24/2021 Approved DERRICK SPENCER
Drywall Nailing 2/25/2021 Approved JOEY BUCHANAN
Final 2/25/2021 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 2/25/2021 Approved JOEY BUCHANAN
Wood Frame 2/25/2021 Approved JOEY BUCHANAN
Special/Order Compliance 3/4/2021 Approved NICK LAROCCA
Final 3/25/2021 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 4/20/2021 Approved NICK LAROCCA
Deputy Other (see comments) 4/20/2021 Approved NICK LAROCCA
Final 5/11/2021 Partial Approval NICK LAROCCA