3219 N ETTRICK ST 90027
Certificate Information: 3219 N ETTRICK ST 90027
- Application / Permit
- 19010-10000-00078
- Plan Check / Job No.
- B19LA00345
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27' 6" X 16' 6" DETACHED ACCESSORY DWELLING UNIT (357 SQ FT) PER AB 494 AND SB 229 STATE APPROVED FACTORY BUILT HOUSING
- Permit Issued
- Issued on 4/2/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 1/25/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/1/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 2/8/2019 | APPLICANT |
| Green Plans Picked Up | 2/20/2019 | APPLICANT |
| Plan Check Approved | 3/13/2019 | SERGIO GUTIERREZ |
| Issued | 4/2/2019 | LADBS |
| CofO in Progress | 6/10/2021 | JOSEPH MCGARRY |
| Permit Finaled | 6/23/2021 | DEROLD HAUFF |
| CofO Issued | 6/23/2021 | DEROLD HAUFF |
| Permit Finaled | 6/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 2/20/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/20/2019 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 2/20/2019 | CELINA MORENO |
| Sewer availability | Cleared | 2/20/2019 | CELINA MORENO |
| GPI Written Notices | Cleared | 3/13/2019 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 3/13/2019 | SERGIO GUTIERREZ |
| Green Code | Cleared | 3/13/2019 | SARAH ABOULHOSN |
Contact Information
| Contractor | Cover Technologies Inc; Lic. No.: 1039029-B | 1219 W. 135TH STREET GARDENA, CA 90247 |
| Engineer | Behnam,, Peter George; Lic. No.: S4678 | 722 N LUCIA AVE UNIT A REDONDO BEACH, CA 90277 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/4/2020 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 6/4/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/4/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 6/4/2020 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 6/4/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/9/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 6/16/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/16/2020 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 6/18/2020 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 6/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/3/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/2/2020 | Approved | OSVALDO PARAMO |
| Final | 11/2/2020 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/2/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 11/2/2020 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 11/2/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/19/2020 | Approved | JOSEPH MCGARRY |
| Final | 11/19/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 11/19/2020 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 11/19/2020 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 11/19/2020 | Approved | JOSEPH MCGARRY |
| Final | 12/3/2020 | Partial Approval | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/3/2020 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 6/2/2021 | OK to Issue CofO | JOSEPH MCGARRY |