9110 N DE SOTO AVE 91311

Certificate Information: 9110 N DE SOTO AVE 91311

Application / Permit
19010-10000-00072
Plan Check / Job No.
B19LA00338
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Household Goods Storage
Work Description
NEW FOUR-STORY, TYPE II-A, SPRINKLERED HOUSEHOLD GOOD SELF-STORAGE BUILDING.
Permit Issued
Issued on 12/26/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 GARO TELMI
Green Plans Picked Up 1/25/2019 APPLICANT
Corrections Issued 2/19/2019 GARO TELMI
Quality Review Completed 2/22/2019 JOHN FRANCIA
Building Plans Picked Up 2/25/2019 APPLICANT
Disabled Access Plans Picked Up 2/28/2019 APPLICANT
Applicant returned to address corrections 5/1/2019 GARO TELMI
Applicant returned to address corrections 5/24/2019 GARO TELMI
Applicant returned to address corrections 7/17/2019 GARO TELMI
Applicant returned to address corrections 7/24/2019 GARO TELMI
Applicant returned to address corrections 7/29/2019 GARO TELMI
Applicant returned to address corrections 8/5/2019 GARO TELMI
Applicant returned to address corrections 10/9/2019 GARO TELMI
Plan Check Approved 12/4/2019 GARO TELMI
Issued 12/26/2019 LADBS
TCO Issued (Expire Date: 02-20-2022) 8/24/2021 JEFFREY DURAN
TCO Issued (Expire Date: 08-08-2022) 2/9/2022 RICKEY JACKSON
CofO in Progress 5/4/2022 JEFFREY FULTON
CofO in Progress 5/4/2022 JEFFREY FULTON
Permit Finaled 6/7/2022 RICKEY JACKSON
CofO Issued 6/7/2022 RICKEY JACKSON
Permit Finaled 6/7/2022 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 4/16/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/16/2019 ELENA LOPEZ
Sewer availability Cleared 4/16/2019 ELENA LOPEZ
ZI Cleared 4/16/2019 DIANA JIMENEZ
Low Impact Development Cleared 4/19/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/19/2019 JEANETTE VONG
Bicycle Parking Cleared 4/29/2019 KARAN PATEL
Hydrant and Access approval Cleared 5/2/2019 GEORGE SUCHAND
Highway dedication Cleared 5/15/2019 MARKOS PEREZ-BRAN
Work Adjacent to Public Way Cleared 5/17/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 8/9/2019 COLIN LOREDO
Driveway location Cleared 8/15/2019 BRANDON WILSON
Internal circulation Cleared 8/15/2019 BRANDON WILSON
Miscellaneous Cleared 8/15/2019 BRANDON WILSON
Construction near power lines Cleared 8/28/2019 RIDWAN HARDY
DAS Clearance Cleared 9/16/2019 GARO TELMI
Trees in Parkway Cleared 9/27/2019 ADRIAN SANCHEZ
"Q" conditions Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
"T" removal Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Comm Cor/Mini-Mall Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Comm Cor/Mini-Mall Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Comm Cor/Mini-Mall Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Permit Cleared 10/1/2019 EMIL KYUPELYAN
Prkng lot landscape/Water mgmt Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Site Plan review Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
ZI Cleared 10/1/2019 SOPHIE GABEL-SCHEINBAU
Building over 3-story or 36-ft Cleared 10/9/2019 CALOSHA APPROVED

Contact Information

Contractor Padelford A J & Son Inc; Lic. No.: 222840-B P O BOX 185      ARTESIA, CA 907020185
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Momeni,, Moe; Lic. No.: C56774 8772 RAINBOW RIDGE      LAS VEGAS, NV 89117
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 1423 S BEVERLY GLEN BLVD APT B      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2020 Partial Inspection ROBERT COLE
Grading Pre-Inspection 2/5/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 2/12/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 2/21/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/27/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/28/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/28/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/2/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/9/2020 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/9/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/3/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/5/2020 Partial Inspection JEFFREY FULTON
Deputy Other (see comments) 6/9/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/9/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 6/10/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/12/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/15/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/17/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 6/29/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 6/29/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 6/30/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/1/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/2/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 7/6/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 7/7/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/8/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/9/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/10/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 7/10/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 7/13/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 7/16/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 7/20/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/21/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 7/22/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 7/22/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 7/23/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/24/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 7/27/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/27/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 7/27/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 7/28/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/28/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/29/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/30/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 7/31/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/3/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/4/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/5/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/6/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/7/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/10/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/12/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/25/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/25/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 8/26/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/27/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 8/31/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 8/31/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 9/1/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 9/3/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 9/3/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 9/4/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/10/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/11/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 9/11/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/14/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/15/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 9/15/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/17/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/18/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/21/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 9/24/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 9/29/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 10/6/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 10/7/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 10/8/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 10/9/2020 Conditional Approval JEFFREY FULTON
Structural Steel Frame 10/9/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 10/14/2020 Conditional Approval JEFFREY FULTON
Drywall Nailing 10/14/2020 Partial Inspection JEFFREY FULTON
Insulation 10/14/2020 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 10/14/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 10/21/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 10/21/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 10/22/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 10/23/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 10/27/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 10/27/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 11/2/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 11/2/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 11/4/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 11/5/2020 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 11/5/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 11/6/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 11/20/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 11/23/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 11/24/2020 Conditional Approval RICKEY JACKSON
Deputy Steel/Welding 11/25/2020 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 12/1/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/2/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/3/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/4/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/7/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/8/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/9/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/10/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/11/2020 Partial Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/16/2020 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 12/18/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/18/2020 Conditional Approval JEFFREY FULTON
Structural Steel Frame 12/18/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 12/21/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 12/22/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/22/2020 Conditional Approval JEFFREY FULTON
Structural Steel Frame 12/22/2020 Partial Inspection JEFFREY FULTON
Deputy Fireproofing 12/23/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/23/2020 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 12/24/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/24/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/29/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/30/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/31/2020 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/8/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/13/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/20/2021 Partial Inspection JEFFREY FULTON
Insulation 2/17/2021 Partial Inspection JEFFREY FULTON
Deputy Fireproofing 3/2/2021 Conditional Approval JEFFREY DURAN
Deputy Fireproofing 3/3/2021 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 3/4/2021 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 3/5/2021 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 3/11/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/23/2021 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/25/2021 Partial Inspection JEFFREY FULTON
Pre-Inspection 4/8/2021 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 5/25/2021 Not Ready for Inspection DANIEL VARNUM
Special/Order Compliance 7/22/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 8/12/2021 Not Ready for Inspection JEFFREY FULTON
Final 8/20/2021 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/20/2021 Approved JEFFREY FULTON
Green Building Final 8/20/2021 Approved JEFFREY FULTON
Green Building Rough 8/20/2021 Approved JEFFREY FULTON
Reinforced Masonry Frame 8/20/2021 Partial Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV No Gas JEFFREY FULTON
Smoke Detectors 8/20/2021 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 8/20/2021 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 1/27/2022 Partial Inspection JEFFREY FULTON
Final 2/1/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 2/1/2022 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 2/1/2022 Approved JEFFREY FULTON
Final 3/9/2022 OK to Issue CofO JEFFREY FULTON