2253 S CRENSHAW BLVD 90016
Certificate Information: 2253 S CRENSHAW BLVD 90016
- Application / Permit
- 19010-10000-00059
- Plan Check / Job No.
- B19LA00291
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 29'-9" X 43' TWO-STORY SINGLE FAMILY DWELLING AT REAR WITH ATTACHED 3 CAR GARAGE
- Permit Issued
- Issued on 8/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | ROSENDO MEDINA |
| Corrections Issued | 2/7/2019 | ROSENDO MEDINA |
| Quality Review Completed | 2/14/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 2/26/2019 | APPLICANT |
| Green Plans Picked Up | 2/26/2019 | APPLICANT |
| Applicant returned to address corrections | 6/26/2019 | ROSENDO MEDINA |
| Plan Check Approved | 6/26/2019 | ROSENDO MEDINA |
| Issued | 8/16/2019 | LADBS |
| CofO in Progress | 6/22/2021 | STUART CHAPMAN |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
| CofO Issued | 4/6/2022 | RONALD MYRICK |
| Permit Finaled | 4/6/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 4/19/2019 | KHEDER ALRAZAA |
| Address approval | Cleared | 5/16/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 5/16/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/16/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 5/16/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 6/20/2019 | GILBERT URREA |
| Housing rent stabilization | Cleared | 6/26/2019 | PHILLIP MUNGUIA |
| Highway dedication | Cleared | 7/3/2019 | ELENA LOPEZ |
Contact Information
| Contractor | E Z Builders Group Inc; Lic. No.: 792026-B | P O BOX 1844 STUDIO CITY, CA 91614 |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2019 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 10/17/2019 | Partial Approval | CHARLES BOGHOSKHAN |
| Rough-Elec/Plmb/HVAC | 10/17/2019 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Sewer | 10/17/2019 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2019 | Partial Approval | ROBERT VORHIS |
| Piling/Pier/Caisson | 10/30/2019 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 11/7/2019 | Approved | CHARLENE BUSTAMANTE |
| Footing/Foundation/Slab | 11/7/2019 | Approved | CHARLENE BUSTAMANTE |
| BUILDING-Rough-Frame | 11/21/2019 | Corrections Issued | CHARLENE BUSTAMANTE |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| Green Building Rough | 11/21/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| MERV13>=Rough | 11/21/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Verify Sprinkler Sign Off | 11/21/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| Deputy Drilled-In Anchors | 12/12/2019 | Conditional Approval | CHARLENE BUSTAMANTE |
| BUILDING-Rough-Frame | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 1/14/2020 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/14/2020 | Approved | FREDDIE RIVERA |
| Structural Steel Frame | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 1/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/5/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 2/5/2020 | Not Ready for Inspection | RUBEN SALAS |
| Structural Steel Frame | 2/5/2020 | Approved | RUBEN SALAS |
| Wood Frame | 2/5/2020 | Approved | RUBEN SALAS |
| Insulation | 2/19/2020 | Approved | CHARLENE BUSTAMANTE |
| Interior/Exterior Lathing | 2/19/2020 | Partial Approval | CHARLENE BUSTAMANTE |
| Drywall Nailing | 2/26/2020 | Approved | CHARLENE BUSTAMANTE |
| ELECTRICAL-Rough | 2/26/2020 | Approved | CHARLENE BUSTAMANTE |
| Gas Test | 2/26/2020 | Partial Approval | CHARLENE BUSTAMANTE |
| Green Building Rough | 2/26/2020 | Approved | CHARLENE BUSTAMANTE |
| PLUMBING-Rough | 2/26/2020 | Approved | CHARLENE BUSTAMANTE |
| Interior/Exterior Lathing | 4/2/2020 | Partial Approval | SABAS ALONSO |
| Shower Pan | 4/2/2020 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 4/8/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 5/29/2020 | Corrections Issued | STUART CHAPMAN |
| Gas Test | 6/16/2020 | Partial Approval | STUART CHAPMAN |
| Grounding or Bonding | 6/16/2020 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Not Ready | STUART CHAPMAN |
| Sewer | 6/16/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 6/16/2020 | Corrections Issued | STUART CHAPMAN |
| Special/Order Compliance | 6/22/2020 | Order to Comply Issued | STUART CHAPMAN |
| Gas Test | 6/25/2020 | Partial Inspection | SCOTT FINNILA |
| Sewer | 6/25/2020 | Approved | SCOTT FINNILA |
| Underground Mechanical | 6/25/2020 | Partial Approval | SCOTT FINNILA |
| Special/Order Compliance | 6/29/2020 | Approved | STUART CHAPMAN |
| Underground Mechanical | 7/6/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/13/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 8/13/2020 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Final | 9/10/2020 | Approved | STUART CHAPMAN |
| Green Building Final | 9/10/2020 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 9/10/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 9/10/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/23/2021 | Approved | STUART CHAPMAN |
| Final | 2/23/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Final | 2/23/2021 | Approved | STUART CHAPMAN |
| MERV13>=Rough | 2/23/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 2/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/23/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/23/2021 | Approved | STUART CHAPMAN |
| Final | 6/8/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 6/8/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 6/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Rec and Parks Fee Memo | 6/8/2021 | Approved | STUART CHAPMAN |
| Final | 6/21/2021 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 6/21/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 6/21/2021 | Approved | STUART CHAPMAN |