4314 W ADAMS BLVD 90018

Certificate Information: 4314 W ADAMS BLVD 90018

Application / Permit
19010-10000-00030
Plan Check / Job No.
B19LA00114
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE V-A, 37 AFFORDABLE UNITS & 1 MANAGER UNIT ( TOTAL 38 UNITS) OVER TYPE I-A GROUND LEVEL PARKING GARAGE & COMMON AREAS.
Permit Issued
Issued on 12/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/18/2019 GARO TELMI
Corrections Issued 1/28/2019 GARO TELMI
Quality Review Completed 2/1/2019 JOHN FRANCIA
Disabled Access Plans Picked Up 2/7/2019 APPLICANT
Applicant returned to address corrections 4/15/2019 GARO TELMI
Applicant returned to address corrections 5/10/2019 GARO TELMI
Applicant returned to address corrections 10/1/2019 GARO TELMI
Applicant returned to address corrections 10/17/2019 GARO TELMI
Applicant returned to address corrections 2/6/2020 GARO TELMI
Applicant returned to address corrections 9/2/2020 GARO TELMI
Applicant returned to address corrections 9/4/2020 GARO TELMI
Applicant returned to address corrections 9/23/2020 GARO TELMI
Applicant returned to address corrections 9/24/2020 GARO TELMI
Applicant returned to address corrections 10/6/2020 GARO TELMI
Applicant returned to address corrections 10/14/2020 GARO TELMI
Applicant returned to address corrections 10/19/2020 GARO TELMI
Green Plans Picked Up 11/12/2020 APPLICANT
Plan Check Approved 11/18/2020 GARO TELMI
Issued 12/17/2020 APPLICANT
Building Plans Picked Up 12/18/2020 APPLICANT
TCO Issued (Expire Date: 03-20-2023) 9/21/2022 TED RIES
CofO in Progress 4/13/2023 EDWIN GREGORYONA
Permit Finaled 4/14/2023 ERNESTO CORRAL
CofO Issued 4/14/2023 ERNESTO CORRAL
Permit Finaled 4/14/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/22/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/22/2019 JEANETTE VONG
Internal circulation Cleared 8/22/2019 EDUARDO HERMOSO
Specific Plan Cleared 8/22/2019 EDUARDO HERMOSO
Project located in CRA area Cleared 9/20/2019 JIM URQUHART
Building over 3-story or 36-ft Cleared 10/11/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/11/2019 CALOSHA APPROVED
Low Impact Development Cleared 5/9/2020 MARTIN FRAGOSO
Construction near power lines Cleared 6/24/2020 RIDWAN HARDY
Construction within easement Cleared 6/24/2020 RIDWAN HARDY
Miscellaneous Cleared 8/20/2020 SAM NAVID
Roof/Waste drainage to street Cleared 8/24/2020 CELINA MORENO
Sewer availability Cleared 9/10/2020 CELINA MORENO
Trees in Parkway Cleared 9/17/2020 JOHN KIM
Green Code Cleared 9/18/2020 GARO TELMI
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
DCP conditions approval Cleared 10/22/2020 JAMES MCCARTHY
Density Bonus 12.22.A.25 Cleared 10/22/2020 JAMES MCCARTHY
Public Housing Cleared 10/29/2020 JORGE ALCANTAR
Fire Marshall Fire Life Safety Cleared 11/4/2020 VIDAL GARCIA
Frnt yard landscape/Water mgmt Cleared 11/5/2020 LAUREN PADICK
Landscape for retaining wall Cleared 11/5/2020 LAUREN PADICK
Miscellaneous Cleared 11/5/2020 LAUREN PADICK
Opn space landscape/Water mgmt Cleared 11/5/2020 LAUREN PADICK
Specific Plan Cleared 11/5/2020 LAUREN PADICK
DAS Clearance Cleared 11/12/2020 ELIZABETH TOMS
Work Adjacent to Public Way Cleared 11/12/2020 GARO TELMI
Highway dedication Cleared 11/17/2020 RENZ SORIANO
Hold Cleared 12/30/2020 JASON SHEETS

Contact Information

Architect Aliano,, Giuseppe; Lic. No.: C26571 3408 BUENA VISTA AVE      GLENDALE, CA 91208
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 EAST FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354
Engineer Khoury,, Samir Michael; Lic. No.: C30567 5049 E LOMITA AVE      ORANGE, CA 92869
Engineer Pearson,, James Dale; Lic. No.: S4335 413 S GRAND OAKS AVE      PASADENA, CA 91107

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 2/17/2021 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/24/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/2/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/11/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 3/11/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/26/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/16/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/30/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/3/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 5/12/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/12/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/17/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/24/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 5/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/22/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/9/2021 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 7/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/20/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 7/29/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/24/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/26/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/27/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/13/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 9/22/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 11/10/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 11/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/6/2021 Conditional Approval NICK DANERI
Drywall Nailing 12/8/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/17/2021 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/7/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/26/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 2/15/2022 Approved EDWIN GREGORYONA
Pre-Inspection 3/10/2022 Approved EDWIN GREGORYONA
Light Gage Steel Frame 6/17/2022 Partial Approval EDWIN GREGORYONA
Verify Rec and Parks Fee Memo 8/8/2022 Approved EDWIN GREGORYONA
Pre-Inspection 9/1/2022 Approved EDWIN GREGORYONA
Pre-Inspection 9/16/2022 Approved EDWIN GREGORYONA
Special/Order Compliance 2/22/2023 Approved JAMES POWERS
Final 4/13/2023 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 4/13/2023 Approved EDWIN GREGORYONA
Green Building Final 4/13/2023 Approved EDWIN GREGORYONA
Green Building Rough 4/13/2023 Approved EDWIN GREGORYONA
METHANE-Barrier 4/13/2023 Approved EDWIN GREGORYONA
METHANE-Final 4/13/2023 Approved EDWIN GREGORYONA
METHANE-Rough 4/13/2023 Approved EDWIN GREGORYONA
METHANE-Subgrade 4/13/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 4/13/2023 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 4/13/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 4/13/2023 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/13/2023 Approved EDWIN GREGORYONA