107 S HEWITT ST 90012

Certificate Information: 107 S HEWITT ST 90012

Application / Permit
19010-10000-00001
Plan Check / Job No.
B19LA00014
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
New 6-story 69-unit apartment building III-A over subterranean basement garage, commercial uses I-A. TOC Tier 4 project. commercial is core and shell only
Permit Issued
Issued on 12/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 LARRY LEE
Corrections Issued 2/4/2019 LARRY LEE
Building Plans Picked Up 2/7/2019 APPLICANT
Quality Review Completed 2/11/2019 CHARLES CHANG
Disabled Access Plans Picked Up 2/28/2019 APPLICANT
Applicant returned to address corrections 7/30/2019 LARRY LEE
Applicant returned to address corrections 11/26/2019 LARRY LEE
Applicant returned to address corrections 12/17/2019 LARRY LEE
Applicant returned to address corrections 4/10/2020 LARRY LEE
Applicant returned to address corrections 4/22/2020 LARRY LEE
Applicant returned to address corrections 4/30/2020 LARRY LEE
Applicant returned to address corrections 5/1/2020 LARRY LEE
Applicant returned to address corrections 5/14/2020 LARRY LEE
Applicant returned to address corrections 6/18/2020 LARRY LEE
Green Plans Picked Up 7/1/2020 APPLICANT
Applicant returned to address corrections 7/31/2020 LARRY LEE
Applicant returned to address corrections 8/3/2020 LARRY LEE
Applicant returned to address corrections 8/20/2020 LARRY LEE
Applicant returned to address corrections 8/31/2020 LARRY LEE
Applicant returned to address corrections 10/16/2020 LARRY LEE
Applicant returned to address corrections 10/20/2020 LARRY LEE
Applicant returned to address corrections 11/13/2020 LARRY LEE
Applicant returned to address corrections 11/25/2020 LARRY LEE
Applicant returned to address corrections 12/3/2020 LARRY LEE
Plan Check Approved 12/11/2020 LARRY LEE
Issued 12/14/2020 APPLICANT
TCO Issued (Expire Date: 09-04-2023) 3/8/2023 TED RIES
CofO in Progress 7/5/2023 RAFAEL ESPINOZA
Permit Finaled 7/13/2023 ERNESTO CORRAL
CofO Issued 7/13/2023 ERNESTO CORRAL
Permit Finaled 7/13/2023 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/23/2019 ERIK BEASLEY
Address approval Cleared 9/19/2019 JEANETTE VONG
Sewer availability Cleared 10/1/2019 THOMAS LANG
ZA Case Cleared 10/8/2019 ANNA VAN
ZA Case Cleared 10/8/2019 ANNA VAN
Site Plan review Cleared 10/15/2019 SOPHIE GABEL-SCHEINBAU
Driveway location Cleared 2/12/2020 EDUARDO HERMOSO
Food Service Establishment Cleared 2/13/2020 KENNETH BROWNE
Metro Rail approval Cleared 2/14/2020 LARRY LEE
Methane Ordinance Cleared 2/18/2020 WILLIAM JOHNS
Trees in Parkway Cleared 2/26/2020 ADRIAN SANCHEZ
Green Code Cleared 3/2/2020 COLIN LOREDO
Bicycle Parking Cleared 3/13/2020 JAMES KHO
Encroachment in public way Cleared 3/13/2020 JAMES KHO
Highway dedication Cleared 4/10/2020 JEANIE LAM
Opn space landscape/Water mgmt Cleared 5/1/2020 JASON CHAN
ZI Cleared 5/1/2020 JASON CHAN
Permit Cleared 5/7/2020 JEANIE LAM
DAS Clearance Cleared 7/4/2020 ELIZABETH TOMS
Hydrant and Access approval Cleared 7/30/2020 KURT CORRAL
Low Impact Development Cleared 8/13/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/14/2020 JAMES KHO
Fire Marshall Fire Life Safety Cleared 10/5/2020 WILLIAM JOHNS
Work Adjacent to Public Way Cleared 10/13/2020 DANNY MORALES
Density Bonus 12.22.A.31 Cleared 10/29/2020 RICHARD TRUONG
Building over 3-story or 36-ft Cleared 12/2/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/2/2020 CALOSHA APPROVED
Miscellaneous Cleared 12/11/2020 JASON CHAN
Miscellaneous Cleared 12/11/2020 JASON CHAN

Contact Information

Architect Rios,, Mark William; Lic. No.: C15744 3101 W EXPOSITION PLACE      LOS ANGELES, CA 90018
Contractor West Builders Inc; Lic. No.: 825395-B 120 RAILROAD AVE      POINT RICHMOND, CA 94801
Engineer Carzzarella,, Gillian Lorraine; Lic. No.: C87787 1015 19TH ST 106      SAN DIEGO, CA 92102
Engineer Conaway,, Johnny Ray; Lic. No.: C19689 PO BOX 155      OAK VIEW, CA 93022
Engineer Faghihi,, Mahmoud; Lic. No.: S5789 888 S FIGUEROA STREET 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY FULTON, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 2/3/2021 Conditional Approval NICK DANERI
Deputy Grading 2/4/2021 Conditional Approval NICK DANERI
Deputy Grading 2/5/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 2/9/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 2/10/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/10/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 2/11/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 2/12/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 2/17/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/17/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 2/17/2021 Partial Approval NICK DANERI
METHANE-Barrier 2/17/2021 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 2/17/2021 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 2/18/2021 Conditional Approval NICK DANERI
Green Building Rough 2/18/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 2/18/2021 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/18/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 2/18/2021 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 2/19/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/19/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 2/24/2021 Partial Approval NICK DANERI
METHANE-Barrier 2/24/2021 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 2/24/2021 Not Ready for Inspection NICK DANERI
Green Building Rough 2/25/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 2/25/2021 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/25/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 2/25/2021 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 2/26/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/1/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/1/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 3/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/1/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 3/2/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/2/2021 Partial Approval NICK DANERI
Deputy Shotcrete 3/3/2021 Conditional Approval NICK DANERI
Green Building Rough 3/3/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 3/3/2021 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 3/3/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/3/2021 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 3/4/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/5/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/5/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/8/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/9/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/9/2021 Not Ready for Inspection NICK DANERI
Green Building Rough 3/10/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 3/10/2021 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 3/10/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/10/2021 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 3/11/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/12/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 3/19/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/5/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/6/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/7/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/8/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/8/2021 Not Ready for Inspection NICK DANERI
METHANE-Barrier 4/8/2021 Conditional Approval NICK DANERI
METHANE-Subgrade 4/8/2021 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 4/9/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/9/2021 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 4/9/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 4/9/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 4/9/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/9/2021 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 4/12/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/13/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/14/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/14/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/15/2021 Conditional Approval RONALD PACHECO
Deputy Shotcrete 4/16/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 4/19/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/19/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/19/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/20/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/20/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/21/2021 Partial Approval NICK DANERI
METHANE-Barrier 4/21/2021 Partial Approval NICK DANERI
METHANE-Subgrade 4/21/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/22/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/22/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/23/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/23/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/26/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/26/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/26/2021 Not Ready for Inspection NICK DANERI
Green Building Rough 4/26/2021 Not Ready for Inspection NICK DANERI
METHANE-Rough 4/26/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 4/26/2021 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 4/26/2021 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 4/27/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 4/27/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/27/2021 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/29/2021 Conditional Approval NICK DANERI
Green Building Rough 5/3/2021 Partial Inspection NICK DANERI
METHANE-Rough 5/3/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 5/3/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/3/2021 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 5/4/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 5/20/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 5/20/2021 Partial Approval NICK DANERI
Deputy Shotcrete 5/21/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 5/25/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 5/26/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 5/27/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 5/28/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 6/3/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/3/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/4/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/14/2021 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 6/15/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/16/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/21/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/22/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/22/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 6/22/2021 Approved RAFAEL ESPINOZA
METHANE-Subgrade 6/22/2021 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/23/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/24/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/28/2021 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 6/28/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 6/29/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 6/30/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/1/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/2/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/2/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/6/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/6/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/6/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/7/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/9/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/9/2021 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/12/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/12/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/13/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/15/2021 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/19/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/20/2021 No Access for Inspection ERNESTO CORRAL
Masonry Wall/Backfill 7/20/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/21/2021 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 7/21/2021 Partial Approval JONATHAN QUACH
Masonry Wall/Backfill 7/22/2021 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Masonry 7/23/2021 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 7/23/2021 Not Ready for Inspection JONATHAN QUACH
Masonry Wall/Backfill 7/26/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/27/2021 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 7/27/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/28/2021 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 7/28/2021 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 8/4/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 8/6/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 8/9/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/10/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/11/2021 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 8/11/2021 Approved RAFAEL ESPINOZA
METHANE-Rough 8/11/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 8/11/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/12/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/13/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/18/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 8/18/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/19/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/19/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/20/2021 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/27/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/31/2021 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 9/16/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/20/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/23/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 9/24/2021 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 9/24/2021 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Masonry 9/27/2021 Conditional Approval DANIEL COLLINS
Masonry Wall/Backfill 9/27/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 9/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/12/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 10/12/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/13/2021 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/14/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/15/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/18/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/18/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/18/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/18/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/20/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 10/20/2021 Corrections Issued RAFAEL ESPINOZA
Deputy Drilled-In Anchors 10/21/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/21/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/22/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 10/22/2021 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 10/22/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/22/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/25/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/25/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/29/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/29/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/1/2021 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 11/1/2021 OK to Expire Permit RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/2/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 11/3/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/5/2021 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 11/9/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 11/9/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/10/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/23/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/24/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/24/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/29/2021 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/3/2021 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/9/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/17/2021 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 12/22/2021 Partial Approval NICK DANERI
Deputy Reinf. Masonry 12/23/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/27/2021 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 12/27/2021 Partial Approval NICK DANERI
Deputy Reinf. Masonry 12/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/28/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 12/29/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 12/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/5/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/6/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/6/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 1/6/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/7/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/13/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 1/13/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/19/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 1/20/2022 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 1/20/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 1/26/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 1/26/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 1/27/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/28/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 1/31/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/31/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 1/31/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/1/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/2/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/3/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/4/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/8/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/9/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/11/2022 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 2/11/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 2/11/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 2/14/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 2/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 2/23/2022 Conditional Approval RAFAEL ESPINOZA
Wood Frame 2/23/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval RAFAEL ESPINOZA
Insulation 2/28/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/28/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/1/2022 Conditional Approval RAFAEL ESPINOZA
Wood Frame 3/3/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/8/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/8/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/9/2022 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 3/9/2022 Partial Approval RAFAEL ESPINOZA
Insulation 3/9/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/9/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/10/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/10/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/11/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval NICK DANERI
Deputy Wood Construction 3/14/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 3/14/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/15/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 3/15/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/16/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval RAFAEL ESPINOZA
Insulation 3/16/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/16/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/17/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/18/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/21/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 3/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/22/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 3/23/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 3/23/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 3/23/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/24/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/25/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/4/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/6/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval RAFAEL ESPINOZA
Insulation 4/6/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/6/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/8/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval RAFAEL ESPINOZA
Insulation 4/8/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/8/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/19/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/21/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/25/2022 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 4/27/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/3/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/5/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/6/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/9/2022 Partial Approval JAMES POWERS
Insulation 5/10/2022 Off-Hour Fees Due
Insulation 5/10/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/16/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 5/20/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/25/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/26/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/27/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/31/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/3/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/14/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/17/2022 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 6/23/2022 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 6/28/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 7/5/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/3/2022 Partial Approval NICK DANERI
Light Gage Steel Frame 8/8/2022 Not Ready for Inspection TED RIES
Light Gage Steel Frame 8/10/2022 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 8/22/2022 Partial Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 8/29/2022 Approved RAFAEL ESPINOZA
Light Gage Steel Frame 8/30/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/1/2022 Approved RAFAEL ESPINOZA
Wood Frame 9/9/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/13/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/13/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 9/23/2022 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 9/23/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/23/2022 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 10/18/2022 Approved RAFAEL ESPINOZA
Drywall Nailing 10/25/2022 Approved RAFAEL ESPINOZA
Final 10/25/2022 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/25/2022 Approved RAFAEL ESPINOZA
Green Building Final 10/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 10/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/25/2022 Conditional Approval RAFAEL ESPINOZA
Final 10/31/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/31/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 11/9/2022 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Approved RAFAEL ESPINOZA
Green Building Final 11/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 11/9/2022 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 11/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 11/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/9/2022 Approved RAFAEL ESPINOZA
Wood Frame 11/9/2022 Approved RAFAEL ESPINOZA
Green Building Final 11/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 11/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 11/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 11/22/2022 Partial Approval RAFAEL ESPINOZA
Final 12/15/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 12/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 12/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 12/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 12/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 1/3/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 1/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 1/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 1/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 1/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 1/4/2023 Partial Inspection RAFAEL ESPINOZA
Final 2/9/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Final 2/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 2/9/2023 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 2/9/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 2/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 7/5/2023 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 7/5/2023 Approved RAFAEL ESPINOZA
Smoke Detectors 7/5/2023 Approved RAFAEL ESPINOZA