2315 S BEVERWIL DR 90034

Certificate Information: 2315 S BEVERWIL DR 90034

Application / Permit
18047-30000-02138
Plan Check / Job No.
B18WL07321
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL and spa.
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 12/10/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 12/13/2018 CORA JOHNSON
Green Plans Picked Up 5/7/2019 APPLICANT
Applicant returned to address corrections 5/16/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/8/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/17/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/13/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/31/2022 APPLICANT
Plan Check Approved 4/5/2022 CHIHARU SUZUKI
Issued 4/5/2022 APPLICANT
CofO in Progress 12/7/2022 OGANES TARAKHCHYAN
No Progress 12/8/2022 KENNETH NAGLE
CofO in Progress 12/20/2022 MICHAEL PELHAM
Permit Finaled 2/8/2023 DANIEL ORRANTE
CofO Issued 2/8/2023 DANIEL ORRANTE
Permit Finaled 2/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/29/2021 KAMRAN GHOTBI RAVANDI

Contact Information

Contractor Owner-Builder       ,
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Proofing Certificate 5/13/2022 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 5/13/2022 Corrections Issued KEVIN SARGSYAN
Pool Piping 5/18/2022 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 5/18/2022 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 5/24/2022 Approved KENNETH NAGLE
Deck 7/25/2022 Corrections Issued KEVIN SARGSYAN
Grounding or Bonding 7/28/2022 Approved OGANES TARAKHCHYAN
Enclosure/Fence 10/21/2022 Corrections Issued OGANES TARAKHCHYAN
Enclosure/Fence 11/8/2022 Approved OGANES TARAKHCHYAN
Equipment Noise Level 11/15/2022 Approved ZEYDI STEWART
Excavation/Setback/Form/Re-Bar 11/16/2022 Approved OGANES TARAKHCHYAN
Final 11/16/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved OGANES TARAKHCHYAN
Final 11/22/2022 Corrections Issued OGANES TARAKHCHYAN
Final 12/6/2022 OK to Issue CofO OGANES TARAKHCHYAN