700 N BUNDY DR 90049

Certificate Information: 700 N BUNDY DR 90049

Application / Permit
18047-30000-02027
Plan Check / Job No.
B18WL06978
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA. 34'-8" X 18'. PER STANDARD PLANS #268
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
Issued on 5/28/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/21/2018 ALFREDO JARA
Corrections Issued 11/28/2018 ALFREDO JARA
Quality Review Completed 12/7/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/24/2020 ALFREDO JARA
No Progress 4/24/2020 ALFREDO JARA
Plan Check Approved 5/18/2020 ALFREDO JARA
Issued 5/28/2020 APPLICANT
Building Plans Picked Up 12/7/2021 APPLICANT

Permit Application Clearance Information

Disturb/Remove Protected Trees Cleared 3/2/2020 STEPHEN DUPREY
Grading Pre-Inspection Cleared 4/24/2020 ALFREDO JARA

Contact Information

Contractor Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 9018 BALBOA BLVD SUITE 353      NORTHRIDGE, CA 91325
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2021 Approved CARLOS MATAMOROS
Pool Piping 2/22/2022 Approved CARLOS MATAMOROS
Pre-Gunite 2/22/2022 Corrections Issued CARLOS MATAMOROS
Deputy Shotcrete 2/25/2022 Approved MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/14/2022 Not Ready for Inspection JUAN VALENZUELA
Enclosure/Fence 3/18/2022 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/18/2022 Partial Approval CARLOS MATAMOROS
Deck 1/17/2023 Approved CARLOS MATAMOROS
Final 8/4/2023 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Not Ready CARLOS MATAMOROS
Deck 8/24/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/24/2023 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 8/24/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 8/24/2023 Not Ready for Inspection CARLOS MATAMOROS