1455 N DONHILL DR 90210
Certificate Information: 1455 N DONHILL DR 90210
- Application / Permit
- 18047-30000-01947
- Plan Check / Job No.
- B18WL06758
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Pool and spa per standard plan 254
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | TARIK SAOUD |
| Corrections Issued | 11/12/2018 | TARIK SAOUD |
| Quality Review Completed | 11/21/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/24/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 6/24/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/20/2021 | TARIK SAOUD |
| Plan Check Approved | 11/3/2021 | TARIK SAOUD |
| Issued | 1/13/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 1/3/2024 | BRENDAN LOONEY |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
| CofO Issued | 1/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/30/2019 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/24/2020 | TARIK SAOUD |
Contact Information
| Contractor | Marquel Group Inc; Lic. No.: 1059595-B | 5231 VIRGINIA AVE LOS ANGELES, CA 90029 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/14/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Shotcrete | 9/26/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 10/14/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 5/10/2023 | Corrections Issued | BRENDAN LOONEY |
| Enclosure/Fence | 5/31/2023 | Corrections Issued | STEPHANIE SWANSON |
| Enclosure/Fence | 6/7/2023 | Conditional Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | BRENDAN LOONEY |
| Final | 10/2/2023 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | BRENDAN LOONEY |
| Final | 11/6/2023 | Conditional Approval | BRENDAN LOONEY |
| Final | 1/3/2024 | OK to Issue CofO | BRENDAN LOONEY |