1608 N AMALFI DR 90272

Certificate Information: 1608 N AMALFI DR 90272

Application / Permit
18047-30000-00217
Plan Check / Job No.
B18WL00654
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 28' x 14' POOL
Permit Issued
Issued on 2/7/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2018 APPLICANT
Assigned to Plan Check Engineer 1/31/2018 BRYAN OSORIO
Plan Check Approved 2/7/2018 KAVIAN REFAHI
Issued 2/7/2018 LADBS
CofO in Progress 4/21/2023 KEVIN SARGSYAN
Permit Finaled 4/22/2023 DANIEL ORRANTE
CofO Issued 4/22/2023 DANIEL ORRANTE
Permit Finaled 4/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 1/31/2018 SARAH GOLDMAN
Miscellaneous Cleared 1/31/2018 SARAH GOLDMAN
Grading Pre-Inspection Cleared 2/7/2018 GRANT WOODS

Contact Information

Contractor Mr Carlos Pools And Construction Inc; Lic. No.: 385622-B 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Biedenbach, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2020 Not Ready for Inspection DANNY TOLENTINO
Pre-Inspection 6/5/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/27/2022 Corrections Issued JOHN KIDWELL
Pool Piping 5/27/2022 Partial Approval JOHN KIDWELL
Rough-Electrical 5/27/2022 Partial Approval JOHN KIDWELL
Rough-Plumbing 5/27/2022 Partial Approval JOHN KIDWELL
Enclosure/Fence 8/11/2022 Corrections Issued JUAN VALENZUELA
Deck 8/15/2022 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 8/15/2022 Not Ready for Inspection KEVIN SARGSYAN
Deck 8/17/2022 Approved JUAN VALENZUELA
Enclosure/Fence 8/17/2022 Approved JUAN VALENZUELA
Pre-Gunite 8/17/2022 Approved JUAN VALENZUELA
Final 1/23/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Not Ready KEVIN SARGSYAN
Final 4/20/2023 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved KEVIN SARGSYAN