8856 W SKYLINE DR 90046

Certificate Information: 8856 W SKYLINE DR 90046

Application / Permit
18047-30000-00171
Plan Check / Job No.
B18WL00549
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool and spa per engineering.
Permit Issued
Issued on 2/21/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2018 APPLICANT
Assigned to Plan Check Engineer 2/2/2018 MANUEL GARCIA
Corrections Issued 2/7/2018 MANUEL GARCIA
Quality Review Completed 2/9/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/9/2018 APPLICANT
Plan Check Approved 2/15/2018 MANUEL GARCIA
Issued 2/21/2018 LADBS
CofO in Progress 4/11/2024 STUART CHAPMAN
Permit Finaled 5/21/2024 RONALD MYRICK
CofO Issued 5/21/2024 RONALD MYRICK
Permit Finaled 5/21/2024 RONALD MYRICK

Permit Application Clearance Information

CPC Cleared 2/15/2018 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 2/15/2018 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 2/15/2018 MANUEL GARCIA
Miscellaneous Cleared 2/15/2018 SARAH GOLDMAN
Miscellaneous Cleared 2/15/2018 SARAH GOLDMAN
Miscellaneous Cleared 2/15/2018 SARAH GOLDMAN
Sewer availability Cleared 2/15/2018 HISASHI KOBAYAKAWA
Specific Plan Cleared 2/15/2018 SARAH GOLDMAN

Contact Information

Architect Getov, Pavel Panayotov; Lic. No.: C32093 3565 REDWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Gould Engineering Inc; Lic. No.: 462007-A P O BOX 647      SAN PEDRO, CA 90733
Engineer Resnick, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/22/2018 Approved RONALD COWAN
Deck 7/17/2018 Not Ready for Inspection RONALD COWAN
Deck 10/16/2018 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 6/10/2021 Approved RAUL BARAJAS
Final 6/10/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Not Ready RAUL BARAJAS
Enclosure/Fence 8/16/2022 Partial Inspection RAUL BARAJAS
Pre-Inspection 8/16/2022 Partial Inspection RAUL BARAJAS
Enclosure/Fence 2/21/2023 Approved RAUL BARAJAS
Grounding or Bonding 3/20/2023 Corrections Issued RAUL BARAJAS
Final 7/14/2023 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved RAUL BARAJAS
Final 8/21/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 4/11/2024 Approved STUART CHAPMAN
Final 4/11/2024 OK to Issue CofO STUART CHAPMAN