13505 W LUCCA DR 90272
Certificate Information: 13505 W LUCCA DR 90272
- Application / Permit
- 18047-20000-01979
- Plan Check / Job No.
- B18VN18461
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (40' X 20'), SPA (7' X 8') & ATTACHED COLD POOL (5' X 5') W/ 5' HIGH WATER FALL FEATURE PER ENG'R DESIGN
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO in Progress on 8/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | ALDOUS CHIC |
| Corrections Issued | 11/13/2018 | ALDOUS CHIC |
| Quality Review Completed | 11/15/2018 | OMID HEDAYAT |
| Green Plans Picked Up | 11/15/2018 | APPLICANT |
| Building Plans Picked Up | 12/20/2018 | APPLICANT |
| Applicant returned to address corrections | 9/17/2019 | ALDOUS CHIC |
| Plan Check Approved | 12/4/2020 | NILOOFAR MEHRAIN |
| Issued | 12/8/2021 | APPLICANT |
| CofO in Progress | 8/5/2025 | KEVIN SARGSYAN |
| No Progress | 8/6/2025 | KENNETH NAGLE |
| CofO in Progress | 8/6/2025 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/5/2018 | ALDOUS CHIC |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2019 | CELINA MORENO |
| Miscellaneous | Cleared | 7/1/2019 | ANNA VAN |
| ZA Case | Cleared | 7/1/2019 | ANNA VAN |
| Miscellaneous | Cleared | 9/30/2020 | NIKTA MOUSAVI |
| Miscellaneous | Cleared | 12/4/2020 | ALDOUS CHIC |
Contact Information
| Contractor | Jensen Const Inc; Lic. No.: 787346-B | 1409 FOOTHILL BLVD SUITE 204 LA CANADA, CA 91011 |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 555 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
| Engineer | Pond,, Britten Reis; Lic. No.: C71221 | 1024 CROWN HILL DR SIMI VALLEY, CA 93063 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/16/2023 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 2/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Gunite | 3/30/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Gunite | 4/7/2023 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 4/12/2023 | No Access for Inspection | KENNETH NAGLE |
| Gas Piping or Gas Test | 9/6/2023 | Partial Approval | KENNETH NAGLE |
| Enclosure/Fence | 6/3/2024 | Approved | EVAN COOPER |
| Pool Equipment Noise Test | 9/12/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 1/31/2025 | Approved | JESUS RODRIGUEZ |
| Final | 1/31/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Pre-Gunite | 1/31/2025 | Partial Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 4/2/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 4/2/2025 | Not Ready for Inspection | HERBERT GIRON |
| Final | 7/21/2025 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 7/21/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 8/4/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| Pre-Gunite | 8/4/2025 | Approved | KEVIN SARGSYAN |