700 S MANHATTAN PL 90005

Certificate Information: 700 S MANHATTAN PL 90005

Application / Permit
18047-20000-00487
Plan Check / Job No.
B18VN04189
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Apartment
Primary Use
(4) Pool/Spa - Public
Work Description
PROPOSED NEW 18' X 40' POOL PER ENGINEERING
Permit Issued
Issued on 9/18/2018
Issuing Office
Valley
Current Status
Permit Finaled on 2/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 RAPHAEL ROSAS
Disabled Access Plans Picked Up 4/17/2018 APPLICANT
Corrections Issued 4/20/2018 RAPHAEL ROSAS
Quality Review Completed 4/27/2018 STEVEN KIM
Building Plans Picked Up 4/27/2018 APPLICANT
Plan Check Approved 9/18/2018 RAPHAEL ROSAS
Issued 9/18/2018 LADBS
Permit Finaled 2/4/2020 LARRY ARNICK

Permit Application Clearance Information

Miscellaneous Cleared 4/26/2018 DENNIS CHEW
ZA Case Cleared 4/26/2018 DENNIS CHEW
ZI Cleared 4/26/2018 DENNIS CHEW
Project located in CRA area Cleared 5/1/2018 JIM URQUHART
DAS Clearance Cleared 8/23/2018 NORLITO MEDRANO
Public Swimming Pool approval Cleared 9/18/2018 LACDHS APPROVED

Contact Information

Contractor Addison Pools Inc; Lic. No.: 753417-B 4363 WOODMAN AVENUE      SHERMAN OAKS, CA 91423
Engineer Chamberlain, Craig Morgan; Lic. No.: S4588 1466 5TH ST      MANHATTAN BEACH, CA 90266
Engineer Lacher, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/2/2019 Approved LARRY ARNICK
Deputy Shotcrete 4/8/2019 Conditional Approval LARRY ARNICK
Gas Piping or Gas Test 10/10/2019 Not Ready for Inspection LARRY ARNICK
Pool Piping 10/10/2019 Not Ready for Inspection LARRY ARNICK
Rough-Plumbing 10/10/2019 Not Ready for Inspection LARRY ARNICK
Enclosure/Fence 10/31/2019 Approved LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/26/2019 Corrections Issued JONATHAN QUACH
Final 11/26/2019 Partial Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/26/2019 SGSOV Not Ready JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 1/31/2020 Conditional Approval TIMOTHY BUXTON
Final 1/31/2020 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 1/31/2020 SGSOV Approved TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 2/4/2020 Approved TIMOTHY BUXTON
Final 2/4/2020 Conditional Approval TIMOTHY BUXTON