9262 W NIGHTINGALE DR 90069

Certificate Information: 9262 W NIGHTINGALE DR 90069

Application / Permit
18047-10000-02231
Plan Check / Job No.
B18LA26166
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL, SPA AND WATER FEATURE PER ENGINEER'S DETAIL. POOL/SPA INFINITY 4'-6" DEPTH 104' X 18'.
Permit Issued
Issued on 2/12/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 ARSALAN SHABESTARI
Corrections Issued 1/2/2019 ARSALAN SHABESTARI
Quality Review Completed 1/9/2019 FELIX FIGUEROA
Building Plans Picked Up 1/10/2019 APPLICANT
Plan Check Approved 2/12/2019 ARSALAN SHABESTARI
Issued 2/12/2019 LADBS
CofO in Progress 7/16/2021 BRAD BESCOS
Permit Finaled 7/20/2021 DEROLD HAUFF
CofO Issued 7/20/2021 DEROLD HAUFF
Permit Finaled 7/20/2021 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Fluid Dynamics Pool And Spa Inc; Lic. No.: 809954-C53 620 E WALNUT AVENUE #B      FULLERTON, CA 92831
Engineer Jansse,, Dirk Jacob; Lic. No.: C76034 140 LOMAS SANTA FE DR UNIT 202      SOLANA BEACH, CA 92075

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 8/26/2019 Approved RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 9/18/2019 Partial Approval RICHARD STEINBACH
Pool Piping 9/18/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 10/1/2019 Partial Approval RICHARD STEINBACH
Grounding or Bonding 10/1/2019 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 10/2/2019 Conditional Approval RICHARD STEINBACH
Pool Piping 11/20/2019 Approved RICHARD STEINBACH
Pool Piping 12/12/2019 Approved RICHARD STEINBACH
Pool Piping 8/3/2020 Partial Approval RAUL BARAJAS
Rough-Electrical 8/3/2020 Not Ready for Inspection RAUL BARAJAS
Rough-Plumbing 9/1/2020 Partial Approval ENRIQUE MIRELES
Enclosure/Fence 1/26/2021 Partial Inspection RAUL BARAJAS
Enclosure/Fence 2/10/2021 Not Ready for Inspection RAUL BARAJAS
Enclosure/Fence 2/23/2021 Approved RAUL BARAJAS
Final 4/22/2021 Partial Approval RAUL BARAJAS
Final 5/19/2021 Not Ready for Inspection RAUL BARAJAS
Final 6/17/2021 Partial Inspection RAUL BARAJAS
Final 7/12/2021 Partial Approval BRAD BESCOS
Final 7/14/2021 OK to Issue CofO BRAD BESCOS