509 N LAS PALMAS AVE 90004
Certificate Information: 509 N LAS PALMAS AVE 90004
- Application / Permit
- 18047-10000-02192
- Plan Check / Job No.
- B18LA25603
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 2) NEW SWIMMING POOL
- Permit Issued
- Issued on 6/6/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2018 | RACHEL BEYENE |
| Corrections Issued | 12/19/2018 | RACHEL BEYENE |
| Quality Review Completed | 12/26/2018 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/27/2018 | APPLICANT |
| Applicant returned to address corrections | 1/8/2019 | RACHEL BEYENE |
| Green Plans Picked Up | 1/18/2019 | APPLICANT |
| Applicant returned to address corrections | 5/10/2019 | RACHEL BEYENE |
| Applicant returned to address corrections | 5/21/2019 | RACHEL BEYENE |
| Plan Check Approved | 5/30/2019 | RAHEL BEYENE |
| Issued | 6/6/2019 | LADBS |
| CofO in Progress | 3/16/2022 | BRIAN SULLIVAN |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
| CofO Issued | 8/11/2022 | DEROLD HAUFF |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 4/4/2019 | ELENA LOPEZ |
| ZA Case | Cleared | 4/5/2019 | DIANA JIMENEZ |
| HPOZ | Cleared | 4/24/2019 | SUKI GERSHENHORN |
| Hist. Property Cntrct Mgr Appr | Cleared | 4/24/2019 | SUKI GERSHENHORN |
| GPI Written Notices | Cleared | 5/30/2019 | RAHEL BEYENE |
| Low Impact Development | Cleared | 5/30/2019 | RYAN HUDSON |
| Excavation more than 5-ft deep | Cleared | 6/5/2019 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/5/2019 | RAHEL BEYENE |
| ZI | Cleared | 6/5/2019 | GRACIELA ACOSTA |
Contact Information
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11661 SAN VICENTE BLVD STE 302 LOS ANGELES, CA 90049 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 3/6/2020 | Partial Approval | RICHARD STEINBACH |
| Special/Order Compliance | 3/6/2020 | Corrections Issued | RICHARD STEINBACH |
| Pre-Gunite | 4/3/2020 | Approved | ROBERT CORNELL |
| Deck | 5/7/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Grounding or Bonding | 5/7/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deck | 5/13/2021 | Approved | BRIAN SULLIVAN |
| Grounding or Bonding | 5/13/2021 | Approved | BRIAN SULLIVAN |
| Enclosure/Fence | 7/1/2021 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 7/9/2021 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Approved | BRIAN SULLIVAN |
| Final | 3/16/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | BRIAN SULLIVAN |