2300 N APOLLO DR 90046

Certificate Information: 2300 N APOLLO DR 90046

Application / Permit
18047-10000-02076
Plan Check / Job No.
B18LA23987
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED POOL AND DECK AT REAR OF (E) SFD.
Permit Issued
Issued on 3/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 LAWRENCE QUIRANTE
Corrections Issued 12/3/2018 LAWRENCE QUIRANTE
Quality Review Completed 12/7/2018 GARO TELMI
Building Plans Picked Up 12/11/2018 APPLICANT
Plan Check Approved 3/18/2019 LAWRENCE QUIRANTE
Issued 3/20/2019 LADBS
CofO in Progress 1/27/2023 STUART CHAPMAN
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/14/2019 ELENA LOPEZ
Grading Pre-Inspection Cleared 3/14/2019 PATRICK MISCHLICH
Low Impact Development Cleared 3/14/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/14/2019 ELENA LOPEZ
Sewer availability Cleared 3/14/2019 ELENA LOPEZ

Contact Information

Architect Sukho, Jang; Lic. No.: C34156       ,
Contractor Kouby Builders Inc; Lic. No.: 1015338-B 9882 CARMELITA AVE      BEVERLY HILLS, CA 90210
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Robinson,, Rory Anthony; Lic. No.: GE2491 4000-A SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/21/2020 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/6/2020 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 12/29/2020 No Access for Inspection RICHARD STEINBACH
Deck 5/24/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 5/24/2021 Partial Approval RAUL BARAJAS
Pre-Gunite 5/24/2021 Not Ready for Inspection RAUL BARAJAS
Rough-Electrical 5/24/2021 Not Ready for Inspection RAUL BARAJAS
Rough-Plumbing 5/24/2021 Not Ready for Inspection RAUL BARAJAS
Grounding or Bonding 6/2/2021 Approved RAUL BARAJAS
Pool Piping 6/2/2021 Approved RAUL BARAJAS
Pre-Gunite 6/2/2021 Approved RAUL BARAJAS
Rough-Electrical 6/2/2021 Partial Approval RAUL BARAJAS
Rough-Plumbing 6/2/2021 Approved RAUL BARAJAS
Deputy Other (see comments) 8/2/2021 Conditional Approval RAUL BARAJAS
Deck 8/3/2021 Approved RAUL BARAJAS
Deputy Other (see comments) 8/10/2021 Conditional Approval RAUL BARAJAS
Deck 1/7/2022 Approved BRIAN SULLIVAN
Grounding or Bonding 1/7/2022 Approved BRIAN SULLIVAN
Enclosure/Fence 1/19/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/19/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/19/2022 SGSOV Not Ready RAUL BARAJAS
Equipment Noise Level 3/24/2022 Approved JUSTIN CURTIS
Pool Equipment Noise Test 3/24/2022 Approved JUSTIN CURTIS
Final 4/27/2022 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved RAUL BARAJAS
Final 11/15/2022 Corrections Issued RAUL BARAJAS
Final 11/28/2022 Corrections Issued BRIAN SULLIVAN
Final 12/5/2022 Conditional Approval RAUL BARAJAS
Final 1/24/2023 Not Ready for Inspection STUART CHAPMAN
Final 1/27/2023 OK to Issue CofO STUART CHAPMAN