10591 W ROCCA WAY 90077
Certificate Information: 10591 W ROCCA WAY 90077
- Application / Permit
- 18047-10000-01530
- Plan Check / Job No.
- B18LA17368
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 6'X9' SPA. **3 OF 6**
- Permit Issued
- Issued on 10/30/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2018 | APPLICANT |
| Green Plans Picked Up | 9/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | MARVEL DELACRUZ |
| Corrections Issued | 9/9/2018 | MARVEL DELACRUZ |
| Quality Review Completed | 9/13/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 9/19/2018 | APPLICANT |
| Applicant returned to address corrections | 12/14/2018 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/25/2019 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/13/2019 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/30/2019 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/16/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 10/18/2019 | MARVEL DELACRUZ |
| Issued | 10/30/2019 | LADBS |
| CofO in Progress | 2/22/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Spann, Anthony Paul; Lic. No.: C17602 | 921 DE LA VINA STREET HARRISON DESIGN ASSOCIATES SANTA BARBARA, CA 93101 |
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 6/16/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Pre-Gunite | 6/17/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Grounding or Bonding | 6/22/2020 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 6/22/2020 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Gunite | 6/22/2020 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 6/22/2020 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 6/24/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Pool Piping | 7/31/2020 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Grounding or Bonding | 5/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 5/4/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 5/4/2021 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 5/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deck | 2/15/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 9/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 9/26/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 9/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/10/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/10/2023 | Approved | CHRISTOPHER WILSON |
| Final | 10/10/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 10/10/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pool Equipment Noise Test | 10/12/2023 | Approved | JUAN ESCOTO DELGADO |
| Final | 2/21/2024 | OK to Issue CofO | CHRISTOPHER WILSON |