1723 N SAN YSIDRO DR 90210
Certificate Information: 1723 N SAN YSIDRO DR 90210
- Application / Permit
- 18047-10000-00610
- Plan Check / Job No.
- B18LA06254
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 40' X 14' POOL WITH 8' X 8' SPA
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2018 | MICHAEL PEREZ |
| Corrections Issued | 4/25/2018 | MICHAEL PEREZ |
| Quality Review Completed | 5/4/2018 | KESETE HAREGOT |
| Building Plans Picked Up | 5/4/2018 | APPLICANT |
| Plan Check Approved | 12/13/2019 | MICHAEL PEREZ |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 7/12/2024 | SEAN HAUPT |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
| CofO Issued | 7/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 6/4/2018 | SARAH GOLDMAN |
| Address approval | Cleared | 12/3/2019 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/3/2019 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/3/2019 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/3/2019 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 12/11/2019 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 12/13/2019 | MICHAEL PEREZ |
Contact Information
| Engineer | Shirley, Peter Franklin; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 8/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 8/24/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 8/24/2021 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 8/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 8/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 9/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 9/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 3/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 3/23/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 3/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Piping or Gas Test | 4/1/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Piping or Gas Test | 4/4/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deck | 10/25/2023 | Corrections Issued | BRENDAN LOONEY |
| Enclosure/Fence | 4/15/2024 | Approved | CARLOS MATAMOROS |
| Pool Piping | 4/15/2024 | Approved | CARLOS MATAMOROS |
| Pool/Spa Cover | 4/15/2024 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 5/9/2024 | Approved | MIKE WANG |
| Excavation/Setback/Form/Re-Bar | 7/11/2024 | Approved | SEAN HAUPT |
| Final | 7/11/2024 | OK to Issue CofO | SEAN HAUPT |