700 N BUNDY DR 90049
Certificate Information: 700 N BUNDY DR 90049
- Application / Permit
- 18030-30000-06729
- Plan Check / Job No.
- B18WL06254
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR NEW RETAINING WALLS, EXISTING POOL BACKFILL AND NEW POOL PER
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/30/2025
Permit Application Status History
| Submitted | 9/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | TARIK SAOUD |
| Corrections Issued | 10/15/2018 | TARIK SAOUD |
| Quality Review Completed | 10/24/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/29/2018 | APPLICANT |
| Plan Check Approved | 2/3/2020 | TARIK SAOUD |
| Issued | 2/4/2020 | LADBS |
| Permit Finaled | 4/29/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/13/2019 | TARIK SAOUD |
| Low Impact Development | Cleared | 8/6/2019 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 5/11/2021 | Partial Inspection | BRIAN OLSON |
| Initial Grading | 5/11/2021 | Approved | BRIAN OLSON |
| Excavation | 5/21/2021 | Partial Approval | BRIAN OLSON |
| Fill/Backfill | 10/7/2021 | Not Ready for Inspection | AL GAMBLE |
| Initial Grading | 10/7/2021 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 10/8/2021 | Partial Approval | MATTHEW JENKINS |
| Fill/Backfill | 10/8/2021 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 10/19/2021 | Not Ready for Inspection | CHARLES POWELL |
| Excavation | 10/19/2021 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Grading | 11/15/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 11/16/2021 | Corrections Issued | CHARLES POWELL |
| Bottom/Toe | 11/17/2021 | Partial Approval | CHARLES POWELL |
| Excavation | 11/17/2021 | Partial Approval | CHARLES POWELL |
| Rough | 11/17/2021 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 12/7/2021 | Partial Approval | CHARLES POWELL |
| Deputy Other (see comments) | 12/7/2021 | Partial Approval | CHARLES POWELL |
| Fill/Backfill | 1/10/2022 | Not Ready for Inspection | CHARLES POWELL |
| Sub-Drain | 1/10/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 1/25/2022 | Not Ready for Inspection | CHARLES POWELL |
| Bottom/Toe | 2/2/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 2/2/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 8/4/2023 | Corrections Issued | VASIL MIHALEV |
| Final | 8/4/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 8/4/2023 | Approved | VASIL MIHALEV |
| Approved Compaction Report | 8/15/2023 | Approved | VASIL MIHALEV |
| Bottom/Toe | 8/24/2023 | Corrections Issued | CHARLES POWELL |
| Final | 8/24/2023 | Not Ready for Inspection | CHARLES POWELL |
| Irrigation/Landscape | 9/19/2023 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 4/22/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 4/22/2024 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 4/29/2025 | Approved | JOHNNY MIRANDA |
| Final | 4/29/2025 | Permit Finaled | JOHNNY MIRANDA |