179 S ROCKINGHAM AVE 90049
Certificate Information: 179 S ROCKINGHAM AVE 90049
- Application / Permit
- 18030-30000-06647
- Plan Check / Job No.
- B18WL06186
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW ACC. BUILDING, POOL/SPA, SITE RETAINING WALLS.
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 9/5/2024
Permit Application Status History
| Submitted | 9/25/2018 | APPLICANT |
| Green Plans Picked Up | 10/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 11/6/2018 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 11/7/2018 | JASON HEALEY |
| Applicant returned to address corrections | 12/11/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/1/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/9/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/26/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/7/2020 | CHIHARU SUZUKI |
| Issued | 12/8/2020 | APPLICANT |
| Building Plans Picked Up | 12/9/2020 | APPLICANT |
| Permit Finaled | 9/5/2024 | VASIL MIHALEV |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 4/10/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/9/2020 | Approved | MATTHEW JENKINS |
| Sub-Drain | 4/27/2021 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 11/2/2021 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 12/22/2021 | Partial Approval | JONATHAN HOM |
| Special/Order Compliance | 2/16/2022 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 5/16/2022 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 5/20/2022 | Corrections Issued | CHARLES POWELL |
| Special/Order Compliance | 6/6/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 7/12/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Sub-Drain | 8/1/2022 | Partial Approval | TIMOTHY POWELL |
| Sub-Drain | 10/5/2022 | Partial Approval | TIMOTHY POWELL |
| Bottom/Toe | 3/29/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 3/29/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Initial Grading | 3/29/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 6/15/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 9/25/2023 | Approved | CHARLES POWELL |
| Bottom/Toe | 9/5/2024 | Approved | VASIL MIHALEV |
| Final | 9/5/2024 | Permit Finaled | VASIL MIHALEV |
| Rough | 9/5/2024 | Approved | VASIL MIHALEV |