13187 W CHALON ROAD 90049
Certificate Information: 13187 W CHALON ROAD 90049
- Application / Permit
- 18030-30000-02499
- Plan Check / Job No.
- B18WL02373
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW SFD, SITE RETAINING WALLS, AND POOL AND SPA.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/14/2023
Permit Application Status History
| Submitted | 4/13/2018 | APPLICANT |
| Green Plans Picked Up | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 5/8/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/14/2018 | APPLICANT |
| Quality Review Completed | 7/24/2018 | JASON HEALEY |
| Applicant returned to address corrections | 7/26/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/31/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/6/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/17/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/5/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/26/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/8/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/8/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/14/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/26/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/1/2021 | KAVIAN REFAHI |
| Plan Check Approved | 7/12/2021 | KAVIAN REFAHI |
| No Progress | 7/12/2021 | KAVIAN REFAHI |
| Plan Check Approved | 7/12/2021 | KAVIAN REFAHI |
| Issued | 8/9/2021 | APPLICANT |
| Permit Finaled | 6/13/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2018 | STEVEN JIN |
| Watercourse | Cleared | 6/29/2021 | NIKTA MOUSAVI |
| Excavation more than 5-ft deep | Cleared | 7/12/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 7/12/2021 | KAMRAN GHOTBI RAVANDI |
Contact Information
| Contractor | Tallen & Tyce Development Inc; Lic. No.: 1029383-B | 15260 VENTURA BLVD #845 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/16/2021 | Approved | MATTHEW JENKINS |
| Rough | 12/9/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 12/9/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 12/13/2021 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/27/2022 | Partial Approval | TIMOTHY POWELL |
| Sub-Drain | 6/22/2022 | Partial Approval | TIMOTHY POWELL |
| Approved Compaction Report | 3/30/2023 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 6/13/2023 | Approved | RUSSELL BONVOULOIR |
| FLOOD-Elevation Certificate | 6/13/2023 | Approved | RUSSELL BONVOULOIR |
| Final | 6/13/2023 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 6/13/2023 | Approved | RUSSELL BONVOULOIR |