1756 N BEVERLY GLEN BLVD 90077
Certificate Information: 1756 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 18030-20000-07115
- Plan Check / Job No.
- B18VN17781
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING, CUT & BACKFILL RETAINING WALL, CUT1594CY, FILL571CY, REMOVE & RECOMPACTED TO GRADE MAX.5'DEEP. 1112CY. EXPORT 988 CY(SEE COMMENTS)
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Valley
- Current Status
- Issued on 10/28/2020
Permit Application Status History
| Submitted | 10/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | CHON CHIO KUO |
| Corrections Issued | 11/7/2018 | CHON CHIO KUO |
| Quality Review Completed | 11/8/2018 | STEVEN KIM |
| Building Plans Picked Up | 11/13/2018 | APPLICANT |
| Green Plans Picked Up | 11/27/2018 | APPLICANT |
| Applicant returned to address corrections | 1/10/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/7/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/14/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/27/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/13/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/28/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/25/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/22/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/20/2020 | CHON CHIO KUO |
| Plan Check Approved | 7/27/2020 | CHON CHIO KUO |
| Issued | 10/28/2020 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/14/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 11/14/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 11/15/2018 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 11/21/2018 | SHEILA GERSHON |
| GPI Written Notices | Cleared | 2/27/2019 | CHON CHIO KUO |
| Miscellaneous | Cleared | 2/27/2019 | CHON CHIO KUO |
| Excavation more than 5-ft deep | Cleared | 3/28/2019 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 4/18/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/18/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 11/13/2020 | Corrections Issued | BRIAN OLSON |
| Initial Grading | 11/16/2020 | Partial Approval | BRIAN OLSON |
| Rough | 12/2/2020 | Partial Inspection | BRIAN OLSON |
| Sub-Drain | 12/29/2020 | Partial Approval | BRIAN OLSON |
| Sub-Drain | 1/11/2021 | Partial Approval | BRIAN OLSON |
| Sub-Drain | 2/1/2021 | Partial Approval | KIRK LINKLATER |
| Drainage Devices/Catch Basin | 4/8/2021 | Corrections Issued | BRIAN OLSON |
| Drainage Devices/Catch Basin | 4/26/2021 | Partial Inspection | BRIAN OLSON |
| Sub-Drain | 9/6/2023 | Partial Approval | CHARLES POWELL |