14060 N CANDLEWOOD DR 91342

Certificate Information: 14060 N CANDLEWOOD DR 91342

Application / Permit
18030-20000-07109
Plan Check / Job No.
B18VN17770
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
POOL EXCAV. & POOL/SPA WALLS BACKFILL.
Permit Issued
Issued on 7/23/2020
Issuing Office
Current Status
Issued on 7/23/2020

Permit Application Status History

Submitted 10/15/2018 APPLICANT
Assigned to Plan Check Engineer 10/26/2018 ABDUL CHEGENI
Corrections Issued 10/29/2018 ABDUL CHEGENI
Quality Review Completed 11/1/2018 STEVEN KIM
Building Plans Picked Up 11/6/2018 APPLICANT
Applicant returned to address corrections 1/17/2019 ABDUL CHEGENI
Applicant returned to address corrections 10/8/2019 ABDUL CHEGENI
Applicant returned to address corrections 12/4/2019 ABDUL CHEGENI
Plan Check Approved 1/23/2020 ABDUL CHEGENI
Issued 7/23/2020 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 9/16/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/16/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/23/2019 ROBYN STEELE
Grading Pre-Inspection Cleared 1/23/2020 ABDUL CHEGENI
Miscellaneous Cleared 1/23/2020 ABDUL CHEGENI

Contact Information

Contractor Crystal Water Pools Plastering; Lic. No.: 1012751-C53 150 HOLGATE STREET      LA HABRA, CA 90631
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Ramirez,, Cesar Raul; Lic. No.: L9266 5872 DARLINGTON AVE      BUENA PARK, CA 90621
Engineer Upasani,, Mohan B; Lic. No.: GE2301 20 SOVENTE      IRVINE, CA 92606

Inspector Information

BRIAN MILLER, (818) 374-4359 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/29/2020 Corrections Issued TIMOTHY POWELL
Excavation 8/26/2020 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 8/27/2020 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 10/29/2020 Not Ready for Inspection TIMOTHY POWELL
Excavation 11/12/2020 Approved TIMOTHY POWELL
Rough 11/20/2020 Partial Inspection TIMOTHY POWELL
Rough 12/14/2020 No Access for Inspection TIMOTHY POWELL
Bottom/Toe 12/16/2020 Approved TIMOTHY POWELL
Excavation 12/29/2020 Partial Inspection TIMOTHY POWELL
Excavation 2/19/2021 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 3/2/2021 Partial Inspection TIMOTHY POWELL
Fill/Backfill 3/19/2021 Not Ready for Inspection TIMOTHY POWELL
Fill/Backfill 4/16/2021 Approved ALEXANDER HELFER
Fill/Backfill 11/12/2021 Corrections Issued CHARLES POWELL
Sub-Drain 1/21/2022 Corrections Issued BRIAN MILLER