1401 S GRAND AVE 90015

Certificate Information: 1401 S GRAND AVE 90015

Application / Permit
18030-10001-04398
Plan Check / Job No.
B21LA01750
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
Supplemental permit to 18030-10000-04398 for flatwork: driveways, vehicle turnaround, and curbs. See comments.
Permit Issued
Issued on 7/18/2022
Issuing Office
Metro
Current Status
Permit Finaled on 3/6/2025

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 ALBERT SERVIN
Corrections Issued 2/1/2021 ALBERT SERVIN
Applicant returned to address corrections 8/16/2021 ALBERT SERVIN
Plan Check Approved 7/18/2022 ALBERT SERVIN
Issued 7/18/2022 APPLICANT
Permit Finaled 3/5/2025 JONATHAN HOM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2021 PAMELA TENEZA
Miscellaneous Cleared 12/10/2021 DANIEL CORONADO
Redevelopment Project Area Cleared 4/22/2022 GRACIELA ACOSTA
Watercourse Cleared 5/25/2022 TERRY PHAN
Construction within easement Cleared 7/8/2022 WALTER RAMIREZ

Contact Information

Contractor Swinerton Builders; Lic. No.: 92-B 2001 CLAYTON RD   7TH FLOOR LEGAL    CONCORD, CA 94520
Engineer , ; Lic. No.: GE3051       ,
Engineer Nevius, David Benjamin; Lic. No.: C65015 3890 MURPHY CANYON ROAD STE 200      SAN DIEGO, CA 92123

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/3/2022 Partial Inspection MATTHEW JENKINS
Initial Grading 8/5/2022 Partial Inspection MATTHEW JENKINS
Initial Grading 1/30/2023 Not Ready for Inspection JONATHAN HOM
Rough 1/30/2023 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 2/7/2023 Partial Inspection JONATHAN HOM
Final 2/7/2023 Partial Inspection JONATHAN HOM
Rough 2/7/2023 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 5/31/2023 Partial Approval JONATHAN HOM
Rough 6/14/2023 Partial Inspection JONATHAN HOM
Final 7/17/2023 Partial Inspection JONATHAN HOM
Rough 7/17/2023 Partial Inspection JONATHAN HOM
Bottom/Toe 7/26/2023 Partial Approval RUSSELL BONVOULOIR
Final 7/26/2023 Partial Inspection RUSSELL BONVOULOIR
Rough 7/26/2023 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 8/15/2023 Partial Inspection JONATHAN HOM
Deputy Other (see comments) 12/14/2023 Approved JONATHAN HOM
Drainage Devices/Catch Basin 12/14/2023 Partial Approval JONATHAN HOM
Sub-Drain 12/14/2023 Partial Inspection JONATHAN HOM
Deputy Other (see comments) 12/15/2023 Approved JONATHAN HOM
Drainage Devices/Catch Basin 12/18/2023 Partial Approval JONATHAN HOM
Sub-Drain 12/18/2023 Partial Inspection JONATHAN HOM
Deputy Other (see comments) 12/19/2023 Approved JONATHAN HOM
Drainage Devices/Catch Basin 2/13/2024 Conditional Approval JONATHAN HOM
Rough 3/21/2024 Partial Inspection JONATHAN HOM
Rough 10/1/2024 Approved ALEXANDER HELFER
Deputy Other (see comments) 10/4/2024 Conditional Approval RUSSELL BONVOULOIR
Bottom/Toe 12/5/2024 Partial Inspection JONATHAN HOM
Final 12/5/2024 Not Ready for Inspection JONATHAN HOM
Deputy Other (see comments) 2/28/2025 Approved JONATHAN HOM
Bottom/Toe 3/5/2025 Approved JONATHAN HOM
Final 3/5/2025 Permit Finaled JONATHAN HOM