7101 W FOOTHILL BLVD 91042
Certificate Information: 7101 W FOOTHILL BLVD 91042
- Application / Permit
- 18030-10000-08723
- Plan Check / Job No.
- B18LA27445
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- site grading for new carwash, cut (79CY), fill 115 CY, inport 36 cy
- Permit Issued
- Issued on 7/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/5/2021
Permit Application Status History
| Submitted | 12/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | CHON CHIO KUO |
| Corrections Issued | 2/12/2019 | CHON CHIO KUO |
| Quality Review Completed | 2/13/2019 | STEVEN KIM |
| Building Plans Picked Up | 2/15/2019 | APPLICANT |
| Plan Check Approved | 1/16/2020 | CHON CHIO KUO |
| Issued | 7/23/2020 | APPLICANT |
| Permit Finaled | 11/2/2021 | TIMOTHY POWELL |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/24/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| ZA Case | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| Grading Pre-Inspection | Cleared | 1/16/2020 | CHON CHIO KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ibrahim,, Wael Suliman; Lic. No.: C48336 | 1517 EAST MCFADDEN AVE SANTA ANA, CA 92618 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 7/24/2020 | Conditional Approval | KIRK LINKLATER |
| Deputy Other (see comments) | 9/24/2020 | Partial Approval | TIMOTHY POWELL |
| Deputy Other (see comments) | 12/10/2020 | Partial Approval | TIMOTHY POWELL |
| Bottom/Toe | 6/8/2021 | Approved | KIRK LINKLATER |
| Final | 6/8/2021 | Corrections Issued | KIRK LINKLATER |
| Rough | 6/8/2021 | Approved | KIRK LINKLATER |
| Final | 6/30/2021 | Corrections Issued | MANUEL TEJADA |
| Approved Compaction Report | 8/11/2021 | Corrections Issued | BRIAN MILLER |
| Approved Compaction Report | 9/13/2021 | Approved | BRIAN MILLER |
| Final | 11/2/2021 | Permit Finaled | TIMOTHY POWELL |